Docket 18-08-14
PURA Review of the Combined Heat and Power Project Solicitation Pursuant to Conn. Gen. Stat. §16-258e
Decisions and notices12
What the Authority has issued in this docket, newest first.
Filings237
26 filings of the selected types
- Avangrid
- Pullman & Comley, LLC
NuPower Updated Interconnection Cost Estimate and Cost Recovery Proposal
- Uil Holdings Corporation
UI Final Facilities Study Report
- Pullman & Comley, LLC
Update on Status of Interconnection
- Uil Holdings Corporation
UI Monthly Interconnection Process Status Update
- Uil Holdings Corporation
UI Monthly Interconnection Process Status Update
- Pullman & Comley, Llc
Update of Interconnection with UI
- Uil Holdings Corporation
UI Monthly Interconnection Process Status Report
- Pullman & Comley, LLC
Interconection Status Report
- Uil Holdings Corporation
UI Monthly Interconnection Process Update
- Uil Holdings Corporation
UI Monthly Status Update of Interconnection Process
- Pullman & Comley, Llc
Status of NuPower's Interconnection with UI
- Uil Holdings Corporation
UI Revised PPA with Modifications
- Uil Holdings Corporation
UI Monthly Update on Status of Interconnection Process
- Uil Holdings Corporation
UI Status of Revised PPA
- Pullman & Comley, Llc
Interconnection Status Report
About this docket
- Docket number
- 18-08-14
- Status
- Closed October 2, 2019
- First filing
- August 16, 2018
- Latest filing
- November 12, 2026
- Public filings
- 237
- Documents
- On the current system
Schedule
Dates for hearings, deadlines, and decisions.
- Docket schedule
Revised September 12, 2024
Search this docket
Reading a docket
- Motions ask the Authority for something; each gets a ruling.
- Interrogatories are written questions, usually from Authority staff; the answers are filed as responses.
- A draft decision comes before the final decision; participants may file exceptions to it.