  1. Page 21 of 46

    Docket No. 26-08-06 Page 17 . Table 7: Authority-Calculated 2027 Deployment Targets Program Area Residential SingleFamily (Level 2) Multi-Unit Dwellings (Level 2) Destination (Level 2) Workplace/Light-Duty Fleets (Level 2) Direct-Current Fast Chargers (DCFCs) Totals B. Per-Site Incentive Baseline Per-Site Incentive Underserved Historical Per-Port Incentive12 - $ 1,500 $ 1,500 360 $ $ $ 20,000 20,000 $ $ 40,000 40,000 $ $ 11,977 9,957 1,190 218 $ 14,252,630 $ 2,170,626 $ 20,000 $ 40,000 $ 6,788 333 $ $ 150,000 $ 250,000 $ 56,987 10 2,111 $ 569,870 $ 19,793,530 Port Targets Budget (Fully Subscribed) 540,000 2,260,404 DCFC UPTIME REQUIREMENT AND ENFORCEMENT STRUCTURE On February 2, 2026, the EDCs proposed an uptime requirement, as defined and required as part of NEVI at 23 C.F.R. § 680.116(b), for DCFC installations awarded after January 1, 2027. Motion No. 1, p. 1. The EDCs recommended that the Terms and Conditions of the commercial program, which already require that participants authorize the EVSE manufacturer/network integrator to provide the utility with “Utilization Data” and “Financial Data,” should be amended to also require “Uptime Data,” mirroring the current requirements of the NEVI program. Id., p. 2. The EDCs proposed Uptime Data be reported every six months to align with NEVI requirements. Id., p. 3. Finally, the EDCs proposed that the enforcement mechanism for compliance with the uptime requirement be a monetary penalty imposed by EOE. Id., p. 7. To solicit feedback on Motion No. 1, the Authority issued a Notice of Request for Written Comments for docket participants to provide comments on the EDCs’ uptime requirement proposal. Notice of Written Comments, Docket No. 26-08-06, February 9, 2026. The Authority received responses from DEEP, OCC, and Save the Sound. DEEP Comments, March 2, 2026; OCC Comments, March 2, 2026; Save the Sound Comments, March 2, 2026. Subsequently, the Authority issued a second Notice of Request for Written Comments on July 9, 2026, for docket participants to provide comments on a modified version of the EDCs’ uptime proposal. Notice of Written Comments, Docket no. 20-08- 12 Because the deployment targets are by port, in order to calculate new deployment targets that adhere to the Statutory Expense Cap, the historical per-port incentives must be used. The EDCs provided the historical per-port incentives in Annual Report, Att. 10a, Table 6; Table 8.
  2. Page 22 of 46

    Docket No. 26-08-06 Page 18 06, July 9, 2026. The Authority received responses from UI, ev.energy, OCC, and Save the Sound. The Authority appreciates the EDCs’ proposal as well as the thoughtful feedback from stakeholders on this matter throughout this proceeding. However, while the DCFC category of the Program will continue, the Authority has determined in Section IV.A.4 of this Decision that the DCFC category will be winding down and future deployments will be limited in scale and targeted to geographic areas that lack DCFC infrastructure. Since the NEVI uptime requirements would apply to incentive Terms and Conditions moving forward only, this proposal would create different operating requirements for a smaller number of DCFC installations yet to enter the program, may create an additional barrier to host site and contractor participation and ultimately, may be at odds with the goal of filling geographic DCFC gaps. Given the relatively limited remaining deployment targets for DCFC, the costs associated with enforcing an uptime requirement also might not drive commensurate benefits. While the Authority supports the spirit of the proposal to adopt NEVI uptime requirements, it is impractical to develop and enforce these new requirements on a limited number of projects as the DCFC incentive program area winds down in the coming years. Accordingly, the Authority denies Motion No. 1. C. EDC COMMERCIAL PROGRAM RECOMMENDATIONS 1. Level 2 EVSE Application Process In Docket No. 25-08-06 the EDCs proposed to adopt the DCFC application process for the Level 2 EVSE Program Areas. Year 5 Decision, p. 10. DCFC applications are accepted in a defined application window, are scored according to a prioritization criteria matrix, and incentives are awarded to the top scored applications until the annual DCFC port deployment target is reached. Id., pp. 10–11. The EDCs argued that adopting this application process for Level 2 EVSE is anticipated to “more precisely control spending and ensure an equitable” distribution of incentives for Level 2 EVSE Program Areas. Id., p. 11. In the Year 5 Decision, Order No. 18.b. directed the EDCs to submit: a proposal regarding Program incentives and deployment targets that includes the following: (1) a proposed methodology for a commercial Level 2 EVSE application process based on the existing DCFC application process, that includes a (a) proposed timeline, (b) prioritization criteria matrix with associated criteria weights, and (c) incentive distribution plan. Id., p. 53. In response to Order No. 18.b., the EDCs proposed the incentive distribution plan discussed in Section IV.A.2 of this Decision, and recommended maintaining a rolling application window for commercial Level 2 Program Areas. Annual Report, p. 38. Interviews conducted by the EDCs' Evaluation, Measurement & Verification (EM&V) Vendor, Demand Side Analytics (DSA), found that customers and contractors strongly prefer maintaining a rolling application window, as it provides the flexibility necessary to
  3. Page 23 of 46

    Docket No. 26-08-06 Page 19 plan and budget projects. Id. The interviewees indicated that moving to a fixed application period would create long windows where funding availability would be unknown, ultimately slowing market interest. Id. Additionally, the EDCs propose a minimum criteria threshold for projects within Level 2 EVSE Program Areas to qualify for incentives, ensuring that incentives are awarded to high-quality projects. Id. Potential minimum criteria include: Site Safety: • Security cameras covering the charging area; • Existing or proposed lighting of the charging area; • Appropriate directional and charger location signage; and • Accessible pedestrian pathways between charging stations and site amenities. Other Amenities: • Public restroom access; • Food and beverage options; • Retail establishments; and • Covered seating or waiting area. Annual Report, pp. 38–39. Stakeholders offered no comment on these specific EDC proposals. The Authority approves the EDCs proposal for maintaining a rolling application window for the commercial Level 2 Program Areas. This change is expected to provide a more flexible application and participation experience for applicants. Additionally, the Authority approves the minimum criteria listed by the EDCs related to Site Safety, however, those listed as Other Amenities shall not be used as minimum criteria. While the Site Safety criteria are important features to protect public use of the charging infrastructure and the investment of site hosts, the Other Amenities criteria create a higher bar for projects that could preclude otherwise adequate projects. 2. Level 2 Commercial Waitlist Process and Prioritization In the 2025 EV Charging Program proceeding, the EDCs recommended that waitlisted applications should only be valid through the end of the Program Year in which they applied, and that if they are not awarded incentive funds, they should reapply in the subsequent Program Year. Year 5 Decision, p. 18. The EDCs argued that this would allow applicants to understand differences in the Program from year-to-year (i.e., in response to the annual review proceedings) and agree to updated terms and conditions. Id. The Authority concurred and found it appropriate for waitlisted applications to expire at the end of each Program Year. Id. However, the Authority directed the EDCs to notify waitlisted applicants of the re-submission requirements. Id. Further, for each waitlisted applicant that is not awarded incentive funds, the EDCs were directed to inform such applicants that they will not receive funds and must re-submit their application in the
  4. Page 24 of 46

    Docket No. 26-08-06 Page 20 subsequent Program Year. Year 5 Decision, p. 18. Finally, the Authority directed the EDCs to prioritize any applications received from formerly waitlisted applicants above newly received applications in that Program Year. Id. In other words, a 2026 waitlisted application that re-applies in 2027 should be prioritized for review above new applications received in 2027 and likewise in subsequent years. Id. In response, the EDCs recommended establishing a standardized commercial Level 2 waitlist and prioritization process for 2026 projects and beyond. Annual Report, p. 53. Specifically, the EDCs recommend the following: Any projects remaining on the waitlist at the end of the program year shall expire and may be resubmitted during a defined reapplication period in the following program year. Prioritization of projects would only apply to waitlisted applications that reapplied by March 1 of the following year. To provide administrative certainty and facilitate timely allocation of available funding, such priority status would apply only during the first 60 days of the subsequent program year. To promote broad market participation and ensure funding opportunities are distributed among multiple market actors, no single contractor on the waitlist may account for more than 40% of the estimated charging ports allocated for the program year through the waitlist prioritization process. The waitlist would be limited to the number of projects that can reasonably be supported by the estimated funding available in the subsequent program year. This approach is intended to prevent the accumulation of an unmanageable backlog of unfunded projects and provide applicants with realistic expectations regarding the likelihood of future funding. Id. The EDCs state that “[s]tandardizing the waitlist prioritization process will improve program transparency, create more predictable outcomes for applicants, and facilitate efficient administration of the commercial charging program.” Id. Stakeholders offered no comment on this specific issue. The Authority approves the proposed process. The Authority directs the EDCs to report the number of waitlisted applicants in the 2027 Annual Report filing in Docket No. 27-08-06. 3. Restrictions on Stacked Funding To maximize the number of customers and charging ports supported through the EV Charging Program, the EDCs recommend that projects receiving funding from another source for the same eligible equipment or installation costs be ineligible for incentives through the commercial program. Annual Report, p. 53–54. Other sources of incentives may include, but are not limited to, the DEEP Volkswagen Settlement Program, the U.S.
  5. Page 25 of 46

    Docket No. 26-08-06 Page 21 Department of Energy Efficiency and Conservation Block Grant (EECBG) Program, and other federal, state, or local funding opportunities. Id., p. 53. The EDCs point out that currently, applicants may have access to multiple sources of funding for a single project, and there is a lack of clear program guidance regarding incentive stacking. Id. The EDCs expressed concern that stacking incentives may prevent available program funds from being allocated as efficiently as possible. Id. Alternatively, if incentive stacking is permitted, the EDCs recommend that total funding received from all sources should not exceed total project costs, and that applicants be required to disclose all anticipated and awarded funding sources during the application process. Annual Report, p. 54. Save the Sound supports the EDCs’ proposal to require that total funding from all sources should not exceed total project costs and applicants should disclose other funding sources during the application process. Save the Sound Comments, October 5, 2026, p. 2. However, Save the Sound does not take a position on whether stacking of incentives should altogether be allowed or prohibited. Id. The acquisition of project funding from more than one source is a common practice, not just in EV charger development, but across other types of development projects. However, as a matter of policy, providing funding in excess of total project costs is not in the public interest. Nor is it appropriate for ratepayers to support projects that can be incentivized to achieve program objectives by other funding sources. Accordingly, the Authority agrees with the EDCs’ alternative recommendation that applicants be required to disclose all anticipated and awarded funding sources during the application process to ensure that incentive funding received from all sources should not exceed total project costs. Moreover, consistent with principles of equity and efficiency that guide the design and implementation of ratepayer funded and budget limited programs, project development should not be over-incentivized. Thus, the Authority also finds that financial incentives received from other sources must commensurately offset the funding allocated from this program for project development. A project with alternative funding resources that exceed amounts provided through this program would not be eligible for any funding under this program. 4. Incentives for New Construction Stretch Building Codes General Statutes § 4b-77 requires the following: (b) On and after July 1, 2026, the Commissioner of Administrative Services shall require each new state facility that will include public parking spaces and is projected to cost more than one hundred thousand dollars to be constructed such that at least eight per cent of the designated parking spaces for cars at such new state facility are electric vehicle capable parking spaces. …
  6. Page 26 of 46

    Docket No. 26-08-06 Page 22 (d) On and after January 1, 2023, a municipality shall require each new construction of a commercial building or multiunit residential building with thirty or more designated parking spaces for cars or light duty trucks to include electric vehicle charging infrastructure that is capable of supporting level two electric vehicle charging stations or direct current fast charging stations in at least ten per cent of such parking spaces. A municipality may, through its legislative body, require any such commercial building or multiunit residential building to include such electric vehicle charging infrastructure in more than ten per cent of such parking spaces. General Statutes § 4b-77(b),(d). No later than January 1, 2029, and every three years thereafter, the Commissioners of Administrative Services, Transportation and Energy and Environmental Protection are required to jointly submit recommendations proposing an appropriate requirement for future electric vehicle charging infrastructure at new state facilities. General Statutes § 4b-77(c). The EDCs recommended that PURA consider the eligibility of projects subject to EV-ready building code requirements. Annual Report, p. 55. Specifically, the Authority should consider whether projects required by code to install EV-ready infrastructure should remain eligible for EV Program incentives; and whether incentives should be limited to infrastructure installed beyond minimum code requirements. Id. The EDCs have observed an increase in commercial EV program applications associated with new construction projects that are subject to these EV charging infrastructure or EV-ready electrical infrastructure. Id., p. 54. The EDCs argue that to maximize the impact of limited program funds, incentives should not be used for projects where EV charging infrastructure is required by law. Id., pp. 54–55. Incentivizing these projects would not expand Connecticut’s charging network by supporting new sites. Annual Report, pp. 54–55. “This raises an important policy question: if the project would move forward regardless of incentive funding, is the incentive influencing the investment decision, or is it simply subsidizing an activity that would have occurred anyway.” Id., p. 55. The EDCs assert that making projects subject to EV-ready building code requirements ineligible for Program incentives would help ensure the cost-effective use of limited program funds that are directed toward projects where incentives are a material driver of deployment. Id. Save the Sound stated that subsidizing activity that is legally required, and would occur with or without incentives, is not the best use of ratepayer funds. Save the Sound Comments, Oct. 5, 2026, pp. 2–3. The Authority agrees with the EDCs and Save the Sound that funding EV charging projects that are legally required, and would occur with or without Program incentives, is not a sound use of ratepayer funds. The Program Objectives, stated in Section III of this Decision, aim to enable Connecticut’s deployment of EVs, remove barriers to the growth of Connecticut’s clean energy economy, and achieve an equitable transition to wide-scale EV deployment, among other objectives. Using ratepayer funds for EV charging projects that would otherwise be required would not serve to advance those objectives and simply
  7. Page 27 of 46

    Docket No. 26-08-06 Page 23 rewards “free riders.” Accordingly, the Authority accepts the EDCs’ recommendation to disallow projects required by code to install EV-ready infrastructure from eligibility for EV Program incentives. D. RESIDENTIAL PROGRAM RECOMMENDATIONS 1. Residential Managed Charging Enrollment Incentive The EV Charging Program requires every customer who receives Residential Single-Family Level 2 EVSE and/or wiring upgrade incentives to participate in the residential managed charging program. EV Decision, p. 15 (requires participation for Level 2 EVSE incentives); Year 1 Decision, p. 16 (requires participation for wiring upgrade incentives). While upfront equipment incentives and managed charging incentives typically target different outcomes, here the two are necessarily connected in terms of Program Outcomes as well as the current incentive structure (i.e., residential upfront equipment incentives require managed charging participation). A majority of the customers currently enrolled in the residential managed charging program received upfront incentives on a Level 2 EVSE and/or a wiring upgrade, which requires managed charging enrollment. Year 5 EV Decision, p. 21. As such, the Authority questioned whether the new Residential Single-Family Level 2 EVSE and wiring upgrade incentive income eligibility requirements, pursuant to Public Act No. 25-173,13 will also significantly reduce the number of residential managed charging program participants. Id., p. 21. Further, the Authority questioned whether the $100 managed charging enrollment incentive would be sufficient to continue robust managed charging participation, or whether it should be modified. Id. In the Year 5 Decision, the Authority found that while the $100 managed charging enrollment incentive may be appropriate to incentivize EV driver enrollment in the managed charging program, the concern remains that the large reduction in estimated Residential Single-Family upfront incentive participation due to the income eligibility requirements might negatively impact managed charging enrollment, necessitating that the enrollment incentive, or other relevant Program structures, be re-examined. Id., p. 22. 13 “[F]urther limit any expenses for electric vehicle charging stations and customer wiring upgrades incentivized as part of any residential single-family customer program to residents who make less than or equal to three hundred per cent of the federal poverty level or reside in any concentrated poverty census tract, as defined in section 32-7x.” General Statutes § 16-244dd(b).
  8. Page 28 of 46

    Docket No. 26-08-06 Page 24 Table 7 shows that while customers who receive EVSE and/or wiring upgrade incentives through the program are not eligible for the one-time enrollment incentive for managed charging, customers who do not receive EVSE and/or wiring upgrade incentives through the program are eligible for the $100.
  9. Page 29 of 46

    Docket No. 26-08-06 Page 25 Table 7: Modified Residential Single-Family Program Upfront Rebates and Incentives Customer Scenario New Networked L2 Charger Existing Networked L2 Charger Telematics with NonNetworked L2 Charger Networked Level 2 Charger Rebate Needs 240v Outlet Wiring Upgrade to 240v Rebate Up to $1,500 One-Time Enrollment Incentive - Has 240v Outlet Up to $1,500 - - Already installed - - $100 Needs 240v Outlet - Up to $1,500 - Has 240v Outlet - - $100 Year 5 EV Decision, pp. 17, 24–26. The Authority directed the EDCs to file a report summarizing the effects, if any, of the reduced pool of Residential Single-Family upfront EVSE and wiring upgrade incentives on new managed charging enrollments during the 2026 Program Year. Year 5 Decision, p. 22; 54 (Order No. 18.c.). Additionally, the Authority directed the EDCs to include a re-examination of the appropriateness of the $100 managed charging enrollment incentives, or other relevant Program components, in motivating EV driver enrollment in the managed charging program. Id. Due to the program changes that went into effect in January 2026, there are fewer equipment and wiring rebates being processed, but managed charging participation continues to be subscribed. Annual Report, p. 33. However, managed charging-only participants represent 88% of participants for Eversource and 92% of participants for UI. Annual Report, p. 31. The EDCs recommended maintaining the $100 managed charging enrollment incentive to support program growth in 2027, but recommend revisiting the topic later in 2027 as more data are available. Annual Report, p. 33. Ev.energy supports the retention of the $100 enrollment incentive for managed charging. Ev.energy Comments, October 5, 2026, p. 4. Ev.energy noted that industry research and evaluation of other programs has shown enrollment incentives to encourage program participation, although it is unclear how varying amounts affect program enrollment rates, and how different amounts vary across marketing channels. Id., pp. 4– 5. Ev.energy has partnered with a higher education institute to study the impact of different incentive rates on enrollment rates and anticipates initial results could be made available in early 2027. Id., p. 5.
  10. Page 30 of 46

    Docket No. 26-08-06 Page 26 Save the Sound supports continuation of the $100 enrollment incentive to help prevent further decline in program enrollment following legislative changes. Save the Sound Comments, October 5, 2026, p. 1. With fewer EVSE and wiring rebates being processed in 2026, the ability of the managed charging program to enroll customers who are receiving Program incentives is likewise reduced. This change necessitates maintaining separate incentives in order to encourage managed charging enrollment. Both the EDCs and stakeholders recommend maintaining the current $100 enrollment incentive to maintain current managed charging enrollment levels. The Authority agrees. Moreover, additional data and analysis on the appropriate residential managed charging enrollment incentive are welcome to inform future incentive levels. The Authority looks forward to reviewing ev.energy’s study on the impact of different incentive rates on enrollment rates in next year’s annual review. Accordingly, the Authority directs the EDCs to continue offering the $100 managed charging enrollment incentive for the 2027 Program year. 2. Incentive Flexibility Eversource proposed a workflow change to simplify the enrollment process for customers to sign up for managed charging. Annual Report, p. 59. According to Eversource, all customers would be allowed to enroll directly into managed charging through the DERMs, instead of being routed through the rebate portal first. Id. As the 2026 program eligibility requirements have reduced the number of customers who are eligible for EVSE and wiring rebates, the contemplated change would allow Eversource to offer the $100 managed charging enrollment incentive to all eligible customers, prior to directing the smaller pool of make-ready customers to the residential EVSE and wiring rebate application, which would be reduced from the current $1,500 to $1,400. Id. Eversource states that managed charging enrollment incentives would be processed more efficiently under its proposal. Id. As explained above in Section IV.D.1., Residential Managed Charging Enrollment Incentive, while customers who receive EVSE and/or wiring upgrade incentives through the program are not eligible for the one-time enrollment incentive for managed charging, customers who do not receive EVSE and/or wiring upgrade incentives through the program are eligible for the $100 enrollment incentive. Save the Sound questioned the added value of the EDC’s proposed approach in practice, suggesting that routing customers through the DERMS portal first would resolve much of the issue. Save the Sound Comments, October 5, 2026, p. 2. Save the Sound argues that, while the proposed change is intended to avoid customer delays that may result from additional review, a review would be required before installing the charging infrastructure to facilitate managed charging. Id. Finally, Save the Sound is concerned that reclassifying a portion of the infrastructure rebate as a managed charging incentive will create confusion for both customers and policymakers around program design and funding utilization. Id. The Authority agrees with Save the Sound that reclassifying a portion of the infrastructure rebate as a managed charging incentive may create confusion for all