Docket No. 26-08-05 Page 46 Eversource was agnostic as to an appropriate threshold for increasing the size of an approved but unbuilt project. Eversource Interrog. Resp. CAE-18. Eversource noted that, from an interconnection perspective, projects are more commonly downsized than increased as a result of study findings. Id. UI recommended against establishing a fixed percentage threshold for allowable system size increases. UI Interrog. Resp. CAE-18. UI argued that a fixed threshold could inadvertently restrict otherwise reasonable project modifications and create unnecessary barriers for customers whose projects are affected by circumstances beyond their control. Id. Similarly, CGB opposed establishing a specific threshold, arguing that Program Administrator discretion would be more appropriate given the variety of circumstances that could necessitate a system size increase. CGB Interrog. Resp. CAE-18. Nevertheless, CGB stated that, if the Authority requires a fixed percentage threshold, the threshold should be no more than a 50% increase in kW. Id. CGB also anticipated that many change orders would instead result in system size reductions due to interconnection restrictions. Id. The Authority will allow customers with projects approved under a now-closed legacy tranche, but not yet installed, to submit change orders to increase system size. However, such increases should be subject to a reasonable limit. The Authority is particularly concerned that, absent a defined threshold, significant increases in system size could be permitted while allowing projects to retain legacy incentive rates. Accordingly, the Authority will allow projects approved under a now-closed legacy tranche, but not yet installed, to increase their system size by no more than 5% for any reason. The 5% threshold is consistent with size-related allowances under Connecticut’s other renewable energy programs. The Non-Residential Renewable Energy Solutions (NRES) Program allows projects to increase their system size by up to 5% of the original approved bid size, regardless of the reason for the increase. Motion No. 11, Jan. 9, 2026, Docket No. 25-08-03, Annual Non-Residential Renewable Energy Solutions Program Review – Year 5, Att. 2a, p. 32. Similarly, the Residential Renewable Energy Solutions (RRES) Program allows a system’s expected annual production to exceed a customer’s highest annual consumption over any 12-month period within the preceding five years by no more than 5% for any reason. EDC Compliance, Ja. 22, 2026, Docket No. 25-08-02, Annual Residential Renewable Energy Solutions Program Review and Rate Setting – Year 5, Att. 1b, p. 25. Establishing a consistent 5% threshold across Connecticut’s clean energy programs will reduce developer confusion, promote uniformity, and facilitate consistent administration. For all projects, an increase of up to 5% shall not result in an increase to the project’s previously approved upfront or enrollment incentive amount. This limitation will prevent customers from using a permitted size increase to obtain a greater upfront incentive and is appropriate because the purpose of allowing these increases is to accommodate project modifications, not to provide an opportunity to increase the upfront value of a legacy incentive award.Page 49 of 69
Docket No. 26-08-05 Page 47 Allowing increases of up to 5% regardless of the underlying reason will reduce administrative burden and promote consistent application of the Program requirements. Requiring the Program Administrators to determine whether each proposed increase resulted from an “unavoidable” circumstance would require case-by-case judgments and could lead to inconsistent treatment of similarly situated projects. A defined 5% threshold instead provides a clear, administrable standard. Accordingly, change orders for projects approved under a now-closed legacy tranche, but not yet completed, will be allowed to increase system size by up to 5% for any reason. Any increase greater than 5% shall require the entire project to transition to the current applicable incentive rate. 3. Insurance Requirements The Program Administrators revised the ESS Program’s insurance requirements for contractors and TPOs to provide greater flexibility for different types of businesses. Program Administrator Order No. 3 Compliance, Aug. 3, 2026, Att. 4, p. 4. Specifically, the Program Administrators proposed removing the requirements that contractors and TPOs maintain automobile and workers’ compensation insurance. Id. OCC expressed concern that reducing the Program’s insurance requirements could shift additional risk to customers or ratepayers. OCC Comments, Aug. 28, 2026, p. 2. The Authority rejects this proposed change. The ESS Program has required contractors and TPOs to maintain automobile and workers’ compensation insurance for several years. Motion No. 6, Jan. 23, 2023, Docket No. 22-08-05, ESS Clean Program Manual, p. 27. The Program Administrators have not demonstrated that circumstances have changed sufficiently to warrant removing these established requirements. Moreover, the Authority agrees with OCC that eliminating these insurance requirements could expose customers and ratepayers to additional risk. For example, an uninsured contractor involved in an automobile accident resulting in significant liability could face financial distress or be unable to continue operating. Such an outcome could reduce the availability of contractors to serve the Program, complicate the servicing of existing ESS projects, or impede the completion of pending projects. Maintaining appropriate insurance requirements provides an important safeguard against these potential risks without materially undermining the Program’s objectives. Accordingly, the Authority rejects the proposed elimination of the automobile and workers’ compensation insurance requirements. The Program Administrators shall retain the existing ESS Program requirements that contractors and TPOs maintain automobile and workers’ compensation insurance. 4. Add-on Storage The Program Administrators proposed a new process for allowing legacy passive dispatch customers to add new capacity to their existing energy storage systems. Program Administrator Order No. 3 Compliance, Aug. 3, 2026, Att. 4, p. 6. Specifically, the Program Administrators proposed allowing add-on capacity to participate in the ESSPage 50 of 69
Docket No. 26-08-05 Page 48 Program on a case-by-case basis, provided that the add-on does not interfere with the existing capacity. Id. The Program Administrators proposed two potential approaches: (1) the customer would repay a prorated portion of the upfront passive dispatch incentive to CGB and convert the entire legacy and add-on project to Construct 5, or the applicable current incentive rate at the time of application; or (2) CGB would calculate a blended performance incentive rate based on the weighted average of the kWh capacity enrolled in passive dispatch and Construct 5, which have different performance incentive rates. Id. Earthlight stated that it has received significant interest from passive dispatch customers seeking to add energy storage capacity to their existing installations. Earthlight Comments, Aug. 28, 2026, p. 3. Earthlight recommended two pathways for system owners seeking to add storage capacity. Id., p. 4. Under the first pathway, customers could add capacity under the same legacy program as the originally installed storage. Id. The add-on capacity would not receive an enrollment incentive, but the entire storage system would be eligible for dispatch under the legacy performance incentive compensation structure. Id. Under the second pathway, customers could add capacity and reenroll their existing legacy capacity in Construct 5. Earthlight Comments, Aug. 28, 2026, p. 4. The entire storage system would then be eligible to participate under the Construct 5 active dispatch compensation structure, with the customer repaying a prorated portion of the original upfront incentive to CGB in exchange for the performance and enrollment incentives available under Construct 5. Id. OCC expressed concern that the Program Administrators’ proposed blended performance incentive rate for add-on capacity, which would allow customers to retain their legacy enrollment, is inconsistent with the rationale for phasing out passive dispatch and transitioning customers to Construct 5. OCC Comments, Aug. 28, 2026, p. 2. The Authority allows legacy projects to add storage capacity and transition the entire project to the Construct 5 performance incentive rates, or the performance incentive rates then in effect, subject to the following conditions. First, the customer shall repay a prorated portion of the original upfront incentive, calculated based on the remaining years of the Program. Second, any applicable clawback fees shall be repaid to the Program Administrators. Third, any Construct 5 enrollment incentive shall apply only to the addon capacity and not to the existing legacy capacity. This approach allows legacy customers to expand their systems while providing a clear pathway for transitioning the entire project from passive dispatch to the current compensation structure. The Authority will not, however, allow add-on capacity to participate under the blended performance incentive rate proposed by the Program Administrators. Allowing a legacy project to retain its passive dispatch enrollment while receiving a blended performance incentive would perpetuate the passive dispatch structure that the Authority has determined should be phased out in favor of compensation based more directly on actual performance. Moreover, the proposed blended approach would require the calculation and administration of individualized performance incentive rates based on the relative amounts of legacy and Construct 5 capacity in each project. Such individualizedPage 51 of 69
Docket No. 26-08-05 Page 49 rates could introduce unnecessary complexity into Program administration and EDC payment processes and potentially increase costs borne by ratepayers. Allowing legacy customers to add capacity through conversion to Construct 5 provides a clearer and more administratively efficient framework while advancing the transition away from passive dispatch. As discussed in the Year 5 Decision, passive dispatch has presented pervasive compliance issues, technical challenges, and substantial clawback risks for participants. See Year 5 Decision, pp. 9, 30. Allowing customers to expand their systems while transitioning the entire project to Construct 5 is therefore consistent with the Authority’s prior determination to move the ESS Program toward greater performance-based compensation. Accordingly, the Program Administrators shall remove the blended performance incentive option for add-on capacity from the Program Manual. Legacy projects may add storage capacity only through the Construct 5 pathway described above, subject to repayment of the applicable prorated upfront incentive and any applicable clawback fees. Any Construct 5 enrollment incentive shall apply only to the add-on capacity. 5. Telemetry Data Audits In Section 5.1 of their proposed Program Manual, the Program Administrators added the following sentence: “Any entity providing telemetry data in the Program may be subject to audits and/ or penalty fees, if data is not provided in the allowable timeframe and/or if there are data QC concerns.” Program Administrator Order No. 3 Compliance, Aug. 3, 2026, Att. 6, p. 53. The Program Administrators stated that this change would help address data quality and timeliness concerns and thereby advance the first and third Program Objectives. Program Administrator Order No. 3 Compliance, Aug. 3, 2026, Att. 4, p. 7. Base Power opposed adoption of the proposed sentence for several reasons. Base Power Comments, Aug. 28, 2026, pp. 3–4. Base Power expressed concern that the provision is overly vague because it does not define what duration of a data delay, or what type of “QC concern,” would trigger an audit or penalty fee; specify the amount or schedule of any penalty fee; provide a cure period before a penalty is assessed; or distinguish a telemetry provider’s failure from a data gap caused by the DERMS platform or another Program Administrator system outside the telemetry provider’s control. Id. Base Power argued that, absent these clarifications, the provision would create an openended compliance risk for Program participants. Id., p. 4. Base Power also noted that the Program Manual already accounts for missing telemetry data through the performance incentive calculation, under which lapsed data results in dispatch performance being measured as zero and therefore reduces the performance incentive earned. Id. The Authority supports efforts to improve the quality and timeliness of telemetry data. However, the proposed addition to Section 5.1 is insufficiently specific to establish a clear and predictable compliance standard. As Base Power noted, the provision does not identify the data delays or types of data quality concerns that would trigger an audit or penalty, establish the amount or methodology for calculating a penalty fee, provide anPage 52 of 69
Docket No. 26-08-05 Page 50 opportunity to cure an identified deficiency, establish how a penalty would be enforced in the event of nonpayment, or explain how responsibility would be assigned when a data deficiency results from a system or entity outside the telemetry provider’s control. These omissions create substantial uncertainty for Program participants and could result in inconsistent application and enforcement of the provision. The Authority therefore rejects the proposed addition to Section 5.1. Without greater specificity regarding the circumstances that would trigger a penalty, the applicable penalty amounts and enforcement procedures, opportunities to cure, and the allocation of responsibility for data deficiencies, the provision does not provide participants with sufficient notice of their obligations or establish a sufficiently clear framework for enforcement. Accordingly, the Program Administrators shall remove the proposed addition. Moreover, the Program Administrators already retain mechanisms to address telemetry data deficiencies. As recipients of telemetry data collected from OEMs through the DERMS, the Program Administrators retain the ability to audit such data. In addition, Section 4.3.6 allows the Program Administrators to place contractors, TPOs, aggregators, operators, payment beneficiaries, and OEMs on probation, suspend them, or terminate them if they fail to meet Program requirements, including requirements to provide telemetry data. Program Administrator Order No. 3 Compliance, Aug. 3, 2026, Att. 6, pp. 47–48. Given these existing enforcement mechanisms, the Authority is not persuaded that the Program Administrators have demonstrated a need for an additional, undefined penalty fee regime, particularly one that could create separate enforcement and collection issues in the event of nonpayment. However, the existing enforcement authority under Section 4.3.6 will be exercised judiciously. Although failure to provide telemetry data consistent with Program requirements may constitute grounds for probation or suspension, such actions should not be taken lightly. The Authority expects the Program Administrators to provide participants with a reasonable opportunity to identify and correct deficiencies before taking such significant enforcement action and to assign responsibility to the entity actually responsible for the underlying issue. The Authority agrees that telemetry data quality and timeliness are important considerations. Accurate and timely telemetry data is necessary for calculating performance incentive payments and conducting the Program’s BCA. Accordingly, the Program Administrators may propose revisions to Section 5.1 in the next annual review to address the data quality and timeliness concerns underlying this year’s proposed addition. The Program Administrators may also consider alternative solutions not previously explored, such as methods for obtaining API access directly from inverters. Any such proposal, however, should be substantially more developed and specific, including clear standards for triggering audits or penalties, the applicable penalty structure and enforcement procedures, opportunities to cure deficiencies, and a process for determining responsibility for data deficiencies.Page 53 of 69
Docket No. 26-08-05 Page 51 6. Miscellaneous The Authority addresses two additional changes to the Program Manual that require correction. First, Table 1 of the ESS Program Manual, which identifies tranche capacity, contains an incorrect MW total for Construct 5. Program Administrator Order No. 3 Compliance, Aug. 3, 2026, Att. 5, p. 8. Specifically, Table 1 identifies 140 MW of commercial capacity under Construct 5 and 290 MW under the legacy program. Id. However, as of August 20, 2026, the Program website identifies only 111.6 MW of commercial capacity remaining across tranches one through three.12 The Year 2 Decision established that any canceled or vacated capacity from earlier tranches would be moved to the final tranche of the Program. Year 2 Decision, p. 33. The Authority has not modified or reversed this determination. Accordingly, the capacity totals in Table 1 should be revised to reflect the Authority’s prior determination. The legacy Program column shall include only active projects approved under the legacy tranches that have not been canceled or moved to Construct 5, while the Construct 5 column should be increased to include all unused or vacated capacity from the earlier legacy tranches. Second, the Program Administrators moved the passive dispatch provisions to a supplement near the end of the Program Manual because passive dispatch is no longer available to new customers. Program Administrator Order No. 3 Compliance, Aug. 3, 2026, Att. 2, p. 3. The Authority supports this organizational change because it makes the Program Manual clearer and easier for stakeholders to navigate. However, the Program Administrators inadvertently retained Table 8, which displays the upfront incentive adder amounts associated with passive dispatch. Program Administrator Order No. 3 Compliance, Aug. 3, 2026, Att. 5, p. 47. Retaining Table 8 while removing the other passive dispatch provisions and references to the associated upfront incentives could create confusion and lead customers to incorrectly conclude that the incentive adders in Table 8 apply to Construct 5 participants. Accordingly, the Program Administrators shall remove Table 8 from the main body of the Program Manual. 7. Updated Documents The Authority directs the Program Administrators to ensure that the final updated Program documents, filed in accordance with this Decision, accurately reflect the Authority’s determinations, including those in Sections IV.B., Bidirectional EV Participation, IV.C., Enrollment Incentive Clawback, and IV.F., Program Redline and Recommended Changes. By December 21, 2026, the Program Administrators shall file the updated ESS Program documents, including the Program Manual, for the Authority's review and 12 See https://energystoragect.com/ess-performance-report/ (page 3, C&I Tranche Capacity).Page 54 of 69
Docket No. 26-08-05 Page 52 approval. The filing must include both clean and redlined versions of all ESS Program documents, incorporating the modifications approved in this Decision. V. CONCLUSION AND ORDERS A. CONCLUSION The Authority approves several changes to the ESS Program to better serve the Program Objectives and provides several additional clarifications for stakeholders. B. EXISTING AND NEW ORDERS For the following Orders, the Company shall file an electronic version through the Authority’s website at www.ct.gov/pura. Submissions filed in compliance with the Authority’s Orders must be identified by all three of the following: Docket Number, Title, and Order Number. Compliance with orders shall commence and continue as indicated in each specific Order or until the Company requests and the Authority approves that the Company’s compliance is no longer required after a certain date. All Orders requiring Authority review and approval shall be submitted as a motion. The below standing orders are a summation of prior orders related to the ESS Program that continue to apply. In some instances, the Authority has amended those standing orders with redline edits. Additionally, given the Program’s maturity and the implementation of Construct 5 last year, Standing Order Nos. 2 and 7 are rescinded. The below new orders apply on a going forward basis. 1. Standing Orders to be filed in ESS Annual Review Dockets 1. Reference Decision, July 28, 2021, Docket No. 17-12-03RE03, Order No. 8, p. 52: No later than October 1, 2021, and by August 1 annually thereafter until the ESS Program stops accepting new enrollments, the EDCs shall submit as a compliance filing in the most recent annual review proceeding a map of circuits that meet the grid edge criteria in Section III.D. The EDCs shall include the map in all relevant Program documentation and on the EDCs’ respective Program webpages. 2. Reference Decision, July 28, 2021, Docket No. 17-12-03RE03, Order No. 12, p. 52: No later than October 1, 2021, the EDCs shall provide a list of all electric storage systems that are eligible for the Program in Docket No. 21-08-05. Any updates shall be submitted in the appropriate Annual or Program Review docket by August 1, and annually thereafter until the ESS Program stops accepting new enrollments, as applicable. 3. Reference Decision, Dec. 21, 2022, Docket No. 22-08-05, Order No. 3, p. 38: No later than August 1, 2022, and annually thereafter until the ESS Program stops accepting new enrollments, the Program Administrators shall submit an annual report summarizing the Program results to date, including an updated BCA using AESC counterfactual one and an updated BCA calculator and including a CTspecific RIM score, and recommendations for any Program modifications to the ESS Program documents including the Program Manual, providing both a cleanPage 55 of 69
Docket No. 26-08-05 Page 53 and a redlined version of all documents and an accompanying narrative document explaining how the recommended changes would help achieve the Program Objectives, which may also be the annual report, in the relevant Annual Review proceeding (i.e., in Docket No. 23-08-05 on August 1, 2023, etc.). The Program Administrators shall include active dispatch only projects in the Program’s total 580 MW deployment goal, and the Program Administrators shall exclude active dispatch only projects from the Program’s Tranche and incentive step MW capacity limits. Further, the Program Administrators shall track total active dispatch only project MW deployment and include such information in the annual report filed with the Authority. Last, the Program Administrators shall include all DERMS fees paid to support the Program by each DERMS provider in an aggregate or total amount, and data on instances where a system could not perform due to OEM-triggered severe storm events called during uncanceled passive dispatch hours. 4. Reference Decision, July 28, 2021, Docket No. 17-12-03RE03, Order No. 25, p. 53: No later than June 15, 2024, and every three years thereafter until the ESS Program stops accepting new enrollments, the Program Administrators shall submit the EM&V consultant’s full report on the established Program metrics into the relevant Program Review proceeding. 5. Reference Decision, Dec. 17, 2025, Docket No. 25-08-05, Order No. 5, pp. 56-57: Each Program Administrator shall submit their prudently incurred costs associated with the administration of the Program in a given calendar year into the subsequent year’s annual review of the Revenue Adjustment Mechanism (RAM) (e.g., costs incurred in 2023 by UI shall be submitted into the 2024 RAM proceeding). The EDCs shall submit such costs into their individual RAM review docket, whereas the CGB may seek recovery of ESS Program costs that have not yet been incurred for the Program year of the RAM proceeding in which they are filing, in accordance with the guidance set forth in Section IV.N. of the Year 3 Decision. Further, CGB shall submit its detailed cost estimates for the subsequent Program year by January 15, and annually thereafter, into both dockets splitting its costs between Eversource and UI based on the proportion of megawatts deployed in each EDC’s respective service territory. Additionally, CGB shall include the total amount of collected commercial application fees in its annual RAM filing, deducting the corresponding fee revenues from its Program administrative costs. Finally, repayment of the unearned incentive through CGB Proposal 2 must occur in full through the first available RAM cycle and shall not be spread over multiple years as CGB gradually collects performance payments. For example, if an existing passive dispatch project transitions to CGB Proposal 2 in 2026, CGB must return the full amount of the unearned upfront incentive to ratepayers in the 2027 RAM cycle as a part of its annual Order No. 5 filing. Specifically, CGB shall deduct the value of previously disbursed but unearned upfront incentive payments from its total program administrative costs—documenting this as a distinct cost line item— prior to seeking program administration cost recovery from the EDCs through the RAM process.Page 56 of 69
Docket No. 26-08-05 Page 54 6. Reference Decision, July 28, 2021, Docket No. 17-12-03RE03, Order No. 24, p. 53: No later than January 1, 2023, the Program Administrators shall publish a website containing all relevant Program data, incorporating all direction provided in Section V.D. 7. Reference Decision, Dec. 8, 2021, Docket No. 21-08-05, Order No. 9, p. 40: No later than August 1, 2022, and annually thereafter until the ESS Program stops accepting new enrollments, the Program Administrators shall submit its compliance with Order No. 22 of the Storage Decision, incorporating the direction provided in Sections IV.B.2. and V.A.4.iii. of this Decision. 8. Reference Decision, Dec. 21, 2022, Docket No. 22-08-05, Order No. 15, p. 41: No later than August 1, 2024, and annually thereafter until the ESS Program stops accepting new enrollments, CGB shall file all project cancellation data for the Authority’s review in the relevant ESS annual review docket. The cancellation data must show which tranche the canceled projects were selected for, as well as the reasons behind the project cancellations, if known by the Program Administrators. 9. Reference Decision, Dec. 21, 2022, Docket No. 22-08-05, Order No. 16, p. 41: No later than 30 days from DAS adoption of an updated building code that incorporates best practices for electric storage, and annually thereafter, the Program Administrators shall file as compliance with the Authority the current best guidance on siting, local permitting, and safety for local officials and developers on FTM and behind-the-meter storage construction and development. Such guidance shall be developed in consultation with relevant state agencies, including DAS, DEEP, and the Siting Council. Such guidance shall also be provided on the ESS Program’s website. A link to such guidance shall be provided to the Authority as a part of the compliance filing. Upon the fulfillment of this order, the Energy Storage Siting Resource shall be updated to incorporate any new siting guidance from DAS. 10. Reference Decision, Nov. 29, 2023, Docket No. 23-08-05, Order No. 18, p. 60: No later than January 5, 2024, and annually thereafter until the ESS Program stops accepting new enrollments, CGB shall provide updated fact sheets for both residential and C&I customers for the ESS Program that reflect the program modifications as directed in the most recent Final Decision issued through the ESS Program Annual Review proceeding, Docket No. XX-08-05. 11. Reference Decision, Nov. 29, 2023, Docket No. 23-08-05, Order No. 20, pp. 6061: No later than April 1, 2024, the Program Administrators shall create an educational resource (Energy Storage Siting Resource) for Program participants compiling existing, publicly available resources regarding any applicable flood proofing, building code, safety, and siting requirements affecting residential and commercial ESS projects and providing relevant state and municipal contact information, which need not be exhaustive (e.g., “the relevant department in most municipalities are X, Y, Z”). For clarity, such resource shall simply aggregatePage 57 of 69
Docket No. 26-08-05 Page 55 publicly available resources into one place for developer ease of access. The Program Administrators shall file the Energy Storage Siting Resource in the present docket, after which the resource shall be published on the ESS website. Further, the Energy Storage Siting Resource shall be updated when Order 10 of the Year 3 Decision is fulfilled, after a new building code for energy storage projects is adopted statewide, and annually thereafter until the ESS Program stops accepting new enrollments, to ensure the Resource remains up to date and relevant for Program developers. The Program Administrators shall file as compliance with the Authority in the applicable ESS proceeding (i.e., for 2024, Docket No. 24-08-05) any future updates to the Energy Storage Siting Resource. 12. Reference Decision, Nov. 29, 2023, Docket No. 23-08-05, Order No. 24, p. 62: No later than August 1, 2024, and annually thereafter until the ESS Program stops accepting new enrollments, CGB shall file as compliance in the applicable annual review proceeding (i.e., in 2024, Docket No. 24-08-05) the average participant cost test (PCT) broken out by customer type, project size category, and Program developer for both residential and commercial customer projects, utilizing all information available to CGB, including Performance Incentive Fee data, to ensure an accurate accounting of the PCT. The PCT shall also specifically be conducted from the perspective of the host customer; to the extent that this necessitates a change from the methodology that has historically been applied, CGB shall submit PCT values calculated using both the historical methodology and the customerfocused methodology. 13. Reference Decision, Nov. 29, 2023, Docket No. 23-08-05, Order No. 25, p. 62: No later than August 1, 2024, and annually thereafter until the ESS Program stops accepting new enrollments, the Program Administrators shall file as compliance in the applicable annual review proceeding (i.e., in 2024, Docket No. 24-08-05) a summary of the Performance Incentive Fees for all residential projects deployed through the end of the previous month (e.g., through July 2024 for the August 1, 2024 filing) by developer, following all direction contained in Section IV.G. 14. Reference Decision, Nov. 29, 2023, Docket No. 23-08-05, Order No. 26, p. 62: No later than August 1, 2024, and annually thereafter until the ESS Program stops accepting new enrollments, each EDC shall file as compliance an ESS Interconnection Report, as detailed in Section IV.D., in the applicable annual review proceeding (i.e., in 2024, Docket No. 24-08-05). The Report shall consist of a summary of the state of interconnection for all commercial ESS projects and shall include, at a minimum: (1) the interconnection status of each commercial ESS project; (2) the expected EDC interconnection approval due date for each commercial project per EDC interconnection guidelines, as applicable; (3) the date all required interconnection materials were submitted to the utility for each commercial ESS project; (4) the number of days from when all required interconnection materials were submitted to the utility for each commercial ESS project up to the completion of the interconnection process; (5) the attrition rate for all commercial ESS projects, based on the withdrawal of a project’s
As listed on the current system