Docket 19-12-33ClosedMarch 11, 2020
Application of Holiday Hill Community Wind, LLC for Qualification of 732 Pine Hill Road, Russell, MA as a Class I Renewable Energy Source
- Status
- Closed March 11, 2020
- First filing
- March 2, 2020
- Latest filing
- October 16, 2026
- Filings
- 33
- Documents
- On the current system (documents are copied for 2024 and later dockets)
This docket's record on the current system (opens in a new tab)
Decisions and notices
What the Authority has issued in this docket, newest first.
- March 11, 2020Decision Final Decision
- March 3, 2020Draft decision Draft Decision
Filings
33 filings.
October 2026
Compliance Filing, Order No. 1October 16, 2026 · Energy New EnglandJuly 2026
Compliance Filing, Order No. 1July 17, 2026 · Energy New EnglandQ1 2026
April 2026
Compliance Filing, Order No. 1April 16, 2026 · Energy New EnglandQ4 2025
January 2026
Compliance Filing, Order No. 1January 20, 2026 · Energy New EnglandQ3 2025
October 2025
Compliance Filing, Order No. 1October 21, 2025 · Energy New EnglandQ2 2025
July 2025
Compliance Filing, Order No. 1July 17, 2025 · Energy New EnglandQ1 2025
April 2025
Compliance Filing, Order No. 1April 25, 2025 · Energy New EnglandQ4 2024
January 2025
Compliance Filing, Order No. 1January 17, 2025 · Energy New EnglandQ3 2024
October 2024
Compliance Filing, Order No. 1October 17, 2024 · Energy New EnglandQ2 2024 Generation
July 2024
Compliance Filing, Order No. 1July 17, 2024 · Energy New EnglandQ1 2024
April 2024
Compliance Filing, Order No. 1April 18, 2024 · Energy New EnglandQ4 2023
January 2024
Compliance Filing, Order No. 1January 19, 2024 · Energy New EnglandCompliance
October 2023
Compliance Filing, Order No. 1October 17, 2023 · Energy New EnglandCompliance
July 2023
Compliance Filing, Order No. 1July 19, 2023 · Energy New EnglandQ1 2023
April 2023
Compliance Filing, Order No. 1April 24, 2023 · Energy New EnglandCompliance
January 2023
Compliance Filing, Order No. 1January 20, 2023 · Energy New EnglandCompliance
October 2022
Compliance Filing, Order No. 1October 20, 2022 · Energy New EnglandQ2 2022
July 2022
Compliance Filing, Order No. 1July 15, 2022 · Energy New EnglandQ1 2022 Generation
April 2022
Compliance Filing, Order No. 1April 22, 2022 · Energy New EnglandQ4 2021 Generation
January 2022
Compliance Filing, Order No. 1January 18, 2022 · Energy New EnglandQ 3 2021 Generation
October 2021
Compliance Filing, Order No. 1October 19, 2021 · Energy New EnglandQ2 2021 generation
July 2021
Compliance Filing, Order No. 1July 15, 2021 · Energy New EnglandQ1 2021 generation
April 2021
Compliance Filing, Order No. 1April 15, 2021 · Energy New EnglandQ4 2020 generation
January 2021
Compliance Filing, Order No. 1January 19, 2021 · Energy New EnglandQ3 2020 generation
October 2020
Compliance Filing, Order No. 1October 15, 2020 · Energy New EnglandQ2 2020 generation
July 2020
Compliance Filing, Order No. 1July 15, 2020 · Energy New EnglandGeneration
April 2020
Compliance Filing, Order No. 1April 16, 2020 · Energy New EnglandGeneration
- Correction (errata)April 1, 2020 ·
Errata
March 2020
Correction (errata)March 25, 2020 ·Draft Errata
- CorrespondenceMarch 24, 2020 · PURA
Notification to Correct Identification Number
- DecisionMarch 11, 2020 ·
Final Decision
- Draft decisionMarch 3, 2020 ·
Draft Decision
- CorrespondenceMarch 2, 2020 · PURA
NEPOOL GIS ID No.