Docket 17-02-23
Application of Cellco Partnership d/b/a Verizon Wireless for Approval of a Construction Plan to Install Wireless Facilities Within Certain Public Rights-of-Way – Westport CT SC4
Decisions and notices3
What the Authority has issued in this docket, newest first.
Filings22
12 filings of the selected types
- James Marpe
- Mark LaClair
Photos submitted during 4/28/17 Hearing
- Matt Finkle
APO Finkel letter of opposition in lieu of attending hearing
- Matt Finkle
APO Finkle Letter of Opposition in Lieu of attending 4/28 Hearing _ duplicate posting
- Robinson & Cole Llp
Pre-Hearing Submittal
- Berchem, Moses & Devlin, P.c.
Public Comment__Town of Westport ) Find an alternate utility pole
- Mark LaClair and I, Jacqueline Tanya Sprague
LaClair and Sprague APO Opposition
- Matt Finkle
Finkle / Cho Opposition
- Karen Elizaga and Jay Ptashek
APO_Elizaga and Ptashek Opposition
- Hal Fishel
APO_Fishel Opposition
- Sue and Stephen Papish
APO_Sue and Stephen Papish_Opposition
About this docket
- Docket number
- 17-02-23
- Status
- Closed August 9, 2017
- First filing
- February 14, 2017
- Latest filing
- April 17, 2025
- Public filings
- 22
- Documents
- On the current system
Schedule
Dates for hearings, deadlines, and decisions.
- Docket schedule
Revised July 31, 2017
Search this docket
Reading a docket
- Motions ask the Authority for something; each gets a ruling.
- Interrogatories are written questions, usually from Authority staff; the answers are filed as responses.
- A draft decision comes before the final decision; participants may file exceptions to it.