DPUC
Docket 09-11-16
Application of Hartford Steam Combined Heat and Power Plant as a Class III Renewable Energy Source
Decisions and notices2
What the Authority has issued in this docket, newest first.
Filings150
7 filings of the selected types
- DPUC
Letter to Nexant Clean Energy Markets, representing Hartford Steam Company, finding that its October 15, 2010 filing fulfills the requirement for Order No. 2, Quarter No. 2
- DPUC
Letter to Nexant Clean Energy Markets (Hartford Steam Company) finding that its October 26, 2010 filing fulfills the requirement for Order No. 1, Quarter No. 3
About this docket
- Docket number
- 09-11-16
- Status
- Closed February 3, 2010
- First filing
- November 20, 2009
- Latest filing
- October 26, 2026
- Public filings
- 150
- Documents
- On the current system
Schedule
Dates for hearings, deadlines, and decisions.
- Docket schedule
Revised January 25, 2010
Search this docket
Reading a docket
- Motions ask the Authority for something; each gets a ruling.
- Interrogatories are written questions, usually from Authority staff; the answers are filed as responses.
- A draft decision comes before the final decision; participants may file exceptions to it.