Docket 02-03-17
Joint Investigation by the DPH and DPUC into the Adequacy of Service Supplied by the Colchester Courtyard Water System
Decisions and notices5
What the Authority has issued in this docket, newest first.
Filings75
Showing 1–50 of 75 filings
- State Of Connecticut
- Colchester Courtyard
request for extension of time
- Colchester Courtyard
request for extension of time
- Colchester Courtyard
Compliance
- MJH, LLC Legal and Consulting Services
Response to letter dated 1/13/05 to Colchester Water System
- DPH &DPUC of Colchester
RE: WATER MAIN EXTENSION
- Town of Colchester
Progress report
- Colchester Courtyard Water System
Acknowledgement receipt of the Agreement to Resolve Proceedings
- Dept. of Public Health
Third request for ext. of time to file LFE is granted
- Aquarion Water Company
Response to Dept.'s & DPH's order
Ltr. regarding Notice of Continuance of Hearing to 10/07/02 at DPH Hartford, CT.
- DPH
Ltr. regarding Late-filed exhibits to be filed around 9/16/2002.
- Colchester Courtyard Water System
Request for extension of time to submit Late Filed Exhibits until September 16, 2002
- Southeastern Connecticut Water Authority
Response to items raised at 8/8/2002 hearing
- DPH/Colchester Courtyard Water System
Ruling on Req for Continuance and Req for Ext of time to submit LFX's
- The Connecticut Water Company
Information requested at 8/8/2002 hearing
About this docket
- Docket number
- 02-03-17
- Status
- Closed April 8, 2004
- First filing
- May 8, 2002
- Latest filing
- October 15, 2014
- Public filings
- 75
- Documents
- On the current system
Search this docket
Reading a docket
- Motions ask the Authority for something; each gets a ruling.
- Interrogatories are written questions, usually from Authority staff; the answers are filed as responses.
- A draft decision comes before the final decision; participants may file exceptions to it.