Motion No. 002
Motion for Authorization to Install Additional Facilities Under and Over Certain PROW
Filed by Fiber AssetCo, LLC dba Zayo1 file
Part of docket 26-09-20Files1
Docket No. 26-09-20-Fiber AssetCo, LLC dba Zayo Motion No. 2-11.20.26.pdf
PDF · 7.9 MB · 63 pagesText searchable
Download Docket No. 26-09-20-Fiber AssetCo, LLC dba Zayo Motion No. 2-11.20.26.pdfRead the text of Docket No. 26-09-20-Fiber AssetCo, LLC dba Zayo Motion No. 2-11.20.26.pdf
Words on different pages
Every word of Eversource rate increase is in the text below, but not all on one page. Pages with any of them are listed and highlighted. Clear highlighting
Page 1 of 63
43 Broad Street | P.O. Box 58 New London, CT 06320-0058 Tel: [phone removed] Fax: [phone removed] www.tcors.com November 20, 2026 Via Electronic Filing Jeffrey R. Gaudiosi, Esq. Executive Secretary Public Utilities Regulatory Authority 10 Franklin Square New Britain, CT 06051 Re: Docket No. 26-09-20 Application of Fiber AssetCo, LLC d/b/a Zayo for Authorization to Install Additional Facilities Under and Over Certain Public Rights-of-Way Motion No. 2 Dear Mr. Gaudiosi: Enclosed please find the following items submitted in connection with the above-referenced docket: • An Application by Fiber AssetCo, LLC d/b/a Zayo for Authorization to Install Additional Facilities in the Public Rights-of-Way (“Application” or “Motion No. 2”), a Non-Proprietary version of Attachment I to that Application, and an original of Attachment II to that Application. This Motion No. 2 is submitted less than 90 days prior to the date planned for the commencement of construction and as such, a waiver of the advance notification requirement is necessary. • An original of Attachment I to the Application containing street segments, route maps, descriptions or aerial maps has been included in an envelope labeled "Proprietary Material". This information is submitted subject to the terms and conditions of the Protective Order, in accordance with the approved Motion for Protective Order dated October 20, 2026 issued in this docket.Page 2 of 63
Please contact the undersigned with any questions about this filing. Very truly yours, Mark J. Cook, Esq. Counsel for Fiber AssetCo, LLC d/b/a Zayo Enclosures cc: Service ListPage 3 of 63
STATE OF CONNECTICUT PUBLIC UTILITIES REGULATORY AUTHORITY Wireline Facilities Installation Application Form Docket Number: Docket No. 26-09-20 Date: November 20, 2026 Enclosed is the Application for Approval of construction of additional wireline facilities within the Public Right-of-Way (Application). Please note that the Public Utilities Regulatory Authority (Authority) requires all filings to be submitted electronically. When filing the Application, the following must be provided: • Electronic: one (1) copy of the Application, including all Attachments. First-time Applicants must file the Application as a New Docket Application in the Authority’s Web Filing System. Applicants who have previously been approved to construct facilities shall file the Application as a motion in the Applicant’s primary wireline attachment docket. The Authority will make reasonable efforts to issue its Decision regarding the Application no later than 60 days after the Application is accepted. Instructions regarding electronic filing with the Authority can be found under the following website, https://portal.ct.gov/PURA/About/Filing-and-Forms/Electronic-Filing. If you need assistance in completing this application or with the application process, please contact the Office of Education, Outreach and Enforcement (EOE) via: Toll Free Number (in Connecticut) [phone removed] Toll Number Outside Connecticut 1-860827-2622 Email: [email removed] Enclosed: ApplicationPage 4 of 63
State of Connecticut Public Utilities Regulatory Authority 10 Franklin Square New Britain, CT 06051 Phone: [phone removed]; Main Fax: [phone removed] http://www.ct.gov/pura APPLICATION FOR APPROVAL TO INSTALL FIBER FACILITIES A. APPLICANT INFORMATION: The term “Applicant” refers to the Certificate of Public Convenience and Necessity (CPCN) holder. Applicant must obtain a Connecticut CPCN prior to submitting this Application. Applicant’s information Name: Fiber AssetCo LLC d/b/a Zayo Address: 1359 Broadway, Suite 1600 Address: New York, NY 10018 Phone: [phone removed] Email: [email removed] Attn.: Megan Glander Attorney’s information (if any): Law Firm: Tobin, Carberry, O’Malley, Riley & Attn.: Mark J. Cook, Esq. Selinger, P.C. Address: 43 Broad Street, P.O. Box 58, New London, Connecticut 06320 Address: Phone: [phone removed] Email: [email removed] B. FACILITY INFORMATION Provide the following information regarding the Facility: Purpose and intended use of the Facilities: The purposes of the proposed Fiber facilities are for Fiber AssetCo LLC d/b/a Zayo (“Fiber AssetCo” or the “Company”) to provide services consistent with its final approved tariff supporting carrier-neutral colocation, cloud services, and customized solutions used on both a wholesale and retail basis by a wide variety of public- and private-sector enterprise customers. Fiber AssetCo will install its Fiber facilities within the communications space on utility poles of The Southern New England Telephone Company d/b/a Frontier Communications and either The United Illuminating Company or The Connecticut Light and Power Company d/b/a Eversource Energy and/or within new conduit. Fiber AssetCo has executed pole attachment agreements in placePage 5 of 63
with the applicable pole owners for the fiber installations, as applicable. Miles (or feet) of Cabling: 470 feet Number of Locations: 1 location total: 1 segment in Danbury, CT-See Attachment I Proposed construction start Start Date: December 20, 2026 date and completion date: Completion Date: December 31, 2026 Specifications of cabling Single-mode, bend-sensitive fiber cabling manufactured by (material, size, weight, etc.): Corning Cable Systems, AFL, Prysmian or ofs. For additional information, please see Attachment II. -2-Page 6 of 63
C. ATTACHMENTS (C-1) Provide as Attachment I, all names of towns and the corresponding miles of fiber proposed for each town. Submit the locations of proposed fiber facilities on route maps and accompanied by a description (applicant may submit such information subject to a motion for protective order). (C-2) Provide as Attachment II, all technical information and specifications (e.g., National Electrical Safety Code and construction standards) regarding the planned fiber facilities. Indicate whether and how the construction will comply with Conn. Agencies Regs. Sec. 16-247c-5. D. SIGNATURE Submitted by, Applicant’s Name: FIBER ASSETCO LLC D/B/A ZAYO Signature: Name: Mark J. Cook, Esq. Tobin, Carberry, O’Malley, Riley & Organization Name: Selinger, P.C. Address: 43 Broad Street, P.O. Box 58 Address: New London, CT 06320 Phone Number: [phone removed] Affiliation with Company: Its Attorneys -3-Page 7 of 63
Docket No. 26-09-20 ATTACHMENT I The route description and route map for each of the following proposed installations has been submitted as a confidential and proprietary filing in accordance with the approved Motion for Protective Order dated October 20, 2026 filed in this Docket No. 26-09-20. -4-Page 8 of 63
Docket No. 26-09-20 ATTACHMENT I EXHIBIT TOWN FEET PROPOSED START DATE 1 Danbury 470 12/20/2026 Total 470 -5- PROPOSED COMPLETION DATE 12/31/2026Page 9 of 63
APPENDIX II Fiber AssetCo LLC (“Fiber AssetCo” or the “Company”) technical information and specifications (e.g., National Electrical Safety Code and construction standards) regarding the planned fiber facilities for the construction proposed above are as follows. Fiber AssetCo intends to comply with the Regulations of Connecticut State Agencies §16-247c-5 and with all state and local regulations affecting public safety during and after the construction of the facilities. The Company will coordinate its construction activity with local authorities, obtain any necessary municipal permits, and comply with any local safety traffic and control requirements applicable to its activities. In accordance with the Authority's prior decisions, Fiber AssetCo will notify the Authority when it completes construction on the projects listed in Attachment I, Exhibit No. 1. This notification will include the status of any required municipal permits and/or any Permit Bonds required by the State of Connecticut, Department of Transportation. A. Request for Waiver of the Regulations of Connecticut State Agencies Section 16-247c5(b) – 90-Day Advanced Filing Requirement Regulations of Connecticut State Agencies § 16-247c-5(b) requires that applications for approval to construct facilities in the public rights-of-way must be filed with the Authority at least 90 days prior to the commencement of construction. Fiber AssetCo respectfully requests a waiver of that requirement to 29 days of advance notice which would be December 20, 2026. The customer requesting service is in particularly urgent need of the telecommunications services proposed. The purpose of this request for waiver is to ask for the Authority’s assistance in expediting construction of this project so that Fiber AssetCo can timely build and provide the advanced telecommunications services to the area indicated in Attachment I. Fiber AssetCo notes that its competitors, Frontier, Verizon and the cable television companies offering services in Connecticut are permitted to install facilities immediately after identifying a network expansion project or receiving a customer order without needing prior Authority authorization. B. Exemption Request for the General Statutes of Connecticut Section 16-234 Requirements Pursuant to the Authority’s decision in Docket No. 01-08-01 Application of Fiber Technologies Networks, L.L.C. f/k/a Fiber Systems L.L.C. for Approval to Install Facilities Under and Over Certain Public Rights-of-Way – Motion No. 27, dated October 14, 2009, Fiber AssetCo's installation within the public rights-of-way should be considered exempt from the statutory notice and consent provisions of Conn. Gen. Stat. §16-234 ("Notice Requirements"). Since the proposed Fiber installations listed in Attachment I, Exhibit No. 1 do not deviate from the nature of Fibertech’s past Fiber installations, Fiber AssetCo's proposed fiber project included in this request should likewise be exempt from the Notice Requirements of Conn. Gen. Stat. §16-234. C. Request for Expedited Approval Section 16-247c-5(c) of the Conn. Agencies Regs. states that PURA shall grant or deny an installation application within sixty (60) days of receipt of all required information. Fiber AssetCo respectfully requests that the PURA grant it within twenty-nine (29) days following -6-Page 10 of 63
receipt of all required information for the many reasons stated in this application including this particular customer’s expressed urgent need for telecommunications services. -7-
As listed on the current system
Motion No. 002 11/20/2026 (Fiber AssetCo, LLC dba Zayo) - Motion for Authorization to Install Additional Facilities Under and Over Certain PROW [26-09-20]