Docket 12-06-02RE04
PURA Review of Power Procurement Plan – Amendment Pursuant to Public Act 25-173
Decisions and notices6
What the Authority has issued in this docket, newest first.
Filings58
12 filings of the selected types
- UI
- CL&P dba Eversource Energy
Answers to questions 14 thru 14
- Retail Energy Supply Association
Answers to questions 17 thru 17
- OCC
Answers to questions 16 thru 16
- CL&P dba Eversource Energy
Answers to questions 15 thru 15
- UI
Answers to questions 1
- UI
Answers to questions 6
- UI
Answers to questions 1 thru 6
- CL&P dba Eversource Energy
Answers to questions 1 thru 6
- UI
Answers to questions 7 thru 9
- OCC
Answers to questions 12 thru 13
- CL&P dba Eversource Energy
Answers to questions 10 thru 11
About this docket
- Docket number
- 12-06-02RE04
- Status
- Open
- First filing
- July 31, 2025
- Latest filing
- February 13, 2026
- Public filings
- 58
- Documents
- On the current system
Schedule
Dates for hearings, deadlines, and decisions.
- Docket schedule
Revised January 9, 2026
Search this docket
Reading a docket
- Motions ask the Authority for something; each gets a ruling.
- Interrogatories are written questions, usually from Authority staff; the answers are filed as responses.
- A draft decision comes before the final decision; participants may file exceptions to it.