Docket 07-04-24
DPUC Review of Energy Independence Act Capacity Contracts
Decisions and notices5
What the Authority has issued in this docket, newest first.
Filings1,685
Showing 1,351–1,400 of 1,685 filings
- Robinson & Cole Llp
- Ameresco
Milestone Status Update
- Ameresco
Quarterly Progress Report
- Pullman & Comley, Llc
Progress Report
- Robinson & Cole Llp
Ltr re weekly billing statement
- Robinson & Cole Llp
Ltr re Forward Capacity Auction
- Ameresco
Bidding Documentation
- Robinson & Cole Llp
Ltr re weekly billing statement
- Robinson & Cole LLP
Ltr K Santopietro re weekly notice of LFRM activity re billing statements 9-28-09
- Robinson & Cole Llp
Ltr enclosing weekly billing statement
- Robinson & Cole Llp
Ltr enclosing August Generating Availability Data
- Robinson & Cole LLP
Letter K. Santopietro ISO-NE's 9/14/09 billing statement
- Robinson & Cole Llp
Ltr enclosing weekly billing statement
- Robinson & Cole Llp
Ltr encl monthly billing statement
- Robinson & Cole Llp
Ltr re weekly notice of billing statements
- Robinson & Cole Llp
Ltr enclosing bids re LFRMs.
- Robinson & Cole Llp
Ltr enclosing data that is required to be provided to DPUC
Ruling: Moot
- Robinson & Cole Llp
Ltr providing billing information
- Robinson & Cole LLP
Correspondence re Milestone Progress Report
- Pullman & Comley, Llc
Progress Report
- Ameresco
Qrtly Progress Report
- Robinson & Cole Llp
Ltr re completion of Milestone Event.
- Robinson & Cole Llp
Ltr re completion of Milestone Event
- DPUC
Ruling: Denied
- Robinson & Cole Llp
Letter re completion of Milestone Event
- Robinson & Cole LLP
Cover letter K. Santopietro re Milestone Progress Report
- Ameresco
Milestone Status Report
Master Agreement Requirements
- Robinson & Cole Llp
Ltr re completion of Milestone Events
- Robinson & Cole Llp
Ltr re certifying completion of Milestone Events
- Robinson & Cole Llp
Notice re Completion of Milestone Event
- Ameresco
Response type: Objection
- Northeast Utilities
Commercial Operation by Waterside Power LLC
- CL&P
CL&P Motion for Disclosure of FMCC Reductions
Monthly Progress Report, Prot. Mat.
- United Illuminating
UI response to Ameresco
- DPUC
Ruling: Granted
- Waterbury Generation LLC
Ltr from Atty Bogan: Motion re Milestone Event
Ameresco CT LLC Request for Exemption from Delay Liquidated Damages
- Ameresco
Milestone Status Updae
Compliance
- Robinson & Cole Llp
Letter from Mr. Bogan re Milestone Progress Report
- Pullman & Comley
Ltr. re Achievement of Milestone Event
- Ameresco
Progress Report, Milestone Update, Agreement Amendment Request
- Robinson & Cole Llp
Ltr from David Bogan re Review of Energy Independence Act
- Lake Road Generating Co., LP
Certificate of Liability
- Rubin and Rudman LLP
May 18, 2007 Capacity Agreement Between Waterside Power, LLC and CL&P
- Robinson & Cole Llp
Ltr with attached Qtrly Progress Report
- Ameresco
Monthly Progress Report and Milestone Status Update
About this docket
- Docket number
- 07-04-24
- Status
- Closed August 22, 2007
- First filing
- May 8, 2007
- Latest filing
- June 2, 2025
- Public filings
- 1,685
- Documents
- On the current system
Schedule
Dates for hearings, deadlines, and decisions.
- Docket schedule
Revised July 13, 2007
Search this docket
Reading a docket
- Motions ask the Authority for something; each gets a ruling.
- Interrogatories are written questions, usually from Authority staff; the answers are filed as responses.
- A draft decision comes before the final decision; participants may file exceptions to it.