    STATE OF CONNECTICUT PUBLIC UTILITIES REGULATORY AUTHORITY TEN FRANKLIN SQUARE NEW BRITAIN, CT 06051 DOCKET NO. 26-08-05 ANNUAL ENERGY STORAGE SOLUTIONS PROGRAM REVIEW – YEAR 6 October 29, 2026 PROPOSED DECISION This proposed Decision is being distributed to the participants in this proceeding for comment. The proposed Decision is not final. The Authority will consider the participants’ arguments and exceptions before reaching a final Decision, which may differ from the proposed Decision. Therefore, this proposed Decision does not establish any precedent and does not necessarily represent the Authority’s final conclusion.
  2. Page 2 of 69

    TABLE OF CONTENTS I. INTRODUCTION ........................................................................................... 1 A. B. C. D. SUMMARY ................................................................................................. 1 BACKGROUND OF THE PROCEEDING............................................................ 1 CONDUCT OF THE PROCEEDING .................................................................. 2 PARTIES AND INTERVENORS OR PARTICIPANTS ............................................ 2 II. LEGAL AUTHORITY ..................................................................................... 3 III. PROGRAM OBJECTIVES ............................................................................ 3 IV. AUTHORITY ANALYSIS ............................................................................... 4 A. PROGRAM OVERVIEW ................................................................................ 4 B. BIDIRECTIONAL EV PARTICIPATION ............................................................. 7 1. Background ..................................................................................... 7 2. Stakeholder Comments .................................................................. 8 3. Authority Analysis .......................................................................... 12 C. ENROLLMENT INCENTIVE CLAWBACK .......................................................... 23 1. Background ..................................................................................... 23 2. Stakeholder Comments .................................................................. 25 3. Authority Analysis .......................................................................... 28 D. FTM STORAGE TARIFF .............................................................................. 31 1. Background ..................................................................................... 31 2. Stakeholder Comments .................................................................. 32 3. Authority Analysis .......................................................................... 36 E. DATA DASHBOARD..................................................................................... 42 1. Background ..................................................................................... 42 2. Authority Analysis .......................................................................... 43 F. PROGRAM REDLINE AND RECOMMENDED CHANGES ..................................... 43 1. Performance Payment Frequency ................................................. 44 2. Change Orders ................................................................................ 45 3. Insurance Requirements ................................................................ 47 4. Add-on Storage ............................................................................... 47 5. Telemetry Data Audits..................................................................... 49 6. Miscellaneous ................................................................................. 51 7. Updated Documents ....................................................................... 51 V. CONCLUSION AND ORDERS ...................................................................... 52 A. CONCLUSION............................................................................................. 52 B. EXISTING AND NEW ORDERS ...................................................................... 52 1. Standing Orders to be filed in ESS Annual Review Dockets....... 52 2. New Orders ...................................................................................... 57
  3. Page 3 of 69

    PROPOSED DECISION I. INTRODUCTION A. SUMMARY The Public Utilities Regulatory Authority (Authority or PURA) approves updates to the Energy Storage Solutions Program (ESS Program or Program), administered by The Connecticut Light and Power Company d/b/a Eversource Energy (Eversource), The United Illuminating Company (UI; collectively, with Eversource, the electric distribution companies or EDCs), and the Connecticut Green Bank (CGB; collectively, with the EDCs, the Program Administrators). The approved changes are intended to better align the ESS Program with the Program’s objectives. B. BACKGROUND OF THE PROCEEDING On July 28, 2021, the Authority issued its Final Decision in Docket No. 17-1203RE03, PURA Investigation into Distribution System Planning of the Electric Distribution Companies – Electric Storage (Storage Decision) establishing a nine-year program to support electric storage in Connecticut, starting on January 1, 2022, and continuing through December 31, 2030, pursuant to Public Act No. 21-53 (PA 21-53) and Conn. Gen. Stat. §§ 16-11, 16-19, 16-19e, and 16-244i, and in accordance with the October 2, 2019 Interim Decision in Docket No. 17-12-03, PURA Investigation into Distribution System Planning of the Electric Distribution Companies (Equitable Modern Grid Decision). Public Act No. 26-127 § 6(a) subsequently extended the ESS Program through December 31, 2035, to align with Connecticut’s successor solar programs. The Authority annually reviews key ESS Program metrics, including deployed megawatts (MW), and makes strategic adjustments as necessary to support the Program’s objectives. Storage Decision, p. 43. Additionally, during the last year of each three-year Program cycle (e.g., 2024), “the Authority will conduct a full program review . . . including an evaluation of the existing program design to ensure that the Program is: (1) delivering on the expected value to Connecticut’s ratepayers; and (2) is meeting the Program Objectives.” Id., p. 44. The Authority conducted the first annual ESS Program review in Docket No. 2108-05, Annual Review of the Electric Storage Program – Year 1, issuing a Decision on December 8, 2021 (Year 1 Decision). The Decision reviewed the Year 1 Program design documents and other key compliance filings, and addressed other topics regarding Program implementation, to successfully execute the first year of the ESS Program beginning January 1, 2022. Additionally, the Authority conducted the second annual ESS Program review in Docket No. 22-08-05, Annual Energy Storage Solutions Program Review – Year 2, and issued a Decision on December 21, 2022 (Year 2 Decision). The Year 2 Decision
  4. Page 4 of 69

    Docket No. 26-08-05 Page 2 reviewed Year 1 deployment data and introduced several modifications to better align the Program with its objectives. The Authority conducted the third annual ESS Program review in Docket No. 2308-05, Annual Energy Storage Solutions Program Review – Year 3, and issued a Decision on November 29, 2023 (Year 3 Decision). The Year 3 Decision assessed Year 2 deployment data and approved additional changes to further enhance the Program’s alignment with its goals. The Authority conducted the fourth annual ESS Program review in Docket No. 2408-05, Annual Energy Storage Solutions Program Review – Year 4, and issued a Decision on December 4, 2024 (Year 4 Decision). The Year 4 Decision reviewed Year 3 deployment data and adopted further adjustments to improve alignment with Program’s objectives. Most recently, the Authority conducted the fifth annual ESS Program review in Docket No. 25-08-05, Annual Energy Storage Solutions Program Review – Year 5, and issued a Decision on December 17, 2025 (Year 5 Decision). The Year 5 Decision reviewed Year 4 deployment data and modified the Program’s compensation structure to place greater emphasis on performance-based incentives. C. CONDUCT OF THE PROCEEDING On March 26, 2026, the Authority issued the Notice of Proceeding in the abovecaptioned docket. On June 16, 2026, the Authority issued a Notice of Request for Written Comments on the following topics: (1) enrollment incentive clawback; and (2) front-of-the-meter (FTM) storage tariff. The Authority received eight sets of written comments from interested stakeholders on July 9, 2026. On August 7, 2026, the Authority held a Technical Meeting to discuss the topics outlined in the June 16, 2026 Notice of Request for Written Comments. On August 12, 2026, the Authority issued a second Notice of Request for Written Comments on the following topics: (1) recommended programmatic changes; and (2) bidirectional electric vehicle (EV) participation. The Authority received nine sets of written comments from interested stakeholders on or before August 28, 2026. On September 3, 2026, the Authority held a second Technical Meeting to discuss the topics outlined in the August 12, 2026 Notice of Request for Written Comments. On October 29, 2026, the Authority issued a Proposed Final Decision and provided an opportunity for docket Participants to file written exceptions. D. PARTIES AND INTERVENORS OR PARTICIPANTS A listing of all Participants to this proceeding is appended hereto as Appendix A.
  5. Page 5 of 69

    Docket No. 26-08-05 II. Page 3 LEGAL AUTHORITY The Authority was directed to “develop and implement one or more programs, and associated funding mechanisms, for electric storage resources connected to the electric distribution system.” General Statutes § 16-243ee (a). Pursuant to General Statutes §§ 16-243ee, 16-11, 16-19, 16-19e, and 16-244i (see Section II of the Storage Decision), the Authority established the Program through the Storage Decision. Furthermore, the Authority is permitted to select CGB, the Department of Energy and Environmental Protection (DEEP), the EDCs, a third party, or any combination thereof to implement and/or administer the Program. General Statutes § 16-243ee(d). The Authority indicated in the Storage Decision that it will initiate an annual docket to review key ESS Program metrics, to ensure that the Program is on track to meet its deployment targets. Storage Decision, p. 43. Herein, the Authority reviews the Program documents developed by the Program Administrators, relevant compliance filings, and current incentive rates to determine if and how the ESS Program should be modified to better align with the direction provided in the Storage Decision. III. PROGRAM OBJECTIVES In the Storage Decision, the Authority adopted the following seven objectives (Program Objectives) to guide the Program Administrators in the development and implementation of the Program: 1) Provide positive net present value to all ratepayers, or a subset of ratepayers paying for the benefits that accrue to that subset of ratepayers. 2) Provide multiple types of benefits to the electric grid, including, but not limited to, customer, local, or community resilience, ancillary services, peak shaving, and avoiding or deferring distribution system upgrades or supporting the deployment of other distributed energy resources. 3) Foster the sustained, orderly development of a state-based electric energy storage industry. 4) Prioritize delivering increased resilience to: (1) low- to moderate-income (LMI) customers, customers in environmental justice or economically distressed communities, customers coded for medical protection, and public housing authorities as defined in General Statutes § 8-39(b); (2) customers on the grid-edge who consistently experience more and/or longer than average outages during major storms; and (3) critical facilities as defined in General Statutes § 16-243y(a)(2). 5) Lower the barriers to entry, financial or otherwise, for electric storage deployment in Connecticut. 6) Maximize the long-term environmental benefits of electric storage by reducing emissions associated with fossil-based peaking generation. 7) Maximize the benefits to ratepayers derived from the wholesale capacity market.
  6. Page 6 of 69

    Docket No. 26-08-05 Page 4 Storage Decision, pp. 5–7. Accordingly, the Authority relied on the Program Objectives to guide its review of the Program Administrators’ compliance filings and in evaluating the current ESS Program design and assessing any possible changes to be ordered in this proceeding. The primary objective of the Authority’s review was to better align the ESS Program with the Program Objectives and the direction provided in the Storage Decision. “Key Annual Review filings shall be submitted on or around August 1st . . . including, but not limited to: an annual report, including Program results and recommendations for Program modifications as discussed in Section V.F.” Storage Decision, p. 43. The Authority reaffirms that the above-listed Program Objectives shall guide the Program Administrators in their administration of the ESS Program, particularly in instances not explicitly addressed through the approved ESS Program documents or through Authority direction in prior Decisions or motion rulings. Finally, the Authority reaffirms that the fourth Program Objective, prioritizing increased resilience, shall be explicitly guided by a goal of 40% deployment amongst low-income populations or in Distressed Municipalities, in line with the Justice 40 goal set in the Storage Decision. Storage Decision, p. 13. IV. AUTHORITY ANALYSIS A. PROGRAM OVERVIEW Public Act 21-53, codified as General Statutes § 16-243cc, established statewide energy storage deployment goals, namely: (1) 300 MW by December 31, 2024; (2) 650 MW by December 31, 2027; and (3) 1,000 MW by December 31, 2030. Further, PA 2153 § 2, codified as General Statutes § 16-243ee, directed the Authority to develop the Program authorized in the Storage Decision, while PA 21-53 § 3, codified as General Statutes § 16-243dd, authorized DEEP to competitively procure energy storage projects. The Authority subsequently established an ESS Program deployment target of 580 MW by the end of 2030 to help achieve these statewide targets. Storage Decision, p. 5. Pursuant to prior Authority Decisions, energy storage projects under the ESS Program are eligible for both enrollment and performance-based incentives, depending on customer type, as shown in Tables 2 and 3. Enrollment incentives vary based on whether the host customer is a grid-edge or non-grid-edge residential customer, or a priority commercial and industrial (C&I) customer. Performance-based incentives differ according to whether the customer is a standard, underserved, or low-income residential customer, or a small- and medium- or large-commercial customer. Energy storage increases the affordability, resilience, and reliability of the state’s electric grid, and can help reduce carbon emissions from the state’s power sector.
  7. Page 7 of 69

    Docket No. 26-08-05 Page 5 Table 1: Program Deployment Targets1 Customer Class Residential Commercial Total TOTAL 150 MW 430 MW 580 MW Year 4 Decision, p. 38. Table 2: ESS Enrollment Incentives Customer Type Incentive Amount Priority Commercial Non-Grid Edge Residential Grid Edge Residential $10/kWh $30/kWh $130/kWh Year 5 Decision, p. 29. Table 3: ESS Performance Incentives Customer Type Total Annual Incentive Amount Small & Medium Commercial $325/kW-year for Years 1–5; $175/kW-year for Years 6–10 $275/kW-year for Years 1–5; $175/kW-year for Years 6–10 Large Commercial $300/kW Standard Residential $450/kW Underserved Residential $550/kW Low-Income Residential Year 5 Decision, p. 29. 1 With the adoption of Construct 5, the Program no longer includes an automatic declining block incentive structure between tranches. Year 5 Decision, pp. 14, 21. Additionally, the Year 4 Decision reallocated the Program’s MW capacity from the original distribution approved in the Storage Decision, shifting residential MWs to the commercial segment. Year 4 Decision, pp. 36–38.
  8. Page 8 of 69

    Docket No. 26-08-05 Page 6 Tables 4 and 5, below, provide a summary of the number of C&I and residential ESS projects approved by the Program Administrators from January 1, 2022 to June 30, 2026. As can be seen from the tables, 133.60 MW of C&I energy storage projects and 21.41 MW of residential energy storage projects have been approved by the Program Administrators and are currently active.2 Table 4: Commercial Project Application Data as of June 30, 2026 Size Category Number of Approved/Complete Projects Total System Power Rating (MW) Large C&I Eversource UI Medium C&I Eversource UI Small C&I Eversource UI Grand Total 36 31 5 22 17 5 14 12 2 72 95.85 87.34 8.51 30.28 27.86 2.42 7.47 6.71 0.76 133.60 Total System Energy Capacity (kWh) 229,990 202,332 27,658 77,056 70,994 6,062 25,142 23,410 1,732 332,188 Program Administrator Order No. 3 Compliance, Aug. 3, 2026, Att. 2, pp. 6–7, 29. Table 5: Residential Project Application Data as of June 30, 2026 Eversource UI Grand Total Number of Approved/ Completed Projects 1,461 352 1,813 Total System Power Rating (MW) 18.90 2.51 21.41 Total System Energy Capacity (kWh) 38,007 5,821 43,828 Low Income (# of Projects) 101 175 276 Underserved Community (# of Projects) 166 61 227 Program Administrator Order No. 3 Compliance, Aug. 3, 2026, Att. 2, pp. 6–7, 29. 2 Tables 4 and 5 exclude withdrawn or canceled projects, meaning the actual total number of MWs approved by the Program Administrators over the life of the Program is higher. See Program Administrator Order No. 3 Compliance, Aug. 3, 2026, Att. 2, pp. 6–7. For more granular and up-to-date data, see the Program’s data dashboard, which is updated daily, here: Energy Storage Solutions Performance Report – Energy Storage Solutions.
  9. Page 9 of 69

    Docket No. 26-08-05 B. Page 7 BIDIRECTIONAL EV PARTICIPATION 1. Background During last year’s annual ESS Program review, the Authority directed the ESS Program Administrators to establish and jointly lead a Bidirectional EV Working Group. Year 5 Decision, p. 60. On behalf of the Working Group, the Program Administrators were required to submit a Bidirectional EV Report presenting the group’s findings and recommendations regarding the integration of bidirectional EVs into the ESS Program. Id. The Program Administrators filed the Bidirectional EV Report (Report) on July 29, 2026. See Program Administrator Order No. 20 Compliance, July 29, 2026. The Report recommended allowing commercial bidirectional EVs with a minimum discharge capacity of 20 kW per charging port to participate in the ESS Program, provided they are not simultaneously enrolled in the state’s managed charging program. Id., Att. 1, p. 61. Under this recommendation, eligible commercial bidirectional EVs would receive the existing small/medium commercial ESS performance incentive for a 10-year enrollment period but would not be eligible for an enrollment incentive, as the Report concluded that this structure maintains a positive Ratepayer Impact Measure (RIM) score. Id., pp. 58, 61– 62. For residential bidirectional EVs, the Report did not recommend immediate inclusion in the ESS Program. Program Administrator Order No. 20 Compliance, July 29, 2026, Att. 1, p. 62. Instead, the Report recommended establishing a pathway with defined milestones that should be achieved before residential participation is considered. Id. These milestones included, among other things, completion of the Bidirectional Energy Innovative Energy Solutions (IES) pilot, incorporation of lessons learned from ongoing Massachusetts demonstrations, resolution of issues related to dual participation in the managed charging and ESS Programs, successful implementation of updated interconnection requirements, and clarification of metering and distributed generation policy considerations. Id., pp. 62–63. The Report recommended revisiting residential bidirectional EV participation during next year's ESS Program review if the Authority determines that doing so remains a priority. Id., p. 63. As discussed above, the Report did not recommend allowing simultaneous enrollment in the ESS and managed charging programs, because of several implementation challenges. Program Administrator Order No. 20 Compliance, July 29, 2026, Att. 1, p. 38. First, absent coordination between the two programs, customer behavior could produce a “timer-peak” effect in which ESS-enrolled vehicles begin charging simultaneously at the conclusion of a dispatch event after discharging energy, thereby undermining the load-shifting objectives of managed charging. Id., p. 36. Stakeholders also raised concerns regarding double penalization, as under the current ESS Program design, charging during an ESS event may negatively affect ESS performance incentives, while the same charging activity could also be penalized under the managed charging program, potentially subjecting a customer to overlapping negative consequences for the same action. Id.
  10. Page 10 of 69

    Docket No. 26-08-05 Page 8 In addition, operating two programs concurrently on the same asset using separate charging and discharging signals could require real-time communication between the respective technology platforms, visibility into the vehicle’s state of charge, and a coordinated customer-facing interface, creating significant implementation complexity. Id., p. 37. Stakeholders also raised customer-related concerns, including the need to enroll in two programs with different compensation structures and the need to ensure that customers retain control over EV dispatch and maintain a state of charge sufficient to meet their transportation needs. Program Administrator Order No. 20 Compliance, July 29, 2026, Att. 1, p. 37. Further, under current EV program rules, receipt of a make-ready or electric vehicle supply equipment (EVSE) rebates for residential customers are conditioned on 24 months of managed charging enrollment, which would prevent such customers from enrolling in the ESS Program during that period. Id., p. 38. Accordingly, until these issues are resolved, the Report did not recommend allowing dual participation. The Report also recommended several technical and programmatic modifications to facilitate bidirectional EV participation. These recommendations included: • • • • • • treating bidirectional EVs as behind-the-meter (BTM) resources, even where the only on-site load is EV charging; removing the existing islanding and backup power requirement for commercial bidirectional EV installations; using the maximum charging capacity of the bidirectional EVSE, rather than historical site demand, when applying the ESS Program’s sizing limitation; requiring several applicable safety and communication certifications; requiring completed distributed energy resource management system (DERMS) integration; and requiring the same static and interval telemetry fields currently required under the ESS Program, while allowing discretion to waive the 15-minute reporting interval for state-of-charge data. Id., pp. 65–66. Separately, in the Year 5 Decision, the Authority directed the EDCs, on behalf of the Interconnection Working Group, to file recommended revisions to the interconnection process for bidirectional EVs, including proposed revisions to the Interconnection Guidelines and any necessary modifications to the PowerClerk system. Year 5 Decision, p. 61. The EDCs submitted these compliance filings on July 1, 2026. See EDC Order No. 25 Compliance, July 1, 2026. The Authority requested written comments on both the Report and the EDCs' recommended interconnection changes for bidirectional EVs. Notice, Aug. 12, 2026, p. 4. The Authority asked stakeholders to identify any specific recommendations they opposed and propose alternative approaches where appropriate. Id. 2. Stakeholder Comments Eversource, UI, and CGB largely echoed the recommendations in the Report, with several additions discussed below. UI Comments, Aug. 27, 2026, pp. 5–7; Eversource Comments, Aug. 28, 2026, pp. 6–9, CGB Comments, Aug. 28, 2026, pp. 4–5. UI