Docket 23-08-27ClosedNovember 22, 2023
Application for Temporary Master Meter Approval at 9 Covered Bridge Road, Newtown, CT
- Status
- Closed November 22, 2023
- First filing
- August 29, 2023
- Latest filing
- March 15, 2024
- Filings
- 13
- Documents
- On the current system (documents are copied for 2024 and later dockets)
This docket's record on the current system (opens in a new tab)
Decisions and notices
What the Authority has issued in this docket, newest first.
- November 22, 2023Decision Final Decision
- November 7, 2023Draft decision Draft Decision
- September 8, 2023Notice Notice of Proceeding
Filings
13 filings.
March 2024
CorrespondenceMarch 15, 2024 · Covered Bridge Newtown LLC- CorrespondenceMarch 13, 2024 · PURA
PURA Correspondence RE: Memo Withdrawing Application
February 2024
CorrespondenceFebruary 7, 2024 · Covered Bridge Newtown LLCMemo withdrawing application
January 2024
Compliance Filing, Order No. 1January 31, 2024 · Upstream Properties II LLCFiled in Error by Co.
November 2023
DecisionNovember 22, 2023 ·Final Decision
- Draft decisionNovember 7, 2023 ·
Draft Decision
October 2023
Interrogatory responsesOctober 7, 2023 · Covered Bridge Newtown LLCAnswers to questions 1 thru 7
- Interrogatory responsesOctober 6, 2023 · Covered Bridge Newtown LLC
Answers to questions 1 thru 7
September 2023
InterrogatoriesSeptember 28, 2023 · RRUTo Covered Bridge Newtown, LLC, questions 1 thru 7
- NoticeSeptember 8, 2023 ·
Notice of Proceeding
August 2023
CorrespondenceAugust 30, 2023 · Covered Bridge Newtown LLCMemo to File
- CorrespondenceAugust 29, 2023 · Covered Bridge Newtown LLC
Correspondence added: Exhibit B-4