Docket 03-04-07
Application of The Connecticut Light and Power Company for Approval of an EAC Charge to Recover Costs Resulting from the Implementation of Standard Market Design
Decisions and notices12
What the Authority has issued in this docket, newest first.
Filings68
21 filings of the selected types
- Northeast Utilities
- Northeast Utilities
Copy of FERC Order re:NRG
- Northeast Utilities
July SMD Adj. Rate
- State of CT - OCC
Add to Service List
- Northeast Utilities
Respond for surety bond termination
- Northeast Utilities
CL&P 5/27/03 FERC filing
- Northeast Utilities
Energy adjustment clause charge for Standard Market Design-related costs for June 2003
- Northeast Utilities
Supplemental information from CL&P's 5-16-03 Motion
- Northeast Utilities
Comments on Final Decision
- AG
Request that DPUC resolve the issues presented in its petition for a Declaratory ruling prior to addressing the merits of CL&P's application
- State of CT - OCC
OCC Objection CL&P request
- Office of the Attorney General
Petition for a declaratory ruling regarding the legality and prudency of CL&P's application concerning the recovery of SMD-related costs for March 1, 2003 through December 31, 2003
- Northeast Utilities
Application and Testimony of CL&P Concerning Recovery of SMD-Related Costs for March 1, 2003 through December 31, 2003
About this docket
- Docket number
- 03-04-07
- Status
- Open
- First filing
- April 22, 2003
- Latest filing
- April 29, 2005
- Public filings
- 68
- Documents
- On the current system
Search this docket
Reading a docket
- Motions ask the Authority for something; each gets a ruling.
- Interrogatories are written questions, usually from Authority staff; the answers are filed as responses.