ScheduleNovember 7, 2023 ·
Docket 23-08-27ClosedNovember 22, 2023
Application for Temporary Master Meter Approval at 9 Covered Bridge Road, Newtown, CT
- Status
- Closed November 22, 2023
- First filing
- August 29, 2023
- Latest filing
- March 15, 2024
- Filings
- 13
- Documents
- On the current system (documents are copied for 2024 and later dockets)
This docket's record on the current system (opens in a new tab)
Decisions and notices
What the Authority has issued in this docket, newest first.
- November 22, 2023Decision Final Decision
- November 7, 2023Draft decision Draft Decision
- September 8, 2023Notice Notice of Proceeding
Filings
1 filing of the selected types.
November 2023