Utility Dockets and Filings

Draft Decision

Files2

Search terms highlighted
Eversource rate increase is on 2 pages of the text below, highlighted. Go to the first matchClear highlighting
2 pages match
  1. Page 40 of 69Match

    Docket No. 26-08-05 Page 38 e. FERC vs PURA Jurisdiction As previously discussed, Eversource raised concerns that an FTM storage retail tariff can infringe on FERC’s jurisdiction to regulate wholesale electric rates. Particularly, Eversource cautioned that an FTM retail tariff that enables an FTM storage resource to purchase power to charge and subsequently sell its output to an EDC at a retail rate would constitute a FERC-jurisdictional transaction. Eversource Comments, pp. 5–6, July 9, 2026. Moreover, Eversource asserted that stand-alone FTM resources are not permitted to sell power to the EDCs under PURPA, which provides the sole means of compelling EDCs to purchase wholesale energy set by states. Id., p. 6. Eversource’s comments capture the complexity of FERC and state jurisdictional issues pertaining to the deployment and operation of FTM energy storage resources. Thus, any retail tariff for FTM storage must be carefully crafted to capture distributionlevel benefits while avoiding incursions into FERC’s jurisdiction over wholesale transactions. While the Authority must evaluate and adjudicate any jurisdictional issues pertaining to a specific FTM storage tariff in a ratemaking proceeding, the Authority briefly summarizes the relevant jurisdictional issues here to inform the Working Group’s deliberations. Under the Federal Power Act (FPA), FERC has exclusive jurisdiction over the sale of electricity as a matter of interstate commerce, while the regulation of retail electricity sales is reserved for the states, no matter the effects the state’s regulatory actions have on wholesale electricity rates. 16 U.S.C. § 824; F.E.R.C. v. Electric Power Assn, 577 U.S. 260, 280 (2016). Within the context of energy storage resources, FERC issued Order No. 841, which set forth the limits of FERC’s jurisdiction of such resources in the wholesale market. 162 FERC ¶ 61,127, Docket Nos. RM16-23-000; AD16-20-000; Order No. 841, Electric Storage Participation in Markets Operated by Regional Transmission Organizations and Independent System Operators (Feb. 15, 2018) (Order No. 841). Specifically, FERC held that “an electric storage resource that injects electricity back to the grid for purposes of participating in an RTO/ISO market engages in the sale of electric energy at wholesale in interstate commerce.”9 Order No. 841, p. 27. Therefore, under Order No. 841, a potential retail tariff cannot compensate FTM storage resources for participation in wholesale energy or ancillary-service markets or, in other words, where the energy from such resources is sold into the wholesale market. Importantly, FERC delineated between the sale of electric energy at wholesale from transactions that do not involve the sale of electricity at wholesale, such as those compensating storage resources as demand response resources.10 Order No. 841, p. 9 FERC defines an “electric storage resource” as a resource capable of receiving electric energy from the grid and storing it for later injection of electric energy back to the grid. Order No. 841, p. 1. FERC further clarified that a resource “capable of later injecting electricity back to the grid” means a storage resource both physically designed and configured to do so and is contractually permitted to do so. 10 A “demand response resource” is defined as a “resource capable of providing demand response.” 18 Code of Federal Regulations (CFR) § 35.28(b)(5). “Demand response” is defined as a “reduction in the consumption of electricity by customers from their expected consumption in response to an increase in the price of electric energy or to incentive payments designed to lower consumption of electric energy.” 18 C.F.R. § 35.28(4).
  2. Page 41 of 69

    Docket No. 26-08-05 Page 39 28, n. 53. Therefore, a retail tariff may compensate an energy storage resource for products that do not include the sale of electric energy in wholesale energy or ancillaryservices markets, such as load reducer benefits and other distribution-level benefits, so long as compensation is not intertwined with a wholesale transaction related to the sale of electric energy into wholesale energy or ancillary-service markets. In sum, under such a construct, load reducer and other distribution-level benefits do not compensate the resource for the sale of electricity into the wholesale market and are separate and distinct from such transactions; therefore, they do not constitute a sale of electricity in interstate commerce under the FPA. Notably, the Authority and Eversource agree that a transaction in which the resources are not being compensated for buying and selling energy as a commodity or are otherwise compelling the EDCs to purchase energy are PURA jurisdictional. Tech Meeting Tr., Aug. 7, 2026, 104:1–16; 105: 2–13; 106:9–19; 109:9-19. Accordingly, any potential bidirectional retail TOU tariff should be designed to compensate FTM storage for identifiable distribution-level services or benefits within the Authority's jurisdiction, rather than to regulate or compensate wholesale transactions subject to FERC jurisdiction, such as wholesale energy arbitrage transactions. Specifically, compensation for distribution-level benefits should be structured separately from wholesale energy and ancillary-service transactions to avoid duplicative compensation. f. Additional Tariff Design Considerations Any future FTM storage tariff must be designed to provide benefits to Connecticut ratepayers that exceed the costs associated with the tariff. A retail tariff developed through this process must not function as an incremental deployment incentive or otherwise provide compensation unrelated to identifiable costs or benefits to the electric system simply to induce the construction of FTM storage. Rather, the purpose of a potential tariff would be to establish appropriate price signals and compensation mechanisms for identifiable distribution-level costs and benefits associated with the operation of eligible FTM storage resources. As discussed above, such benefits could include, but need not be limited to, shifting charging or discharging away from constrained periods, reducing the EDCs’ allocation of Regional Network Service costs through reductions in relevant system peaks, and avoiding or deferring distribution system investments. Further, a potential tariff should be evaluated using a quantifiable ratepayer-impact framework that demonstrates a net benefit to Connecticut ratepayers. To the extent practicable, the CT-RIM methodology used to evaluate the ESS Program should be applied to proposed tariff parameters to promote consistency in the methodologies used to assess Connecticut’s energy storage programs. Any tariff ultimately recommended for the Authority’s consideration should demonstrate a CT-RIM score of at least 1.4, consistent with the ratepayer-protection threshold applied in the ESS Program. A potential FTM storage tariff would also need to be carefully coordinated with the existing WDAT framework and wholesale market participation. Specifically, the interactions between a potential retail tariff, the WDAT, and wholesale market participation
  3. Page 42 of 69

    Docket No. 26-08-05 Page 40 are relevant to tariff design, including to prevent conflicting price signals or duplicate compensation for the same service or benefit. If a retail tariff is intended to provide sufficient economic value to influence FTM storage operation, a bidirectional structure warrants consideration. Such a structure could establish time-varying prices for charging and compensation for discharging during periods when the resource provides greater value to the distribution system. g. Working Group and Next Steps The current record is insufficient to establish these parameters through this proceeding. Significant technical, economic, rate-design, and operational, and legal issues remain regarding, among other things, the valuation of distribution-level benefits, appropriate eligibility requirements, metering, WDAT interaction, non-bypassable charges, cost allocation, location-specific value, and coordination with wholesale market participation. These issues warrant substantial stakeholder expertise and engagement before the Authority considers a specific tariff for adoption. Notably, both EDCs expressed openness to, and identified potential value in, examining these issues through a workinggroup structure similar to the original FTM Storage Working Group. Tech Mt’g Tr., Aug. 7, 2026, 86:12–89:11. Accordingly, the Authority reestablishes the FTM Storage Working Group that previously examined FTM storage and informed the development of the WDAT framework. CGB, as an ESS Program administrator with experience in clean energy policy and stakeholder engagement, shall lead the Working Group. 11 Subject to future prudence review, costs incurred by CGB in connection with this initiative shall be eligible for consideration for cost recovery in future RAM proceedings and shall be submitted as a specific line item in CGB's annual RAM filing. CGB shall invite, at a minimum, the EDCs, DEEP, OCC, ACT, SEIA, CCSA, and all members of the original FTM Storage Working Group to participate in the process. See EDC Compliance, Docket No. 22-08-05, Dec. 29, 2023, WG Report, p. 19. CGB shall establish the Working Group no later than March 1, 2027, and shall submit a comprehensive FTM Storage Tariff Report by December 1, 2027. The report shall identify the Working Group's findings and recommendations regarding the feasibility and design of a bidirectional retail TOU tariff for standalone FTM storage and shall identify any issues that may require additional statutory authorization before implementation. Upon receipt of the FTM Storage Tariff Report, the Authority may initiate a separate proceeding to consider whether to adopt the proposed FTM storage tariff, consistent with the Authority's statutory authority at that time. Any such proceeding will be separate from the ESS annual review dockets because standalone FTM storage presents distinct regulatory, operational, and rate-design considerations and would not constitute an expansion of the ESS Program. 11 CGB, at its discretion and in recognition of DEEP’s role in the deployment of FTM storage in the state, may invite DEEP to participate in a leadership capacity within the Working Group.
  4. Page 43 of 69

    Docket No. 26-08-05 Page 41 At a minimum, the FTM Storage Tariff Report shall address: 1. the appropriate structure and time periods for any bidirectional retail TOU tariff, including whether charging and discharging should be subject to different timevarying rates or credits; 2. the specific distribution-level benefits that could appropriately be recognized through a retail tariff and the methodology for quantifying and attributing those benefits to participating resources; 3. the appropriate compensation mechanism for identified distribution-level benefits, including whether compensation should vary based on time, system conditions, or other relevant characteristics; 4. whether the tariff should provide location-specific compensation for FTM storage resources that can avoid or defer identified distribution system investments and, if so, how any such compensation should be calculated; 5. the appropriate charge structure, including the treatment of transmission, distribution, and non-bypassable charges and whether alternative charge methodologies are necessary to avoid inappropriate or duplicative charges; 6. the appropriate eligibility, sizing, metering, and performance requirements for participating FTM storage resources, including the treatment of co-located resources; 7. how the tariff should interact with the WDAT and wholesale market participation, including appropriate mechanisms to avoid conflicting price signals and duplicate compensation; 8. whether alternative versions of the tariff should be developed to support participation in a subset of wholesale markets (e.g., forward capacity market only); 9. any federal legislation or regulation that explicitly permits or prohibits participation of an FTM storage resource in wholesale markets that takes service on a retail tariff; 10. the appropriate treatment of cost allocation and the potential impacts on participating and non-participating customer classes; and 11. the participant and ratepayer impacts of the proposed tariff, including the PCT and CT-RIM score, using ESS Program methodologies to the greatest extent possible. h. Conclusion The reestablishment of the FTM Storage Working Group does not constitute a determination that a particular FTM storage tariff should ultimately be adopted or that the Authority presently has sufficient statutory authority to implement every potential recommendation developed through the Working Group. Rather, the purpose of this process is to develop the technical and economic record necessary for the Authority to make those determinations in a subsequent proceeding or, as appropriate, to identify any additional legislative authorization that may be necessary. Ultimately, FTM storage may provide benefits to Connecticut's electric system and ratepayers that are not fully reflected through existing wholesale market mechanisms.
  5. Page 44 of 69

    Docket No. 26-08-05 Page 42 The Working Group will provide an opportunity to evaluate those potential benefits rigorously and develop recommendations regarding whether, and under what framework, they could appropriately be reflected in Connecticut's retail rate structure. E. DATA DASHBOARD 1. Background The Authority investigated whether additional information should be included on the ESS Program data dashboard, including annual performance incentive payments and identification of the actual annual ISO-NE system peak hour. PURA Interrogatories, June 16, 2026, p. 1. Eversource and UI supported adding total and average annual performance incentive payments to the dashboard, stating that greater cost transparency would help customers make more informed decisions when selecting battery systems. Eversource Interrog. Resp. CAE-2, p. 1; UI Interrog. Resp. CAE-2, p. 1. UI further noted that making performance payment information publicly available could encourage improved OEM performance. UI Interrog. Resp. CAE-2, p. 1. CGB similarly supported adding performance incentive payment information, stating that doing so would enhance cost transparency, provide greater visibility into the scale of annual performance-based payments, and provide a more complete understanding of Program costs and participant benefits over time. CGB Interrog. Resp. CAE-2, p. 1. CGB stated that implementation would require obtaining or confirming historical final seasonal performance payments from the EDCs and estimated that dashboard integration and data validation would take approximately two months after receiving complete final payment information from the EDCs. Id. Eversource and UI also supported identifying the day and hour on which the annual ISO-NE system peak occurred on the Dispatch Event Metrics tab of the dashboard. Eversource Interrog. Resp. CAE-3, p. 1; UI Interrog. Resp. CAE-3, p. 1. UI stated that this information would enhance Program transparency and facilitate analysis of performance trends across Program years. UI Interrog. Resp. CAE-3, p. 1. Eversource noted that ISO-NE makes the final determination of the annual system peak day and hour in the following calendar year using settlement data rather than operational data. Eversource Interrog. Resp. CAE-3, p. 1. CGB stated that the actual annual peak hour for prior seasons could be identified on the Dispatch Event Metrics tab through several approaches, including: (1) a separate indicator identifying whether a dispatch event coincided with the annual peak hour; (2) a visual flag or note within the existing event-level metrics; or (3) a summary field or filter allowing users to isolate events occurring during the applicable peak hour. CGB Interrog. Resp. CAE-3, p. 1. From a dashboard usability perspective, CGB recommended an event-level flag that could also be filtered or summarized, allowing users to readily distinguish dispatch events occurring during the annual system peak from other dispatch activity. Id.
  6. Page 45 of 69

    Docket No. 26-08-05 Page 43 2. Authority Analysis Adding data enhancements to the ESS Program data dashboard—specifically, annual performance incentive payment information and identification of the annual ISONE system peak hour—will improve Program transparency. Publicly reporting actual performance incentive payments will provide greater visibility into Program costs and the performance payments associated with different OEMs and customer sectors. This information may also encourage OEMs to improve system performance relative to other manufacturers. Similarly, identifying the annual ISO-NE system peak hour will provide greater transparency into whether ESS Program resources are being dispatched when systemwide peak reduction provides the greatest potential value to ratepayers. Reporting this information would facilitate evaluation of Program performance and enable a more effective assessment of the Program’s contribution to peak reduction during this critical period. Accordingly, the Authority directs CGB to add performance incentive payment information to the ESS Program data dashboard no later than April 1, 2027. The information shall be broken out by season, where applicable, customer sector, and OEM. The EDCs shall provide CGB with the information necessary to verify the accuracy and completeness of the reported performance incentive payment data. CGB may, at its discretion, normalize performance incentive payments by kW or another metric that CGB determines would provide the most useful comparison for customers and stakeholders. The Authority further directs CGB, by April 1, 2027, to identify the annual ISO-NE system peak hour for all prior dispatch years on the Dispatch Event Metrics tab. CGB shall use a clear flag, filter, or comparable dashboard feature that allows users to readily identify and isolate dispatch events that occurred during the applicable annual system peak hour. CGB shall continue to add the annual ISO-NE system peak hour to the dashboard for each subsequent dispatch year once ISO-NE has made its final determination of the applicable peak hour. F. PROGRAM REDLINE AND RECOMMENDED CHANGES Order No. 3 of the Year 5 Decision directs the Program Administrators to file by August 1 annually “recommendations for any Program modifications.” Year 5 Decision, p. 56. In compliance with Order No. 3, the Program Administrators filed proposed Program modifications and updated Program documents, including an updated Program Manual. See Program Administrator Order No. 3 Compliance, Aug. 3, 2026, Att. 4. In this section, the Authority addresses revisions to the Program documents filed in compliance with Order No. 3 that are not addressed by other aspects of this Decision. Finally, the Authority approves all additional redline and programmatic changes proposed by the Program Administrators which are not discussed in this section or affected by other parts of the Decision.
  7. Page 46 of 69

    Docket No. 26-08-05 Page 44 1. Performance Payment Frequency In the Year 5 Decision, the Authority directed the Program Administrators to provide participants with a choice between two performance incentive payment structures: (1) a new single annual payment option covering both the winter and summer dispatch seasons; or (2) the existing seasonal payment option, providing one payment following each dispatch season. Year 5 Decision, p. 23. The Authority approved the new single annual payment option because it would streamline Program administration by requiring only one annual performance calculation and was consistent with the Program Administrators’ revised active dispatch incentive design proposal submitted last year. See Program Administrator Compliance, May 1, 2025, Docket No. 24-08-05, Att. 1, pp. 17, 22; Year 5 Decision, p. 23. The Authority nevertheless retained the existing seasonal payment option to avoid adversely affecting project economics due to the time value of money, as participants could otherwise experience a delay in receiving payment for performance during the earlier dispatch season. Year 5 Decision, p. 23. The Program Administrators now seek to reverse that determination by revising the Program Manual to eliminate the single annual payment option and require all participants to receive performance incentives through two seasonal payments. Program Administrator Order No. 3 Compliance, Aug. 3, 2026, Att. 4, p. 3. According to the Program Administrators, the Program’s DERMS providers indicated that administering a single annual performance incentive payment would present technical challenges. Id. The small number of participants that have already selected the single annual payment option would consequently be transitioned to the seasonal payment option. Id. Furthermore, Eversource argued that paying incentives shortly after each dispatch season strengthens the connection between a participant’s actions and associated reward, which could improve participant retention and year-over-year load curtailment. Eversource Interrog. Resp. CAE-1, p. 1. Eversource also asserted that seasonal payments reduce the risk of errors accumulating over longer settlement periods and allow the EDCs to identify underperforming accounts earlier, providing an opportunity for corrective action or targeted outreach before the subsequent dispatch season. Id., p. 2. Eversource stated that its DERMS provider, EnergyHub, cannot currently accommodate an annual incentive payment. Eversource Interrog. Resp. CAE-27. Specifically, Eversource asserted that implementing such a payment structure would require custom development to enable a single annual payment covering two demand response seasons. Id. UI similarly stated that maintaining multiple payment methodologies would introduce additional system and administrative complexity. UI Interrog. Resp. CAE-1, pp. 1–2. UI’s DERMS provider advised that transitioning to annual performance incentive payments would require significant system modifications, including developing, testing, and implementing new reporting logic and additional data warehouse configurations. Id., p. 2. According to UI, these modifications would increase Program costs borne by ratepayers by approximately $40,000. Id.; UI Interrog. Resp. CAE-27.
  8. Page 47 of 69

    Docket No. 26-08-05 Page 45 Earthlight supported eliminating the annual payment option. Earthlight Comments, Aug. 28, 2026, p. 3. Earthlight argued that maintaining a biannual payment structure would bring Construct 5 customers into greater alignment with legacy customer payments, thereby streamlining operations for the Program Administrators. Id. Earthlight further argued that a biannual incentive payment structure provides system owners with tangible value sooner than an annual payment structure. Id. The Authority does not reverse a prior determination lightly. In this case, the Authority would have preferred that the Program Administrators identify the implementation challenges associated with an annual payment structure before approval last year. This is particularly true because the annual payment option was consistent with the Program Administrators’ original incentive design proposal intended to address issues associated with passive dispatch. See Program Administrator Compliance, May 1, 2025, Docket No. 24-08-05, Att. 1, pp. 17, 22. Nevertheless, the Authority finds that the circumstances presented here warrant revisiting its prior determination. Maintaining both annual and seasonal payment structures would result in significant implementation costs and administrative complexity. In addition, no stakeholder opposed elimination of the annual payment option, and only six approved or submitted projects had selected the annual payment option as of August 3, 2026. See Program Administrator Order No. 3 Compliance, Aug. 3, 2026, Att. 4, p. 3. On balance, the administrative and implementation benefits of a single payment methodology outweigh the limited benefits of retaining an annual payment option for the small number of affected participants. Accordingly, the Authority approves the proposed change and directs the Program Administrators to remove the annual payment option from the Program Manual. Participants currently enrolled under the annual payment option shall be transitioned to the biannual payment structure. 2. Change Orders The Program Administrators proposed allowing customers with projects approved under a now-closed legacy tranche, but not yet installed, to submit change orders to increase system size under unavoidable circumstances. Program Administrator Order No. 3 Compliance, Aug. 3, 2026, Att. 4, p. 6. The Program Administrators clarified, however, that change orders resulting in a significant increase in system size would require the entire system to transition to the current incentive rate. Id. The Program Administrators did not define the circumstances under which an approved but uninstalled project could increase its system size, nor did they establish a threshold for determining when an increase would be considered significant and therefore require the project to transition to the current incentive rate. See Id. Accordingly, the Authority asked the Program Administrators to propose an appropriate percentage threshold for increases to a project’s system size after approval but before incentive payment, identify the limited circumstances under which such increases should be permitted, and justify their recommendations. PURA Interrogatories, Aug. 12, 2026, p. 4.
  9. Page 48 of 69Match

    Docket No. 26-08-05 Page 46 Eversource was agnostic as to an appropriate threshold for increasing the size of an approved but unbuilt project. Eversource Interrog. Resp. CAE-18. Eversource noted that, from an interconnection perspective, projects are more commonly downsized than increased as a result of study findings. Id. UI recommended against establishing a fixed percentage threshold for allowable system size increases. UI Interrog. Resp. CAE-18. UI argued that a fixed threshold could inadvertently restrict otherwise reasonable project modifications and create unnecessary barriers for customers whose projects are affected by circumstances beyond their control. Id. Similarly, CGB opposed establishing a specific threshold, arguing that Program Administrator discretion would be more appropriate given the variety of circumstances that could necessitate a system size increase. CGB Interrog. Resp. CAE-18. Nevertheless, CGB stated that, if the Authority requires a fixed percentage threshold, the threshold should be no more than a 50% increase in kW. Id. CGB also anticipated that many change orders would instead result in system size reductions due to interconnection restrictions. Id. The Authority will allow customers with projects approved under a now-closed legacy tranche, but not yet installed, to submit change orders to increase system size. However, such increases should be subject to a reasonable limit. The Authority is particularly concerned that, absent a defined threshold, significant increases in system size could be permitted while allowing projects to retain legacy incentive rates. Accordingly, the Authority will allow projects approved under a now-closed legacy tranche, but not yet installed, to increase their system size by no more than 5% for any reason. The 5% threshold is consistent with size-related allowances under Connecticut’s other renewable energy programs. The Non-Residential Renewable Energy Solutions (NRES) Program allows projects to increase their system size by up to 5% of the original approved bid size, regardless of the reason for the increase. Motion No. 11, Jan. 9, 2026, Docket No. 25-08-03, Annual Non-Residential Renewable Energy Solutions Program Review – Year 5, Att. 2a, p. 32. Similarly, the Residential Renewable Energy Solutions (RRES) Program allows a system’s expected annual production to exceed a customer’s highest annual consumption over any 12-month period within the preceding five years by no more than 5% for any reason. EDC Compliance, Ja. 22, 2026, Docket No. 25-08-02, Annual Residential Renewable Energy Solutions Program Review and Rate Setting – Year 5, Att. 1b, p. 25. Establishing a consistent 5% threshold across Connecticut’s clean energy programs will reduce developer confusion, promote uniformity, and facilitate consistent administration. For all projects, an increase of up to 5% shall not result in an increase to the project’s previously approved upfront or enrollment incentive amount. This limitation will prevent customers from using a permitted size increase to obtain a greater upfront incentive and is appropriate because the purpose of allowing these increases is to accommodate project modifications, not to provide an opportunity to increase the upfront value of a legacy incentive award.
  10. Page 49 of 69

    Docket No. 26-08-05 Page 47 Allowing increases of up to 5% regardless of the underlying reason will reduce administrative burden and promote consistent application of the Program requirements. Requiring the Program Administrators to determine whether each proposed increase resulted from an “unavoidable” circumstance would require case-by-case judgments and could lead to inconsistent treatment of similarly situated projects. A defined 5% threshold instead provides a clear, administrable standard. Accordingly, change orders for projects approved under a now-closed legacy tranche, but not yet completed, will be allowed to increase system size by up to 5% for any reason. Any increase greater than 5% shall require the entire project to transition to the current applicable incentive rate. 3. Insurance Requirements The Program Administrators revised the ESS Program’s insurance requirements for contractors and TPOs to provide greater flexibility for different types of businesses. Program Administrator Order No. 3 Compliance, Aug. 3, 2026, Att. 4, p. 4. Specifically, the Program Administrators proposed removing the requirements that contractors and TPOs maintain automobile and workers’ compensation insurance. Id. OCC expressed concern that reducing the Program’s insurance requirements could shift additional risk to customers or ratepayers. OCC Comments, Aug. 28, 2026, p. 2. The Authority rejects this proposed change. The ESS Program has required contractors and TPOs to maintain automobile and workers’ compensation insurance for several years. Motion No. 6, Jan. 23, 2023, Docket No. 22-08-05, ESS Clean Program Manual, p. 27. The Program Administrators have not demonstrated that circumstances have changed sufficiently to warrant removing these established requirements. Moreover, the Authority agrees with OCC that eliminating these insurance requirements could expose customers and ratepayers to additional risk. For example, an uninsured contractor involved in an automobile accident resulting in significant liability could face financial distress or be unable to continue operating. Such an outcome could reduce the availability of contractors to serve the Program, complicate the servicing of existing ESS projects, or impede the completion of pending projects. Maintaining appropriate insurance requirements provides an important safeguard against these potential risks without materially undermining the Program’s objectives. Accordingly, the Authority rejects the proposed elimination of the automobile and workers’ compensation insurance requirements. The Program Administrators shall retain the existing ESS Program requirements that contractors and TPOs maintain automobile and workers’ compensation insurance. 4. Add-on Storage The Program Administrators proposed a new process for allowing legacy passive dispatch customers to add new capacity to their existing energy storage systems. Program Administrator Order No. 3 Compliance, Aug. 3, 2026, Att. 4, p. 6. Specifically, the Program Administrators proposed allowing add-on capacity to participate in the ESS
No matches

As listed on the current system

Draft Decision, 10/29/2026 [26-08-05]