Docket 25-01-03
Annual Review of the Rate Adjustment Mechanisms of The Connecticut Light and Power Company
Decisions and notices12
What the Authority has issued in this docket, newest first.
Filings163
Showing 101–150 of 163 filings
- CL&P dba Eversource Energy
- CL&P dba Eversource Energy
Answers to questions 46, 47, 48
- CL&P dba Eversource Energy
Answers to questions 45
- CL&P dba Eversource Energy
Answers to questions 30, 32, 33, 39, 40, 41, 42, 43, 44
- CL&P dba Eversource Energy
Answers to questions 25, 26, 27, 28, 29, 31, 35, 36, 37, 38
- Eversource Energy
Supplement Compliance Filing
- PURA
Ruling: Granted
- Eversource Energy
Response type: Supplemental Filing
- PURA
Hearing Agenda 3/14/2025
- Eversource Energy
with Compliance order No 5 in docket 17-12-03RE11
- Eversource Energy
filed with 17-12-03RE11 order no 5
- PURA
Ruling: Granted
- PURA
Ruling: Granted
- CL&P dba Eversource Energy
MPO for RAM attachments
- CL&P dba Eversource Energy
Motion for Approval Order 11 (17-12-03re11)
- CL&P dba Eversource Energy
Extension of Time for PURA set 4 IR's
- Eversource Energy
Compliance filing
- Eversource Energy
Compliance Filing
- Eversource Energy
Compliance filing
- Eversource Energy
Compliance filing
- CL&P dba Eversource Energy
Answers to questions 10 thru 14
- RSR
To CL&P, questions 4 thru 4
- CAE
To CL&P, questions 45 thru 48
- CAE
To CL&P, questions 25 thru 44
- OCC
To CL&P, questions 15 thru 32
- CL&P dba Eversource Energy
Answers to questions 3
- CL&P dba Eversource Energy
Answers to questions 18
- Eversource Energy
Compliance Filing
- Eversource Energy
Compliance Filing
- OCC
To CL&P, questions 10 thru 14
Sched. 3/14/2025…
- CL&P dba Eversource Energy
protected material
- CL&P dba Eversource Energy
Answers to questions 1 thru 2
- CL&P dba Eversource Energy
Answers to questions 23
- CL&P dba Eversource Energy
Answers to questions 20, 24
- CL&P dba Eversource Energy
Answers to questions 13, 14, 15, 16, 17, 19, 20, 21, 22
- CL&P dba Eversource Energy
Answers to questions 7, 8, 9, 10, 11, 12
- PURA
Ruling: Granted
- CL&P dba Eversource Energy
Extension of time
- RSR
To CL&P, questions 3 thru 3
- CL&P dba Eversource Energy
Answers to questions 1 thru 9
of Admitted Evidence…
- PURA
Ruling: Granted in part - Denied in part
- RSR
To CL&P, questions 1 thru 2
- CAE
To CL&P, questions 7 thru 24
re: Confidential Information…
- OCC
Response type: Comment
- Connecticut Green Bank
SUPPLEMENTAL compliance with December 4, 2024, Final Decision in Docket No. 24-08-05
- Eversource Energy
Response type: Objection
- OCC
To CL&P, questions 1 thru 9
About this docket
- Docket number
- 25-01-03
- Status
- Closed August 13, 2025
- First filing
- November 7, 2024
- Latest filing
- April 13, 2026
- Public filings
- 163
- Documents
- Not copied yet
Schedule
Dates for hearings, deadlines, and decisions.
- Docket schedule
Revised July 29, 2025
Search this docket
Reading a docket
- Motions ask the Authority for something; each gets a ruling.
- Interrogatories are written questions, usually from Authority staff; the answers are filed as responses.
- A draft decision comes before the final decision; participants may file exceptions to it.