Docket 16-03-08
Petition of Windham Solar LLC for Approval of a Power Purchase Agreement Between Windham Solar LLC and The Connecticut Light and Power Company d/b/a Eversource Energy
Decisions and notices10
What the Authority has issued in this docket, newest first.
Filings78
12 filings of the selected types
- Brown Rudnick
PETITION OF WINDHAM SOLAR LLC FOR A DETERMINATION OF INTERCONNECTION COSTS PROPERLY ALLOCABLE TO WINDHAM SOLAR LLC FOR ITS INTERCONNECTION AGREEMENT WITH THE CONNECTICUT LIGHT AND POWER COMPANY d/b/a EVERSOURCE ENERGY
- Windham Solar, LLC
Administrative Appeal
- Allco Renewable Energy Limited
Second Notice of Additional Authority
NOTICE OF ADDITIONAL AUTHORITY
- Allco Renewable Energy Limited
Notice of Additional Authority
- Allco Renewable Energy Limited
United States Postal Service Evidence of Mailing
- Allco Renewable Energy Limited
Confirmation re: Oral Arguments
*POSTED IN ERROR*
- Keegan Werlin Llp
response to certain information requests
- Keegan Werlin LLP
Appearance of Counsel
- Brown Rudnick Berlack Israels LLP
Request for further clarification regarding May 17 hearing
About this docket
- Docket number
- 16-03-08
- Status
- Closed August 24, 2016
- First filing
- March 10, 2016
- Latest filing
- March 31, 2020
- Public filings
- 78
- Documents
- On the current system
Schedule
Dates for hearings, deadlines, and decisions.
- Docket schedule
Revised August 25, 2016
Search this docket
Reading a docket
- Motions ask the Authority for something; each gets a ruling.
- Interrogatories are written questions, usually from Authority staff; the answers are filed as responses.
- A draft decision comes before the final decision; participants may file exceptions to it.