Docket No. 26-08-05 Page 19 Second, the Report recommended that, for purposes of the Program’s 580 MW deployment target, the export rating, in kW, of EVSE enrolled in the ESS Program be counted toward the Program’s MW goal. Id., p. 64. The Authority agrees that the export rating shall be used for this purpose unless performance data demonstrates that bidirectional EVs consistently perform substantially below their rated export capacity. This approach is consistent with the treatment of stationary storage, for which the full export rating is counted toward the Program’s MW deployment target upon enrollment, notwithstanding that actual performance during dispatch may be lower. Counting bidirectional EVs on the same basis promotes consistency across resource types and avoids establishing a different treatment for EV-based storage without a demonstrated need to do so. Accordingly, absent compelling evidence demonstrating that the rated export capacity materially overstates the capacity reasonably available from enrolled bidirectional EVs, the Authority does not anticipate revisiting this determination. h. Technical and Telemetry Requirements The Report proposed several technical requirements and certifications for bidirectional EV participation, as summarized in Table 6 below. Given the broad stakeholder support for these requirements, the Authority approves the technical standards identified in Table 6, subject to the clarifications discussed below. Table 6: Standards and Certifications Applicable to Bidirectional EV Participation in the ESS Program Standard/Certification UL 1741 SB UL 1741 SC Description Enhanced inverter/grid standard with advanced functions. Already required by EDCs for interconnection. Applicable pathway for DCcoupled EVSE. Extension of UL 1741 designed for mobile, onboard vehicle inverters (ACcoupled systems). Requires paired EV to be SAE J3072 certified. Finalized in May 2026. Applicable to EVSE? Applicable to EV? Recommendation Yes No Require for DCcoupled EVSE as well as for stationary storage Yes (ACCoupled) No Require for ACcoupled EVSE upon finalizationPage 22 of 69
Docket No. 26-08-05 Standard/Certification UL 1741 SB CRD SAE J3072 UL 9741 UL 2594 UL 2202 ISO 15118- 20 Page 20 Description Pathway for jointly certifying a specific EV-EVSE pair as a composite DER under the SB framework. Available now; used by some manufacturers (e.g., Tesla). Defines bidirectional energy transfer requirements for plug-in EVs paired with UL 1741 SC EVSE. Safety standard for bidirectional EVSE capable of exporting power to the grid or premises. Safety standard for Level 1 and Level 2 AC EVSE. Safety standard for DC fast charging EVSE. Governs EV-toEVSE communication for bidirectional power transfer. Applicable to EVSE? Applicable to EV? Recommendation Yes (Paired) Permitted as alternative pathway for composite DER pairings (ACcoupled) Yes (ACCoupled) Yes (ACCoupled) Require for EVs paired with UL 1741 SC EVSE; not a standalone requirement Yes No Require Yes (AC) No Require for Level 1/2 AC chargers Yes (DC) No Require for DC fast chargers Yes (partial) Require, with Program Administrator discretion to grant exceptions where certification ecosystem not yet mature Yes Yes Program Administrator Order No. 20 Compliance, July 29, 2026, Att. 1, pp. 44–45. As noted by VGIC, certain AC-coupled systems may be unable to obtain UL 9741 certification but may be capable of obtaining UL 1741 SC certification. VGIC Comments, Aug. 28, 2026, p. 22. The Authority cannot independently determine from the record whether UL 9741 is technically inapplicable to all AC-coupled systems. Nevertheless, rigid application of specific certification standards could unnecessarily restrict participation in a rapidly evolving technology market, particularly where an alternative orPage 23 of 69
Docket No. 26-08-05 Page 21 subsequently developed certification provides comparable assurance of safety and functionality. Accordingly, for the purposes of ESS enrollment, the Authority authorizes the Program Administrators to waive any technical requirement identified in Table 6 when an applicant demonstrates either that: (1) an alternative or subsequently developed certification or standard fulfills the same substantive purpose as the applicable requirement; or (2) the specified certification is not technically applicable or reasonably obtainable for a particular class of resources. The Program Administrators shall incorporate this clarification into the revised Program Manual filed in compliance with this Decision. The burden of demonstrating that a waiver is warranted shall rest with the applicant. The Program Administrators shall not be required to establish independently that an alternative certification satisfies the applicable requirement absent a sufficient showing by the applicant. The Authority does not extend this waiver authority to the Program’s telemetry requirements. The Report recommended maintaining the current requirement that enrolled resources provide telemetry data at 15-minute intervals, while also allowing the Program Administrators discretion to waive that requirement for stored kWh because a working group participant indicated that some EVs may be unable to consistently provide data at that frequency. Program Administrator Order No. 20 Compliance, July 29, 2026, Att. 1, p. 51. However, detailed telemetry data is fundamental to effective ESS Program administration. Granular telemetry is necessary to evaluate resource performance and identify and troubleshoot operational issues. Accordingly, bidirectional EV charging systems enrolled in the ESS Program shall be required to provide stored kWh telemetry at 15-minute intervals, and the Program Administrators shall not waive this requirement. If an enrolled bidirectional EV charging system fails to provide required discharge telemetry data for a particular period, the performance associated with that period shall be recorded as zero for purposes of calculating the applicable performance incentive. This approach appropriately places the risk of inadequate telemetry on the participant and avoids compensating a resource for performance that the Program cannot verify. Finally, the Authority agrees with Tesla that the Program Manual revisions proposed by the Program Administrators do not appear to fully capture the technical requirements and certification pathways described in the Report. See Tesla Comments, Aug. 28, 2026, p. 5; Program Administrator Order No. 3 Compliance, Aug. 3, 2026, Att. 5, pp. 24–25. Accordingly, the Program Administrators shall carefully review and revise the Program Manual to ensure that it accurately and comprehensively incorporates all technical and programmatic requirements applicable to bidirectional EV participation identified in the Report and approved by the Authority. The revised Program Manual shall also clearly reflect the waiver authority established by this Decision and the requirement for 15-minute telemetry data. i. Sizing Requirements The Report recommended a minimum discharge capacity threshold of 20 kW per charging port for commercial bidirectional EV charging systems enrolling in the ESSPage 24 of 69
Docket No. 26-08-05 Page 22 Program. Program Administrator Order No. 20 Compliance, July 29, 2026, Att. 1, p. 4. The Program Administrators explained that this threshold is intended to focus initial enrollment on direct current fast charging (DCFC) stations, as AC or Level 2 chargers typically have a maximum discharge capacity below 20 kW. Program Administrator Interrog. Resp. CAE-13, p. 1. According to the Program Administrators, focusing initially on DCFC chargers would streamline potential fleet-discharging use cases and facilitate smoother V2G integration into the ESS Program, while also reducing the need to enroll individual AC-coupled bidirectional EVs because Level 2 chargers generally lack an inverter. Id. The Authority agrees with the 20 kW per port minimum for the first year of commercial bidirectional EV charging system enrollment. The threshold provides a reasonable means of focusing initial ESS Program participation on larger, more readily dispatchable commercial charging applications while the Program Administrators and the Authority gain experience with bidirectional EV enrollment, dispatch, telemetry, and performance. The Authority views this as an initial implementation threshold rather than a permanent limitation on the types of bidirectional EV resources that may participate in the ESS Program. As the Program Administrators gain operational experience and data, and as the Authority considers residential eligibility, the Authority expects to revisit the threshold. In particular, the Authority does not intend to limit future eligibility solely to DCFC systems. The inability of a Level 2 or other AC charging system to meet the initial threshold, including circumstances in which the charger itself lacks an inverter and bidirectional functionality must instead be provided through the vehicle, should not constitute a permanent barrier to otherwise cost-effective participation. As the technology and market mature and the Program develops greater experience with bidirectional EV resources, the Authority will consider whether a lower threshold could expand participation while continuing to provide benefits commensurate with incentive costs. Further, there shall be no maximum sizing limitation for EV charging systems enrolling in the ESS Program. The Report recommends using the maximum charging rating of the bidirectional EVSE as a proxy for historical maximum peak demand when applying the ESS Program’s sizing limitation of 150% of the customer’s annual peak demand, or 2 MW. Program Administrator Order No. 20 Compliance, July 29, 2026, Att. 1, p. 30. That limitation, however, was developed in connection with the Program’s prior passive dispatch construct, which is no longer open to new enrollments. Year 2 Decision, pp. 20–21. The current Program construct, Construct 5, does not impose a maximum sizing limitation for active dispatch. Year 5 Decision, p. 23. Accordingly, to maintain consistency with the current Program design, there shall be no separate maximum size limit for bidirectional EV charging systems enrolling in the ESS Program. j. Interconnection Guidelines Consistent with the broad stakeholder support for the revised Interconnection Guidelines developed to facilitate interconnection of bidirectional EV charging systems, the Authority approves the revised Interconnection Guidelines and directs the EDCs toPage 25 of 69
Docket No. 26-08-05 Page 23 use the revised Guidelines for all applicable bidirectional EV interconnection requests no later than January 4, 2027. See EDC Order No. 25 Compliance, July 1, 2026. By the same date, the EDCs shall also update their respective interconnection webpages to include the revised Interconnection Guidelines and shall file compliance with the Authority confirming that such updates have been completed. However, implementation of the revised Interconnection Guidelines will provide the first significant opportunity to identify whether additional modifications are necessary. Accordingly, the EDCs shall monitor their implementation of the revised Interconnection Guidelines and identify any material issues, ambiguities, or necessary modifications. Any proposed revisions shall be included in the compliance filing addressing residential bidirectional EV eligibility described prior, which specifically addresses whether further revisions to the Interconnection Guidelines are warranted based on the EDCs’ implementation experience. k. Conclusion The Authority approves commercial bidirectional EV charging system participation in the ESS Program beginning January 1, 2027, subject to the requirements and conditions established in this Decision and the final approved Program Manual. This initial eligibility is intended to provide the ESS Program with meaningful experience with V2G resources while maintaining appropriate protections for residential bidirectional EV owners. The Authority considers residential bidirectional EV participation to remain an important future opportunity and has therefore established a defined process for evaluating residential eligibility as part of a subsequent annual ESS Program review. In contrast, the Authority does not identify dual enrollment of bidirectional EV charging systems in the ESS and managed charging programs as an immediate priority. The Authority will require participating bidirectional EVs to enroll in a single program, based on the significant technical, operational, customer-facing, and ratepayercompensation concerns discussed above. Finally, any requirement, recommendation, or proposal contained in the Report that is not expressly addressed in this section is approved, provided that it is consistent with the determinations and requirements established elsewhere in this Decision. C. ENROLLMENT INCENTIVE CLAWBACK 1. Background During the Year 5 ESS annual review cycle, the Authority adopted Construct 5, which eliminated passive dispatch and significantly reduced upfront incentives in favor of a predominantly performance-based compensation structure. Year 5 Decision, pp. 20– 21. This construct was intended to minimize ratepayer exposure while better aligning participant compensation with realized system value. Id. Construct 5 does not include aPage 26 of 69
Docket No. 26-08-05 Page 24 clawback provision tied to participation in active dispatch, as active dispatch participation is not a condition for receipt of the enrollment incentive. Id., pp. 14-15. Further, Section 3.7 of the ESS Program Manual provides that, once a customer who has received an enrollment incentive unenrolls from active dispatch, “there is no requirement to return any portion of the Enrollment Incentive.” Motion No. 15, Jan. 6, 2026, Docket No. 25-08-05, Att. 2, p. 27. In Section A of its January 13, 2026 ruling on Motion No. 15, the Authority directed the Program Administrators to implement a clawback mechanism for the enrollment incentive where participants disenroll from the ESS Program prior to the expiration of their 10-year term. Motion No. 15 Ruling, Jan. 13, 2026, Docket No. 25-08-05, p. 2. The Authority determined that, although the enrollment incentive under Construct 5 is not conditioned on active dispatch participation, it is premised on continued participation in the ESS Program over the 10-year enrollment term. Id. Specifically, allowing a participant to retain the full enrollment incentive despite early disenrollment could undermine the structure and intent of Construct 5 by creating a potential incentive to enroll solely to obtain the upfront payment without delivering sustained ratepayer benefits. Id. The ESS Program Administrators objected and filed a motion for reconsideration pursuant to General Statutes § 16-9. Motion No. 16, Jan. 21, 2026, Docket No. 25-0805, p. 2. The ESS Program Administrators raised concerns regarding the feasibility and implementation of an enrollment incentive clawback requirement, including administrative burden and cost, the potential for customers to be subject to clawbacks due to circumstances beyond their control (such as manufacturer bankruptcy), and uncertainties associated with customer relocation or transfer of battery ownership. Id., pp. 3-4. The ESS Program Administrators requested that the issue be deferred to the Year 6 annual ESS Program review to allow for broader stakeholder input. Id., p. 4. In light of these concerns, the Authority stayed Section A of its Motion No. 15 Ruling and indicated its intent to revisit the issue during the Year 6 annual ESS Program review. Motion No. 16 Ruling, Jan. 29, 2026, Docket No. 25-08-05, p. 3. The Authority further clarified that the absence of a clawback provision in the Year 5 Decision reflected a determination specific to dispatch participation requirements, rather than continued enrollment in the ESS Program. Id., p. 2; Year 5 Decision, pp. 14–15. Accordingly, the Authority sought stakeholder input on whether an enrollment incentive clawback should be implemented such that, if a project disenrolls prior to the conclusion of its 10-year enrollment term, a prorated portion of the enrollment incentive must be repaid. Notice, June 16, 2026, p. 2. For example, a project that disenrolls after one year could be required to return 90% of the incentive. Id. Consistent with prior determinations, any clawback could be conditioned solely on continued ESS Program enrollment and not on participation in active dispatch. Id.Page 27 of 69
Docket No. 26-08-05 Page 25 2. Stakeholder Comments Eversource argued that implementing a formal enrollment incentive clawback mechanism would not be a prudent use of customer funds given the limited number of customers expected to enroll in the ESS Program solely to obtain an enrollment incentive before promptly disenrolling. Eversource Comments, July 9, 2026, p. 3. Eversource expressed concern that implementing such a mechanism would impose administrative costs on customers that could exceed any amounts ultimately recovered. Id. Eversource also noted that customers may disenroll before completing their 10-year enrollment term for legitimate reasons beyond their control, including the sale of a home, battery damage or malfunction, or battery original equipment manufacturer (OEM) bankruptcy. Id., pp. 34. According to Eversource, applying an enrollment incentive clawback in these circumstances would be inequitable. Id., p. 4. Finally, Eversource argued that battery systems continue to provide resilience benefits to customers regardless of whether they remain enrolled in the ESS Program. Eversource Comments, July 9, 2026, p. 4. UI raised similar concerns, stating that implementing an enrollment incentive clawback would increase administrative complexity and labor costs, which ultimately would be borne by all ratepayers. UI Comments, July 9, 2026, p. 2. Nevertheless, if the Authority elects to implement such a mechanism, UI recommended establishing a costeffectiveness threshold to ensure that administrative costs do not materially exceed the expected ratepayer benefits from recovered enrollment incentives. Id. UI also recommended exempting customers whose early disenrollment results from circumstances beyond their reasonable control, including equipment failure not attributable to the customer, OEM or vendor bankruptcy, force majeure events, and property transfers where the original participant no longer controls the battery system. Id., p. 3. In addition, UI recommended limiting any enrollment incentive clawback to residential and commercial customers who both disenroll early and install battery systems exceeding their annual peak demand, to discourage customers from intentionally oversizing battery systems to maximize enrollment incentives under Construct 5. Id. UI concluded that any clawback mechanism should complement, rather than materially complicate, the Construct 5 framework adopted last year and should avoid introducing unnecessary complexity that could reduce customer understanding or participation. UI Comments, July 9, 2026, p. 4. Similarly, CGB opposed implementing an enrollment incentive clawback for homeowner-owned residential projects, arguing that the administrative costs and adverse impacts on customer participation would outweigh any potential ratepayer benefits. CGB Comments, July 9, 2026, p. 1. CGB argued that an enrollment incentive clawback would create financial uncertainty, particularly for underserved customers who may disenroll for reasons beyond their control, such as relocation, equipment failure, or the need to preserve battery capacity for backup power during outages. Id. According to CGB, the prospect of an enrollment incentive clawback could discourage participation, negatively affect customer perceptions of the Program, and diminish the resilience benefits the ESS Program provides to vulnerable communities. Id. CGB further noted that battery systems continue to provide grid and resilience benefits through backup power and increased solar self-consumption even after a customer disenrolls from the ESS Program. Id., p. 2.Page 28 of 69
Docket No. 26-08-05 Page 26 If the Authority nevertheless adopts an enrollment incentive clawback mechanism, CGB recommended limiting its application, where appropriate, to commercial-scale and residential third-party owned (TPO) projects. CGB Comments, July 9, 2026, p. 2. CGB argued that homeowner-owned residential systems present distinct equity and administrative considerations that differ from commercial-scale and residential TPO projects. Id. Finally, CGB noted that customers already have a significant financial incentive to remain enrolled in the ESS Program because early disenrollment results in the loss of ongoing performance incentive payments. Id. OCC argued that ratepayer-funded enrollment incentives should be conditioned on delivering ratepayer value throughout the full enrollment term for which they were designed. OCC Comments, July 9, 2026, p. 2. According to OCC, an enrollment incentive clawback serves two purposes: recovering incentive funds when customers disenroll early and deterring opportunistic disenrollment, thereby preserving the ESS Program's cost-effectiveness. Id. OCC argued that these ratepayer protection benefits outweigh the administrative costs of implementing a clawback mechanism and supported an equal prorated repayment schedule. Id., p. 3. OCC nevertheless urged the Authority to adopt narrowly tailored exemptions for circumstances genuinely beyond a participant's control. Id. OCC recommended that any such exemptions require affirmative documentation, place the burden of proof on the participant seeking relief, and not undermine the overall clawback framework. OCC Comments, July 9, 2026, p. 3. OCC further argued that repayment responsibility should generally rest with the party that received and benefited from the enrollment incentive while accounting for which party had control over the event leading to disenrollment. Id. OCC also recommended applying any outstanding performance incentive payments toward satisfaction of an enrollment incentive clawback before seeking additional repayment. Id., p. 4. Lastly, although OCC supported applying a clawback across all customer classes, it acknowledged that a de minimis threshold may be appropriate where administrative costs would be disproportionate to the amount recoverable from the smallest residential participants.3 Id. The Alliance for Climate Transition (ACT), the Solar Energy Industries Association (SEIA), and the Coalition for Community Solar Access (CCSA; collectively, the Energy Storage Stakeholders) argued that the administrative costs of implementing an enrollment incentive clawback would likely exceed the value of any recovered funds, would not effectively deter early disenrollment, and would primarily affect customers whose disenrollment resulted from circumstances beyond their control. Energy Storage Stakeholder Comments, July 9, 2026, p. 2. The Energy Storage Stakeholders asserted that the decision to not institute an enrollment incentive clawback in the prior annual review represented a significant program design improvement that was expected to increase participation in and performance of the ESS Program. Id., p. 2. 3 In its second set of written comments, recognizing the lower enrollment incentive available through Construct 5 and the administrative complexities associated with enforcing the clawback, OCC revised its position and stated that it did not oppose limiting the clawback mechanism to commercial priority customers and residential TPO systems. OCC Comments, Aug. 28, 2026, p. 2.Page 29 of 69
Docket No. 26-08-05 Page 27 The Energy Storage Stakeholders further argued that administering an enrollment incentive clawback would require significant resources to monitor disenrollment, calculate repayment amounts, coordinate with customers, OEMs, and third parties that received enrollment incentives, and collect repayment, potentially causing administrative costs to exceed any recovered funds. Id. The Energy Storage Stakeholders also contended that introducing repayment risk, including risks associated with manufacturer bankruptcy, customer relocation, or changes in battery ownership, would discourage customers from participating in the ESS Program. Id., p. 3. According to the Energy Storage Stakeholders, early disenrollment is expected to be rare because customers already have a strong financial incentive to remain enrolled, as the loss of a single year of performance incentive payments typically exceeds the enrollment incentive for most battery systems. Energy Storage Stakeholder Comments, July 9, 2026, p. 3. Nevertheless, if the Authority adopts an enrollment incentive clawback, the Energy Storage Stakeholders recommended applying it only to the entity that received the enrollment incentive and calculating the repayment amount on a prorated basis for the remaining enrollment term. Id. The Connecticut Solar and Storage Association (ConnSSA) opposed any enrollment incentive clawback that would hold installers or contractors responsible for circumstances beyond their control, including a customer's decision to disenroll from the ESS Program. ConnSSA Comments, July 9, 2026, pp. 1-2. ConnSSA argued that the Construct 5 framework already substantially shifted customer compensation from upfront incentives to performance-based payments, thereby reducing ratepayer risk by tying most compensation to actual grid performance. Id., p. 1. According to ConnSSA, a broad enrollment incentive clawback would create customer confusion, discourage ESS Program participation, and increase administrative burden while providing little additional ratepayer protection. Id. If the Authority nevertheless adopts an enrollment incentive clawback, ConnSSA recommended limiting repayment responsibility to the party that owns the battery system, receives the enrollment incentive, controls the enrollment decision, or affirmatively causes the project to be removed from the ESS Program. Id., p. 2. ConnSSA argued that contractor liability should be limited to contractor-caused issues, such as installing ineligible equipment, failing to complete required project documentation, or other precompletion noncompliance within the contractor's control. ConnSSA Comments, July 9, 2026, p. 2. Accordingly, ConnSSA urged the Authority to distinguish between contractorcaused noncompliance and customer-controlled post-completion conduct if it implements an enrollment incentive clawback. Id. CPower did not oppose a prorated enrollment incentive clawback for residential and commercial customers that disenroll before completing their 10-year enrollment term. CPower Comments, July 9, 2026, p. 2. CPower argued that battery projects are economically dependent on continued participation in the ESS Program and, therefore, are unlikely to disenroll before the end of their enrollment term except in cases of catastrophic battery damage. Id. In those circumstances, CPower argued that recovering a prorated share of the enrollment incentive would be appropriate because ratepayers would no longer receive the intended benefits from the battery system. Id. CPowerPage 30 of 69
Docket No. 26-08-05 Page 28 further recommended assessing any clawback against the entity receiving ESS Program payments at the time the clawback is imposed, rather than the entity that received payments when the project originally enrolled, to ensure repayment responsibility rests with the party then responsible for the battery system while reducing administrative complexity. Id. Earthlight cautioned against adopting an overly broad enrollment incentive clawback that would apply to customers who disenroll before completing their 10-year enrollment term, arguing that doing so would create unnecessary negative customer experiences and discourage future ESS Program participation. Earthlight Comments, July 9, 2026, p. 2. Earthlight noted that most early disenrollments result from circumstances beyond a customer's control, such as OEM bankruptcy. Id. Earthlight further argued that the Construct 5 framework already adequately protects ratepayers by reducing the upfront enrollment incentive and shifting a larger share of compensation to performance-based payments, thereby ensuring that customers receive most ESS Program incentives only if they continue participating in seasonal dispatch events. Id., p. 3. 3. Authority Analysis An enrollment incentive clawback provision is necessary to ensure that ratepayerfunded enrollment incentives remain reasonably aligned with the benefits the ESS Program is intended to provide over a participant’s enrollment term. Although the enrollment incentive under Construct 5 is substantially smaller than the upfront incentive offered under the prior passive dispatch structure, it is not de minimis. The enrollment incentive may be $3,900 or more for grid-edge residential customers and may be substantially higher for commercial priority customers, depending on system size. See Program Administrator Corresp., Aug. 3, 2026, pp. 5–6. Without a clawback provision, a system owner could disenroll from the ESS Program shortly after receiving the enrollment incentive while retaining the full payment. Such an outcome would allow a participant to receive a ratepayer-funded benefit without providing the full period of Program participation contemplated by Construct 5 and could reduce the peak reduction, dispatch, and other system benefits expected from the Program, thereby adversely affecting the Program’s RIM score. The Authority recognizes the stakeholder concerns regarding the administrative costs associated with implementing and enforcing a clawback, as well as the potential for customers to disenroll for legitimate reasons beyond their control. Further, Construct 5 has already substantially reduced ratepayer risk by shifting a greater portion of participant compensation from upfront incentives to performance-based payments. Nevertheless, the existing compensation structure does not eliminate the need for a narrowly tailored clawback. The enrollment incentive remains a material payment, and the possibility that a participant could retain the full incentive after prematurely ending their participation creates a risk that is not addressed by the loss of future performance incentive payments alone. This concern is particularly relevant as TPOs are expected to become increasingly important to the ESS Program as a result of recent changes to the federal investment tax