Docket 08-02-06
DPUC Investigation into The Connecticut Light and Power Company's Billing Issues
Decisions and notices9
What the Authority has issued in this docket, newest first.
Filings214
Showing 1–50 of 214 filings
- DPUC
DPUC letter to CL&P finding them in compliance with Order No. 7.
- Northeast Utilities
Compliance Filing, Order No. 7
- DPUC
Letter to CL&P regarding proposed bill insert (Order No. 7 ) and directing that the bill insert be revised and submitted to the Department for approval.
- Northeast Utilities
Compliance Filing, Order No. 7
- DPUC
DPUC letter to TransCanada Power Marketing approving the amended Standard Payment Agrrangement Policy filed on 2/2/09.
- DPUC
DPUC letter to Constellation NewEnergy approving the amended Standard Payment Arrangement Policy filed on 1/30/09.
- Northeast Utilities
Compliance Filing, Order No. Interim
- TransCanada Power Marketing Ltd.
Compliance Filing, Order No. 3
- Robinson & Cole Llp
Compliance Filing, Order No. Order
- Direct Energy Services, LLC
Compliance Filing, Order No. 3
- Sempra Energy Solutions Llc
Compliance Filing, Order No. 3
- DPUC
DPUC letter to Hess Corporation approving the amended Standard Payment Arrangement Policy.
- Hess Corporation
Letter Correspondence of 01/20/09
- DPUC
DPUC letter to Sempra Energy Solutions regarding Order No. 3. Sempra shall submit its revised policy no later than 1/30/09.
- DPUC
DPUC letter to Hess Corporation regarding Order No. 3. Hess shall submit its revised policy no later than 1/30/09.
- DPUC
DPUC letter to Direct Energy Services regarding Order No. 3. Direct Energy shall submit the revised policy no later than 1/30/09.
- DPUC
DPUC letter to TransCanada Power Marketing regarding Orders No. 3 and 8.
- DPUC
DPUC letter to Suez Energy Resources regarding Order No. 3.
- DPUC
DPUC letter to Constellation NewEnergy regarding Orders No. 3 and 8.
- Suez Energy Resources NA
Compliance Filing, Order No. Order
- Northeast Utilities
Compliance Filing, Order No. 4
- Robinson & Cole Llp
Ltr with info required by Order No. 8
- Con Edison Solutions
Response to Dept. request
- Murtha Cullina LLP
Compliance Filing, Order No. 3
- TransCanada Power Marketing Ltd.
Revised
- Suez Energy Resources NA
Compliance Filing, Order No. 3
- Robinson & Cole LLP
Compliance Filing, Order No. 3
- Hess Corporation
Letter Exec Sec To Hess 10/15/08
- Northeast Utilities
Compliance Filing, Order No. No
- Robinson & Cole LLP
Compliance Filing, Order No. 4
- DPUC
Letter to Consolidated Edison Solutions, Inc. regarding Order Nos. 3, 4, 7 and 8
- DPUC
DPUC letter to Sempra Energy Solutions, LLC.
- DPUC
DPUC letter to Direct Energy Services, LLC finding the Company in compliance with Orders No. 3, 4 and 8 and the Company needs to submit its revised policy (16-259a) no later than 11/21/08.
- Direct Energy Services, LLC
Compliance Filing, Order No. 8
- DPUC
DPUC letter to Suez Energy Resources NA, Inc. finding the Company in compliance with Order No. 3 and advising Company no further action or filing is required from Suez relating to Order No. 4.
- DPUC
DPUC letter to Sempra Energy Solutions, LLC finding the Company in compliance with Order No. 3, the policy submitted implementing CGS Section 16-259a is unacceptable and is directed to refile its policy by 11/14/08 and no further action or filing is required under Orders No. 4 and 8.
- DPUC
DPUC letter to Hess Corporation finding the policy submitted by Hess implementing CGS Section 16-259a is unacceptable and will need to refile no later than 11/10/08.
- DPUC
DPUC letter to Glacial Energy of New England stating the Company has not complied with Department orders and directs the Company to file the requested information no later than 10/31/08 and a report is due to the Department by 11/7/08.
- DPUC
DPUC letter to Consolidated Edison Solutions, Inc. stating the Company has not complied with Department orders and they have until 10/31/08 to submit filings. Also, the Company is directed to submit to the Department a report no later than 11/7/08.
- DPUC
DPUC letter to TransCanada Power Marketing Ltd. finding them in compliance with Order Nos. 3, 4 and 8.
- DPUC
DPUC letter to Constellation NewEnergy finding them in compliance with Order Nos. 3, 4 and 8.
- DPUC
DPUC letter to CL&P finding the Company in compliance with Order Nos. 1 and 2 and Order No. 4 of the Interim Order. The Department requests information (questions 1-3) no later than 10/20/08 regarding Order No. 4.
About this docket
- Docket number
- 08-02-06
- Status
- Closed August 6, 2008
- First filing
- February 19, 2008
- Latest filing
- November 29, 2010
- Public filings
- 214
- Documents
- On the current system
Schedule
Dates for hearings, deadlines, and decisions.
- Docket schedule
Revised July 23, 2008
Search this docket
Reading a docket
- Motions ask the Authority for something; each gets a ruling.
- Interrogatories are written questions, usually from Authority staff; the answers are filed as responses.
- A draft decision comes before the final decision; participants may file exceptions to it.