Docket 20-10-22

Petition for Approval of Method and Manner of Construction and Permission : To Energize the 100, 1410, 1280, and 1080 Lines – Horton Cove Circuit Separation Project

Closed January 27, 2021

9 public filings, the latest on August 2, 2021.

Decisions and notices3

What the Authority has issued in this docket, newest first.

Filings9

2 filings of the selected types

About this docket

Docket number
20-10-22
Status
Closed January 27, 2021
First filing
November 6, 2020
Latest filing
August 2, 2021
Public filings
9
Documents
On the current system

This docket on the current system (opens in a new tab)

Schedule

Dates for hearings, deadlines, and decisions.

Search this docket

Finds words in this docket's filings and in the text of its documents.

Reading a docket

  • Motions ask the Authority for something; each gets a ruling.
  • Interrogatories are written questions, usually from Authority staff; the answers are filed as responses.
  • A draft decision comes before the final decision; participants may file exceptions to it.