Skip to main content

A prototype public docket site for the Connecticut Public Utilities Regulatory Authority

Utility Dockets and Filings

Docket 23-08-17

Petition for approval of Method and Manner of construction and permission: to energize the 1550 and 1163 lines rebuild project between Frost Bridge substation and Noera substation

Closed September 20, 2023

5 public filings, the latest on July 30, 2024.

Decisions and notices3

What the Authority has issued in this docket, newest first.

Filings5

About this docket

Docket number
23-08-17
Status
Closed September 20, 2023
First filing
August 29, 2023
Latest filing
July 30, 2024
Public filings
5
Documents
On the current system

This docket on the current system (opens in a new tab)

Schedule

Dates for hearings, deadlines, and decisions.

Search this docket

Finds words in this docket's filings and in the text of its documents.

Reading a docket

  • Motions ask the Authority for something; each gets a ruling.
  • Interrogatories are written questions, usually from Authority staff; the answers are filed as responses.
  • A draft decision comes before the final decision; participants may file exceptions to it.

All terms explained