Docket 22-08-33
Application Of The Connecticut Light And Power Company dba Eversource Energy For Approval Of The Issuance Of Long-Term Debt
Decisions and notices4
What the Authority has issued in this docket, newest first.
Filings26
26 filings
- Eversource Energy
Final Decision
Docket schedule (dates for hearings, deadlines, and decisions)
- OCC
Written Exceptions
- CL&P dba Eversource Energy
Written Exceptions
Draft Decision
- Eversource
Exhibits 3
- CL&P dba Eversource Energy
Answers to questions 22
- CL&P dba Eversource Energy
Answers to questions 11, 13, 14
- PURA
October 28, 2022 LFE Hearing Agenda
- Eversource
Exhibits 1 thru 3
- PURA
Ruling: Granted in part - Denied in part
- Eversource Energy Service Company
Exhibits 001 - 3 requested
- CL&P dba Eversource Energy
Answers to questions 11
- PURA
Agenda – October 20, 2022 Hearing
- CL&P dba Eversource Energy
Motion for Protected attachments
- CL&P dba Eversource Energy
Answers to questions 21 thru 27
- CL&P dba Eversource Energy
Answers to questions 1 thru 20
Notice of Proceeding…
Sched. October 20, 2022…
- RRU
To CL&P d/b/a Eversource, questions 21 thru 27
- RRU
To CL&P d/b/a Eversource, questions 1 thru 20
About this docket
- Docket number
- 22-08-33
- Status
- Closed November 30, 2022
- First filing
- September 8, 2022
- Latest filing
- February 7, 2024
- Public filings
- 26
- Documents
- On the current system
Schedule
Dates for hearings, deadlines, and decisions.
- Docket schedule
Revised November 30, 2022
Search this docket
Reading a docket
- Motions ask the Authority for something; each gets a ruling.
- Interrogatories are written questions, usually from Authority staff; the answers are filed as responses.
- A draft decision comes before the final decision; participants may file exceptions to it.