Docket 13-11-20ClosedFebruary 19, 2014
Application of 2012 ESA Project Company LLC for Qualification of ATT Bridgeport as a Class I Renewable Energy Source
- Status
- Closed February 19, 2014
- First filing
- December 9, 2013
- Latest filing
- July 28, 2021
- Filings
- 22
- Documents
- On the current system (documents are copied for 2024 and later dockets)
This docket's record on the current system (opens in a new tab)
Decisions and notices
What the Authority has issued in this docket, newest first.
- February 19, 2014Decision Final Decision
- February 4, 2014Draft decision Draft Decision
Filings
22 filings.
July 2021
Compliance Filing, Order No. 1July 28, 2021 · Bloom EnergyApril 2021
Compliance Filing, Order No. 1April 28, 2021 · Bloom EnergyQ4 2020 Emissions Screenshots
February 2021
Compliance Filing, Order No. 1February 1, 2021 · Bloom EnergyQ3 2020 Emissions Screenshots
October 2020
Compliance Filing, Order No. 1October 28, 2020 · Bloom EnergyQ2 2020 Emissions Screenshots
July 2020
Compliance Filing, Order No. 1July 29, 2020 · Bloom EnergyQ1 2020 Emissions Screenshots
May 2020
Compliance Filing, Order No. 1May 1, 2020 · Bloom EnergyQ4 2019 Emissions Screenshots
January 2020
Compliance Filing, Order No. 1January 28, 2020 · Bloom EnergyQ3 2019 Emissions Screenshots
December 2019
Compliance Filing, Order No. 1December 13, 2019 · Bloom EnergyQ2 2019 Emissions Screenshots
August 2019
Compliance Filing, Order No. 1August 16, 2019 · Bloom EnergyPURA Screenshots Q1-2019
June 2019
Compliance Filing, Order No. 1June 8, 2019 · Bloom EnergyQ4 2018 Emissions Screenshots - ATT Bridgeport
March 2019
Compliance Filing, Order No. 1March 18, 2019 · Bloom EnergyQ3 2018 Emissions Screenshots
December 2018
Compliance Filing, Order No. 1December 10, 2018 · 2012 ESA Project Company, LLC2018, Q2 - Emissions, ATT Bridgeport
September 2018
Compliance Filing, Order No. 1September 28, 2018 · Bloom Energy2018 - Q1 - Emissions Screenshots
May 2018
Compliance Filing, Order No. 1May 3, 2018 · Bloom EnergyQ4 2017 Emissions Screenshots
February 2018
Compliance Filing, Order No. 1February 2, 2018 · Bloom EnergyEmissions screenshots
October 2017
Compliance filingOctober 30, 2017 · Bloom EnergyCompliance Filing, Order No. 1
July 2017
Compliance filingJuly 13, 2017 · Bloom EnergyCompliance Filing, Order No. 1
April 2017
Compliance filingApril 21, 2017 · Bloom EnergyCompliance Filing, Order No. 1
February 2014
DecisionFebruary 19, 2014 ·Final Decision
- Draft decisionFebruary 4, 2014 ·
Draft Decision
December 2013
CorrespondenceDecember 9, 2013 ·Additional Information