Docket 13-07-25
Petition for Approval of Method and Manner of Construction and Permission to Energize the Stevenson - Frost Bridge - Baldwin 115-kV Transmission Line (1990 Line)
Decisions and notices2
What the Authority has issued in this docket, newest first.
Filings3
1 filing of the selected types
About this docket
- Docket number
- 13-07-25
- Status
- Closed August 14, 2013
- First filing
- August 12, 2013
- Latest filing
- December 19, 2014
- Public filings
- 3
- Documents
- On the current system
Search this docket
Reading a docket
- Motions ask the Authority for something; each gets a ruling.
- Interrogatories are written questions, usually from Authority staff; the answers are filed as responses.
- A draft decision comes before the final decision; participants may file exceptions to it.