Utility Dockets and Filings

Draft Decision

Files2

Words on different pages
Every word of Eversource rate increase is in the text below, but not all on one page. Pages with any of them are listed and highlighted. Clear highlighting
Words on different pages
  1. Page 9 of 31

    Docket No. 26-08-04 Page 7 ratepayer impact of a price cap increase, the identified changes in project costs justify an increase to the price cap. Id. 2. Authority Analysis The Year 8 SCEF price cap shall be $179.00/MWh, consistent with the NRES large buy-all price cap recommended for the 2027 NRES procurement. See Motion No. 4, July 29, 2026, Docket No. 26-08-03, Annual Non-Residential Renewable Energy Solutions Program Review – Year 6, p. 2. Maintaining a price cap equal to the NRES large buy-all price cap is consistent with the approach adopted by the Authority in the Year 7 SCEF annual review. Year 7 Decision, p. 10. In that proceeding, the Authority established equal price caps for the SCEF Program and the NRES large buy-all category because of the potential for interprogram competition. Id. The project sizes and market participants in the two programs are sufficiently similar to warrant continued consideration of this potential competition. Maintaining aligned price caps also provides a consistent framework for developers evaluating the two procurement opportunities. The SCEF and NRES Programs are not identical, and developers may consider a variety of factors when determining which program to pursue. Nevertheless, certain characteristics of the SCEF Program may provide economic advantages relative to NRES large buy-all projects. Unlike NRES projects, SCEF projects do not require a host customer with an electric bill or a beneficial account. See Motion No. 5, July 30, 2026, Docket No. 26-08-03, Att. 2a, pp. 4, 8. As a result, SCEF developers do not face the same customer acquisition and engagement requirements or the expectation to share tariff-related benefits with a host customer or beneficial account. These differences may lower the costs of developing a SCEF project relative to a comparable NRES large buyall project. Accordingly, a higher price cap for SCEF projects, relative to comparable NRES large buy-all projects, is not justified. A $179.00/MWh price cap is below the highest selected SCEF bid price from the prior procurement, which was $182.93/MWh. See DEEP Compliance, Sept. 1, 2026, p. A2. The $182.93/MWh bid was one cent below the Year 7 price cap of $182.94/MWh. Year 7 Decision, p. 11. Therefore, establishing a $179.00/MWh price cap would exclude bids between $179.00/MWh and $182.93/MWh that otherwise could have been eligible for selection. However, the Year 7 selection results demonstrate that most selected projects — specifically, nine2 out of 13, or approximately 69% — were bid below $179.00/MWh. In Eversource’s service territory, the median selected bid price was $161.30/MWh and the average selected bid price was $171.09/MWh, with the lowest selected bid at $143.95/MWh. See Motion No. 6, May 15, 2026, Docket No. 25-08-04, Att. B. In addition, two qualified but unselected bids were below $179.00/MWh, at $172.80/MWh and $177.80/MWh, respectively. Id. Thus, a $179.00/MWh price cap remains above both the median and average selected bid prices in Eversource’s Year 7 procurement and above two qualified bids that were not selected. By setting the price 2 Including the solar canopy project, which is eligible to bid above the price cap provided that its evaluated bid price is below the cap. Specifically, one Eversource solar canopy project submitted a bid of $274.15/MWh, but its evaluated bid price of $164.49/MWh was below $179.00/MWh. See Motion No. 6, May 15, 2026, Docket No. 25-08-04, Att. B
  2. Page 10 of 31

    Docket No. 26-08-04 Page 8 cap below the Year 7 level but above the evaluated bid prices of most projects selected in that procurement, the Authority can limit payments for higher-cost projects while preserving opportunities for lower-cost projects to participate. Given the Program’s fixed budget, lowering the average price paid per unit of capacity could also enable the Program to procure more MW within the available budget. The Year 7 results in UI’s service territory warrant additional consideration because selected bid prices were substantially closer to the existing price cap. In the first Year 7 solicitation round, the median selected bid price was $182.93/MWh and the average selected bid price was $182.58/MWh. See Motion No. 7, June 18, 2026, Docket No. 25-08-04, Att. B. Nevertheless, these results do not establish a need to maintain the higher $182.94/MWh price cap. Unlike Eversource’s solicitation, in which eight qualified bids were not selected or withdrawn, all three qualified UI bids were selected. Id.; Motion No. 6, May 15, 2026, Docket No. 25-08-04, Att. B. In addition, only two companies participated in the UI solicitation, compared with nine companies participating in the Eversource solicitation. Id. The limited number of bids and bidders in UI’s solicitation reduced the competitive pressure on bid prices. Accordingly, the Authority cannot conclude from the Year 7 UI results that a price cap of $179.00/MWh would have resulted in insufficient participation or materially different procurement outcomes. The Authority also considered the potential effects of federal actions, including tariffs, on solar project costs. Such actions may increase development costs and, in turn, affect future SCEF bid prices. However, the Authority accounted for significant federal policy uncertainty in last year’s price cap determination, when it increased the SCEF price cap from $133.00/MWh to $182.94/MWh, an increase of approximately 37.55% in a single year. Year 7 Decision, pp. 7–11. The record in this proceeding does not establish that subsequent federal actions have increased costs to a level that would render either the current price cap of $182.94/MWh, or a modestly reduced price cap of $179.00/MWh, economically unviable for project development. Rather, the record establishes only that costs may increase. Moreover, the magnitude and duration of the effects of federal trade and tax policies remain uncertain. The Authority is also concerned that, given the Program’s fixed budget, increasing the price cap without a corresponding increase in funding could reduce the amount of capacity ultimately selected if developers respond by submitting bids closer to the higher cap. The Authority therefore declines to increase the price cap based on potential future cost impacts that remain speculative or are not sufficiently supported by quantitative analysis. The Year 8 SCEF price cap shall be set at $179.00/MWh, consistent with the recommended NRES large buy-all price cap. This price cap appropriately balances the objectives of facilitating continued SCEF participation, maintaining consistency between the SCEF and NRES large buy-all procurements, and limiting unnecessary procurement costs to ratepayers. C. BUDGET REALLOCATION 1. Background For the Year 7 procurement, the Authority adopted separate budget caps for each EDC, pursuant to General Statutes §§ 16-244z(c)(1)(A) and 16-244z(c)(1)(B). Year 7
  3. Page 11 of 31

    Docket No. 26-08-04 Page 9 Decision, pp. 8–9. Specifically, the approved 2026 SCEF budget caps were $9,864,750.81 for Eversource and $5,709,894.63 for UI. Id., p. 10. However, these allocations do not reflect the typical 80/20 allocation between the EDCs based on their respective shares of statewide electric revenues. Rather, the approved values reflected the projected payment obligations associated with projects selected during the Year 5 procurement. Unlike Eversource, UI selected a fuel cell project during the Year 5 procurement. Year 7 Decision, p. 9, fn. 5. Because fuel cell projects generally operate at higher capacity factors than conventional solar projects, UI’s resulting SCEF budget allocation exceeded the amount that would have resulted under the standard 80/20 revenue-based allocation methodology. Id. Importantly, following the enactment of Public Act 25-173, fuel cells that emit pollutants are no longer eligible for participation in the SCEF Program.3 Therefore, the Authority requested stakeholder comment on whether the combined SCEF budget of $15,574,645.44 should be reallocated between the EDCs using the standard 80/20 revenue-based allocation methodology. Id. Under such an approach, the resulting allocations would be $12,459,716.35 for Eversource and $3,114,929.09 for UI. Id. 2. Stakeholder Comments The EDCs opposed reallocating the Year 8 SCEF budget using the standard 80/20 revenue-based allocation methodology. EDC Comments, Sept. 11, 2026, p. 4. The EDCs argued that the methodology adopted last year better controls SCEF Program costs because it reflects the EDCs’ actual payment obligations. Id., p. 5. The EDCs noted that increasing Eversource’s allocation under an 80/20 methodology would increase Eversource’s available budget by approximately $2.6 million without a corresponding change in the underlying project compensation obligations used to establish the current budget. Id. The EDCs therefore asserted that reallocating the budget would be inconsistent with the cost-control methodology used to establish the existing EDC-specific allocations. Id. DEEP, in contrast, supported reallocating the SCEF budget using the standard 80/20 revenue-based allocation methodology. DEEP Comments, Sept. 14, 2026, p. 1. DEEP noted that UI received sufficient bids to utilize less than half of its available budget, resulting in UI initiating a second procurement round. Id., pp. 1–2. In contrast, DEEP stated that Eversource received substantially more eligible bids than it could accept, even after increasing its original $9,864,750.81 budget by $3,082,758.17 to account for previously selected projects that were terminated. Id., p. 2. Accordingly, DEEP argued that allocating $12,459,716.35 to Eversource and $3,114,929.09 to UI for Year 8 would produce a procurement outcome similar to that of the Year 7 Round 1 solicitation. Id. OCC supported reallocating the total 2027 SCEF budget of $15,574,645.44 between the EDCs using the standard 80/20 revenue-based methodology. OCC Comments, Sept. 14, 2026, p. 2. OCC noted that UI’s elevated Year 7 budget allocation 3 The Authority clarifies that not all fuel cells are ineligible for the Program; rather, only fuel cells that emit pollutants are ineligible. See DEEP Comments, Sept. 14, 2026, p 2.
  4. Page 12 of 31

    Docket No. 26-08-04 Page 10 resulted from the selection of a single fuel cell project, which would no longer be eligible for the Program following changes to fuel cell eligibility. Id. OCC argued that, given UI’s comparatively urban service territory, maintaining the current allocation creates a risk that a meaningful portion of the final-year budget will remain unutilized. Id. OCC further stated that General Statutes § 16-244z(c)(1)(A) provides the Authority with discretion to adjust procurement parameters to maintain a competitive and efficient Program, including for purposes of reallocating the Year 8 budget. Id. If the Authority reallocates the budget, OCC emphasized that the combined budget cap should remain unchanged because that cap provides the operative protection for nonparticipating ratepayers. OCC Comments, Sept. 14, 2026, p. 3. Andover Energy supported changing the Year 8 SCEF budget to the standard 80/20 allocation between Eversource and UI. Andover Energy Corresp., Sept. 14, 2026, p. 1. Andover Energy noted the change in fuel cell eligibility and argued that an 80/20 allocation would provide the Year 8 solicitation with a greater opportunity to procure renewable energy capacity at cost-effective rates while reducing the risk that budget capacity remains unutilized during the final Program year. Id. Verogy likewise supported reallocating the SCEF budget to an 80/20 Eversource/UI split. Verogy Comments, Sept. 14, 2026, p. 2. Verogy argued that an 80/20 allocation would provide additional funding for viable SCEF projects in Eversource’s geographically larger service territory without adversely affecting the viability of SCEF projects in UI’s service territory, which Verogy noted was undersubscribed in the Year 7 spring procurement. Id., pp. 2–3. Verogy also recommended that any unused Program budget or capacity following the Year 7 procurement be allocated using an 80/20 methodology rather than allowing unused UI capacity from Year 7 to roll forward exclusively into UI’s Year 8 allocation. Id., p. 3. Allco supported a hybrid approach to the Year 8 budget allocation. Allco Comments, Sept. 14, 2026, p. 2. Allco argued that the Authority should initially maintain the existing budget allocation methodology rather than reset the allocation to 80/20. Id. Allco asserted that maintaining the existing allocation would preserve UI customers’ opportunity to participate in the SCEF Program. Id. However, Allco recommended that, after UI’s Year 8 awards are finalized, any remaining unused UI budget be transferred to Eversource. Id. Save the Sound similarly supported maintaining the current EDC-specific budget allocations rather than immediately reallocating the budget to an 80/20 split. Save the Sound Comments, Sept. 14, 2026, p. 3. Save the Sound based its position on historical data indicating that project bids in UI’s service territory have generally been higher on a $/MWh basis than bids in Eversource’s service territory. Id. Save the Sound argued that, to the extent the Authority seeks to maintain an 80/20 allocation of Program capacity between the EDC service territories, a proportionately larger budget for UI may be necessary because of those higher bid prices. Id. Save the Sound nevertheless recognized the difference in bid volume between the EDCs, noting that UI has historically received fewer bids than Eversource. Id., pp. 3–4. To address the potential for unused Program capacity or budget, Save the Sound recommended a “blended” or hybrid approach. Save the Sound Comments, Sept. 14,
  5. Page 13 of 31

    Docket No. 26-08-04 Page 11 2026, p. 4. Specifically, Save the Sound recommended that, following the initial Year 8 awards, any unused UI budget or capacity be made available to the next eligible projects in the Eversource bid queue. Id. Save the Sound argued that this approach would preserve sufficient budget for UI to meet its allocated procurement commitments while reducing the risk that unused UI budget or capacity remains stranded in the final Program year. Id. 3. Authority Analysis Consistent with the recommendations of OCC, DEEP, Andover Energy, and Verogy, the 2027 SCEF budget shall be reallocated using the standard 80/20 split based on the EDCs’ respective shares of statewide electric revenues. The aggregate 2027 SCEF budget will not increase as a result of this reallocation. The 63/37 Eversource/UI allocation established for the prior program year was based on circumstances that are not representative of current SCEF procurements. As discussed earlier, UI selected a fuel cell project during the Year 5 procurement. Year 7 Decision, p. 9, fn. 5. That fuel cell project, which had a higher capacity factor than typical solar projects, accounted for approximately $4.32 million, or 76%, of the annual subscriber organization payments associated with UI’s 2024 procurement, which was the solicitation year used to establish the EDC-specific budgets for the prior Program year. See Motion No. 9, May 13, 2024, Docket No. 23-08-04, Att. B; Year 7 Decision, pp. 8–9. Thus, the higher UI budget allocation was driven primarily by the payment obligations associated with a single fuel cell project, rather than by greater demand for SCEF projects in UI’s service territory. Because fuel cells that emit pollutants are no longer eligible for the SCEF Program, the circumstances underlying that allocation are unlikely to recur in future SCEF procurements. An 80/20 allocation more appropriately aligns responsibility for SCEF Program costs with the EDCs’ respective shares of statewide electric revenues. The Authority finds this approach preferable to continuing to base the EDC-specific allocations on a historical procurement containing an atypical project. Maintaining a budget allocation that materially differs from the EDCs’ respective shares of statewide electric revenues without a corresponding current-year basis could result in one EDC’s customers bearing a greater or lesser share of Program costs than would otherwise be reflected by that EDC’s share of statewide electric revenues. Reallocating the budget to 80/20 therefore provides a more consistent and equitable basis for allocating the aggregate Program budget between the EDCs. The 80/20 allocation is also consistent with the existing allocation of SCEF procurement capacity between the EDCs. The Program currently provides for 40 MW of capacity in Eversource’s service territory and 10 MW in UI’s service territory, representing an 80/20 allocation. Decision, Docket No. 25-08-01, 2025 Clean and Renewable Energy Program Data and Report, Att. 1, p. 36. Reallocating the budget to the same proportion therefore does not alter the existing relative allocation of Program capacity between the EDCs. Rather, it aligns the available budget associated with that capacity with the existing 80/20 Program structure.
  6. Page 14 of 31

    Docket No. 26-08-04 Page 12 Finally, maintaining the existing 63/37 budget allocation could result in a meaningful portion of the final-year SCEF budget remaining underutilized. UI’s comparatively urban service territory may limit the availability of developable sites for SCEF projects and, as a result, may contribute to lower solicitation interest than in Eversource’s service territory. The first Year 7 solicitation round illustrates this difference. Only 7.49 MW of the 10 MW allocated to UI was selected, leaving approximately 2.51 MW unallocated. Motion No. 6, May 15, 2026, Docket No. 25-08-04, Att. B. In contrast, Eversource received substantially more bid interest than its available budget could accommodate. Eversource received approximately $23 million in eligible bids compared with approximately $13 million in available budget after accounting for terminated projects. EDC Corresp., Sept. 14, 2026, p. 3; Motion No. 6, May 15, 2026, Docket No. 25-08-04, Att. B. The difference in solicitation interest is particularly significant because Year 8 is the final year of the SCEF Program. If the existing EDC-specific budget allocations are maintained, unused UI budget capacity may remain unavailable for projects in Eversource’s service territory despite substantially greater demonstrated demand there. This creates a risk that available Program funds will not be fully utilized and that the finalyear procurement will result in fewer projects being selected than could otherwise be supported within the aggregate Program budget. The Authority therefore finds that the Year 8 solicitation results provide an additional basis for aligning the EDC-specific budgets with the 80/20 allocation. The Authority also considered the alternative proposal advanced by Allco and Save the Sound, under which the Authority would initially retain the existing 63/37 allocation and subsequently make any unused UI budget available to Eversource following completion of the UI solicitation. This approach could preserve the existing level of funding available to UI while reducing the risk that any unused UI budget remains stranded at the conclusion of the final procurement. However, the Authority declines to adopt this approach. First, depending on the level of UI participation, transferring all unused UI budget to Eversource could result in Eversource ultimately receiving more than 80% of the aggregate Program budget. Such an outcome would depart from the standard 80/20 allocation that the Authority finds appropriate for Year 8. Second, a subsequent transfer would require an additional allocation process following completion of the UI solicitation and could create administrative and implementation issues for the EDCs. The Authority finds it preferable to establish the appropriate EDC-specific allocations at the outset of the final procurement rather than rely on a subsequent transfer mechanism. The Authority emphasizes, however, that reallocating the EDC-specific budgets does not increase the aggregate SCEF budget; rather, it changes only the allocation of the existing budget among the EDCs. Accordingly, the reallocation will not increase total ratepayer costs for the Program on a statewide basis. Finally, the Authority reiterates that the EDC-specific budget allocations are hard caps. The EDCs shall not exceed their respective allocations under any circumstances, after accounting for unused, terminated, withdrawn, or reduced-size projects. During the Year 7 solicitation, Eversource exceeded its budget by $6,195.97, which resulted in the Authority directing Eversource to subtract that amount from its Year 8 budget. Motion No. 6 Ruling, May 26, 2026, Docket No. 25-08-04, pp. 2–3. That determination remains
  7. Page 15 of 31

    Docket No. 26-08-04 Page 13 unchanged. To maximize utilization of the available budget without exceeding the applicable cap, the EDCs should consider making partial awards as an EDC approaches its full budget allocation, provided the applicant agrees to accept a partial award. Accordingly, the Authority reallocates the $15,574,645.44 SCEF budget to an 80/20 Eversource/UI split. This results in an initial allocation of $12,459,716.35 for Eversource and $3,114,929.09 for UI. After accounting for the $6,195.97 amount by which Eversource exceeded its Year 7 budget, Eversource’s Year 8 allocation is reduced to $12,453,520.38. The resulting Year 8 SCEF budget allocations are shown in Table 1 below. Table 1: SCEF Program Annual Budget Caps D. Year Eversource UI Total 2026 2027 $9,864,750.81 $12,453,520.38 $5,709,894.63 $3,114,929.09 $15,574,645.44 $15,568,449.47 BID PREFERENCES The Authority also conducts an annual review of the SCEF Program’s bid preferences. As part of its Year 8 review, the Authority solicited stakeholder input on the appropriate bid preferences for the Year 8 procurement. Notice, Aug. 25, 2026, p. 3. Stakeholders were encouraged to support any proposed changes with analyses of potential ratepayer impacts, effects on stakeholder participation and project diversity, and consistency with the Program Objectives. Id. 1. Stakeholder Comments The EDCs supported maintaining the existing bid preferences for Year 8: 40% for solar canopies and 20% for landfills or brownfields. EDC Comments, Sept. 11, 2026, p. 5. The EDCs argued that the existing preferences appropriately balance the policy objectives of encouraging development on preferred sites with maintaining cost-effective and competitive procurement outcomes. Id., p. 6. The EDCs further asserted that the existing preference levels have demonstrated their ability to support participation from preferred site types, noting that six solar canopy projects were selected in the prior two procurements. Id. DEEP recommended maintaining the bid preference categories and levels used in Year 7 for Year 8. DEEP Compliance, Sept. 1, 2026, pp 3–4. DEEP stated that maintaining the existing bid preferences would balance the cost-effectiveness of the Program with the environmental and ratepayer benefits associated with developing projects on preferred sites. Id., p. 4. OCC supported maintaining the existing bid preference categories and levels for Year 8. OCC Comments, Sept. 14, 2026, p. 3. OCC stated that bid preferences are appropriate to the extent they are necessary for the Program to achieve its objectives. Id. OCC also opposed establishing new bid preference categories in the final Program year, arguing that introducing new bid preferences at this stage would provide neither bidders nor the Authority with a sufficient basis to evaluate their effects. Id.
  8. Page 16 of 31

    Docket No. 26-08-04 Page 14 Andover Energy recommended retaining the bid preferences adopted for Years 6 and 7. Andover Energy Corresp., Sept. 14, 2026, p. 1. Andover Energy argued that the existing bid preference levels provide preferred site types with an opportunity to participate in the SCEF Program while maintaining rates that are reasonable for ratepayers. Id. Save the Sound supported maintaining the Year 7 bid preference levels for Year 8. Save the Sound Comments, Sept. 14, 2026, p. 4. Save the Sound noted that one landfill project was selected in the Year 8 procurement and that the project also represented the second-lowest evaluated bid in Eversource’s service territory. Id. Save the Sound argued that this result indicates that the existing 20% landfill/brownfield preference is sufficient to facilitate participation by landfill projects and that the limited number of other landfill or brownfield projects may be attributable to factors other than the bid preference amount. Id. Save the Sound also noted that two solar canopy bids were submitted in the Year 8 procurement, one of which was selected, and argued that this result supports maintaining the existing 40% solar canopy preference. Id., p. 5. Verogy likewise supported maintaining the existing bid preference levels for Year 8. Verogy Comments, Sept. 14, 2026, p. 3. Verogy additionally recommended permitting landfill and brownfield projects to bid above the price cap, similar to the treatment of solar canopy projects. Id., pp. 3–4. Verogy argued that this change would streamline the SCEF Program’s design and asserted that the existing general price cap has become prohibitive for development of projects on landfill and brownfield sites. Id. 2. Authority Analysis Consistent with the broad stakeholder support for maintaining the existing bid preferences, the SCEF bid preference categories and amounts shall remain unchanged for Year 8. Maintaining the existing 20% bid preference for landfill and brownfield projects and the 40% bid preference for solar canopy projects appropriately balances the objectives of encouraging development on preferred sites with the need to maintain a competitive and cost-effective procurement, particularly as the SCEF Program enters its final year. The Year 7 procurement results provide evidence that the existing bid preference amounts can support the development of preferred-site projects. In Eversource’s Year 7 procurement, one landfill project and one solar canopy project were selected. See Motion No. 6, May 15, 2026, Docket No. 25-08-04, Att. B. Moreover, the selected solar canopy project ranked seventh among the 10 selected projects based on evaluated bid price, while the selected landfill project had the second-lowest evaluated bid price. Id. Thus, the results demonstrate that projects receiving the existing bid preferences can remain competitive with other SCEF projects under the current procurement structure. Only one landfill project and one solar canopy project were selected; no additional brownfield, landfill, or solar canopy projects were selected in the Year 7 procurements. However, the limited number of selected preferred-site projects does not, by itself, establish that the existing bid preference amounts are insufficient to support development of those project types. The number of projects available for selection may also be affected
  9. Page 17 of 31

    Docket No. 26-08-04 Page 15 by the availability of suitable sites, the development characteristics and costs associated with individual sites, the number of developers pursuing such projects, and developers’ relative preference for developing preferred-site projects versus less complex standard projects. The Authority therefore does not find sufficient evidence in the Year 7 results to conclude that a change in the existing bid preferences is warranted. Maintaining the existing bid preferences also promotes stability and predictability as the SCEF Program enters its final year. The existing preferences have been in place for multiple years, and the Year 7 procurement provides recent evidence regarding their operation. Introducing new bid preference categories or materially changing existing preference amounts in the final Program year could create additional uncertainty for developers and make it more difficult to assess the effects of those changes within the remaining procurement period. The Authority considered Verogy’s proposal to permit landfill and brownfield projects to bid above the price cap in a manner similar to solar canopy projects. There is potential merit in evaluating whether the treatment of the various bid preference categories should be more consistent. However, the Authority does not believe that such a substantive change to the bid preferences is appropriate in the final year of the SCEF Program. Instead, the issue may be more appropriately considered in Docket No. 26-0604, Implementation of Clean Energy Successor Programs, as the Authority develops the successor NRES and SCEF Programs. Accordingly, the Authority determines that the SCEF bid preference categories and amounts for Year 8 shall remain unchanged from Year 7. The applicable bid preference categories and amounts are shown in Table 2 below. Table 2: SCEF Program Bid Preferences Preference Type E. Preference Amount Solar Canopy4 40% Landfills or Brownfield 20% PROGRAM DOCUMENTS 1. EDC Proposed Changes Order No. 13 of the Year 7 Decision requires the EDCs to file, by September 1 each year, the current SCEF Program Requirements and all RFP documents “proposing modifications, as necessary and appropriate.” Year 7 Decision, p. 19. In compliance with this directive, the EDCs filed Motion No. 2 on August 31, 2026, which includes updated 4 As determined by the Year 5 Decision, solar canopies may submit bids above the price cap, provided that the final bid price, inclusive of the bid preference, does not exceed the price cap. See Year 5 Decision, pp. 12–13.
  10. Page 18 of 31

    Docket No. 26-08-04 Page 16 SCEF Program documents, including a revised Program Manual. See Motion No. 2, Aug. 31, 2026. The EDCs did not propose substantive changes to the SCEF Program documents, citing the maturity of the SCEF Program and its entry into its final year. Motion No. 2, Aug. 31, 2026, p. 1; EDC Comments, Sept. 11, 2026, p. 7. The EDCs stated that the revisions proposed in Motion No. 2 are limited to addressing instances of inconsistency and ambiguity in the existing Program documents and are not intended to modify the underlying Program structure or requirements. EDC Comments, Sept. 11, 2026, p. 7. When commenting on the proposed changes, OCC requested, among other things, that the Authority clarify how unused budget or MW allocations will be treated at the conclusion of the Program’s final year, including whether such funds will lapse or be addressed through successor programs. OCC Comments, Sept. 14, 2026, p. 3. The Authority finds that the EDCs’ proposed revisions are limited in scope and are primarily intended to improve consistency among the Program documents and clarify existing requirements. Accordingly, except as otherwise addressed in this Decision, the Authority approves the redline changes proposed by the EDCs, thereby granting Motion No. 2 with modification. The Authority also notes that the revised Program documents provide that any unallocated Program budget will expire and will not roll over into a subsequent Program year. Motion No. 2, Aug. 31, 2026, Att. 1, p. 11. This provision addresses OCC’s request for clarification regarding the treatment of unused Program budget following the final SCEF procurement. 2. DEEP Proposed Changes Order No. 15 of the Year 7 Decision requires DEEP to file, annually by September 1, proposed changes to Appendix B of the SCEF Program Manual. Year 7 Decision, p. 19. In compliance with this directive, DEEP submitted proposed revisions to Appendix B. See DEEP Compliance, Sept. 1, 2026. DEEP characterized its proposed modifications as minimal and stated that none of the proposed changes impose additional burdens on bidders. Id., p. 4. DEEP indicated that most of the proposed revisions are intended to clarify existing requirements. Id. For example, DEEP proposed revisions specifying that bidders must provide the full 11-digit census tract number; confirming that Appendix B submissions are due to DEEP by the date and time established by the EDCs in their SCEF RFP; adding a new section addressing Freedom of Information Act (FOIA) exemptions; and revising the Veracity of Statement Affidavit to clarify that the affiant refers to an individual bid rather than a batch of bids submitted by the same developer. Id., pp. 4–5. The Authority finds that DEEP’s proposed changes are limited in scope, primarily clarify existing requirements, and do not introduce new barriers to participation. Accordingly, the Authority approves the redlined changes proposed by DEEP that are not otherwise impacted by other sections of this Decision.
No matches

As listed on the current system

Draft Decision, 10/19/2026 [26-08-04]