Docket 20-06-06ClosedJune 26, 2020
Application of The Lyman Farm, Inc. for Qualification of 27 Lyman Road, Middlefield, CT as a Class I Renewable Energy Source
- Status
- Closed June 26, 2020
- First filing
- June 17, 2020
- Latest filing
- August 20, 2024
- Filings
- 14
- Documents
- On the current system (documents are copied for 2024 and later dockets)
This docket's record on the current system (opens in a new tab)
Decisions and notices
What the Authority has issued in this docket, newest first.
- June 24, 2020Decision Final Decision
- June 17, 2020Draft decision Draft Decision
Filings
14 filings.
August 2024
Compliance Filing, Order No. 12August 20, 2024 · The Lyman Farm, Inc.January 2024
Compliance Filing, Order No. 11January 9, 2024 · The Lyman Farm, Inc.2023-Q1&Q2 Report
July 2023
Compliance Filing, Order No. Lyman-01July 20, 2023 · The Lyman Farm, Inc.2023-07-20 Q1 Production Generation
April 2023
Compliance Filing, Order No. 10April 19, 2023 · The Lyman Farm, Inc.Q4 2022 Compliance Filing
November 2022
Compliance Filing, Order No. Q2November 18, 2022 · The Lyman Farm, Inc.19
August 2022
Compliance Filing, Order No. 16August 15, 2022 · The Lyman Farm, Inc.Q1 2022 Compliance Filing
May 2022
Compliance Filing, Order No. 13May 17, 2022 · The Lyman Farm, Inc.Q4 2021 Compliance Filing
February 2022
Compliance Filing, Order No. 10February 15, 2022 · The Lyman Farm, Inc.Q3 2021 Compliance
November 2021
Compliance Filing, Order No. 9November 15, 2021 · The Lyman Farm, Inc.Q2 2021 Compliance Filing
August 2021
Compliance Filing, Order No. 2August 13, 2021 · The Lyman Farm, Inc.2021 Q1 Compliance Filing
May 2021
Compliance Filing, Order No. 4May 27, 2021 · The Lyman Farm, Inc.Q4 2020 Compliance Filing
February 2021
Compliance Filing, Order No. 3February 17, 2021 · The Lyman Farm, Inc.Q3 2020 Compliance Filing
June 2020
DecisionJune 24, 2020 ·Final Decision
- Draft decisionJune 17, 2020 ·
Draft Decision