Docket 25-03-11ClosedJuly 15, 2026
Investigation into the Accident on March 11, 2025, at 341 East Road, Broad Brook, CT
- Status
- Closed July 15, 2026
- First filing
- March 26, 2025
- Latest filing
- November 2, 2026
- Filings
- 96
- Documents
- Not copied yet
This docket's record on the current system (opens in a new tab)
Decisions and notices
What the Authority has issued in this docket, newest first.
- July 15, 2026Decision Final Decision
- June 18, 2026Draft decision Draft Decision
- April 14, 2026Notice of Technical Meeting Revised Notice - Sched, for 5/…
- April 7, 2026Notice Notice of Technical Meeting
- March 9, 2026Notice Extension of Statutory Deadlin…
- November 14, 2025Notice Procedural Order
- November 14, 2025Notice Extension of Statutory Deadlin…
- September 16, 2025Notice Notice of Statutory Deadline E…
- July 21, 2025Notice Procedural Order
- April 1, 2025Notice Notice of Extension of Statuto…
- March 26, 2025Notice Notice of Proceeding; Procedural Order
Filings
Showing 1–50 of 96 filings.
November 2026
CorrespondenceNovember 2, 2026 · Eversource Energy- CorrespondenceNovember 2, 2026 · Day Pitney LLP
2026.11.02 Ltr. Gaudiosi - NextEra Response PURA Docket 25-03-11
- CorrespondenceNovember 2, 2026 · Day Pitney LLP
2026.11.02 Ltr. Gaudiosi - NextEra Response PURA Docket 25-03-11
October 2026
CorrespondenceOctober 19, 2026 · PURAPURA Corresp. to Eversource and NextEra re: Updates
- CorrespondenceOctober 2, 2026 · R. Dana Van Steenburgh
Comments
- CorrespondenceOctober 1, 2026 · State Rep. Jaime Foster, State Senator Saud Anwar, First Selectman Jason Bowsza
Comments
September 2026
Compliance Filing, Order No. ProceduralSeptember 15, 2026 · EversourceSupplemental Compliance
- CorrespondenceSeptember 14, 2026 · Jason E. Bowsza-First Selectman
Comments
- Ruling on Motion No. 006September 8, 2026 · PURA
Ruling: Granted
August 2026
Motion No. 006August 12, 2026 · NextEra Energy Resources, LLC and Eversource Energypower quality study and equipment inspection plan
- Compliance Filing, Order No. 1August 12, 2026 · Filed in Error, See Motion 6
power quality study and equipment inspection plan
July 2026
DecisionJuly 15, 2026 ·Final Decision
- ExceptionJuly 1, 2026 · Town of East Windsor
Written Exceptions
- ExceptionJuly 1, 2026 · NextEra Energy Resources, LLC
Written Exceptions
- ExceptionJuly 1, 2026 · CL&P dba Eversource Energy
Written Exceptions
June 2026
Draft decisionJune 18, 2026 ·Draft Decision
May 2026
Interrogatory responsesMay 22, 2026 · NextEra Energy Resources, LLCAnswers to questions 52 thru 56
- Interrogatory responsesMay 22, 2026 · CL&P dba Eversource Energy
Answers to questions 47 thru 51
- InterrogatoriesMay 15, 2026 · RSR
To Eversource, questions 47 thru 51
- CorrespondenceMay 7, 2026 · PURA
Technical Meeting Agenda 05/14/2026
April 2026
Response to Motion No. 004April 30, 2026 · Day PitneyResponse type: Supplemental Filing
- Ruling on Motion No. 004April 20, 2026 · PURA
Ruling: Granted in part - Denied in part
- Ruling on Motion No. 003April 20, 2026 · PURA
Ruling: Granted
- Notice of Technical MeetingApril 14, 2026 ·
Revised Notice - Sched, for 5/…
- Interrogatory responsesApril 8, 2026 · CL&P dba Eversource Energy
Answers to questions 42
- CorrespondenceApril 8, 2026 · Day Pitney LLP
2026.04.08 Ltr. J. Gaudiosi re NextEra Request to Reschedule May 1 Technical Meeting, CT PURA Docket No. 25-03-11
- NoticeApril 7, 2026 ·
Notice of Technical Meeting
- CorrespondenceApril 7, 2026 · Christina Dahl
Comments
- CorrespondenceApril 7, 2026 · Amanda Berube
Comment
- Response to Motion No. 004April 6, 2026 · Day Pitney
Response type: Comment
- Response to Motion No. 004April 1, 2026 · Dept. Of Energy & Envir. Prot.
Response type: Comment
- Interrogatory responsesApril 1, 2026 · NextEra Energy Resources, LLC
Answers to questions 46 thru 46
- Interrogatory responsesApril 1, 2026 · CL&P dba Eversource Energy
Answers to questions 40, 41, 43, 44, 45
- CorrespondenceApril 1, 2026 · Nicole Paradise
Comments
- CorrespondenceApril 1, 2026 · Christina Dahl
Comments
March 2026
Ruling on Motion No. 005March 31, 2026 · PURARuling: Granted
- CorrespondenceMarch 31, 2026 · Amanda Berube
Comments
- Motion No. 005March 27, 2026 · CL&P dba Eversource Energy
Extension for East Road Broad Brook
- CorrespondenceMarch 25, 2026 · Amanda Berube
Comments
- InterrogatoriesMarch 18, 2026 · RSR
To NextEra Energy Resources, LLC; NextEra Energy Services CT, LLC, questions 46 thru 46
- InterrogatoriesMarch 18, 2026 · RSR
To Eversource, questions 40 thru 45
- Response to Motion No. 004March 17, 2026 · Day Pitney
Response type: Supplemental Filing
- NoticeMarch 9, 2026 ·
Extension of Statutory Deadlin…
February 2026
Motion No. 004February 27, 2026 · NextEra Energy Resources, LLC2026.02.27 Ltr. Gaudiosi - DG Solar III East Windsor Update to PURA, NextEra Energy Resources_ LLC Motion for Protective Order_ Affidavit and Protective Order (Docket No. 25-03-11)
- CorrespondenceFebruary 26, 2026 · Day Pitney LLP
2026.02.26 Ltr. Gaudiosi NextEra, CT PURA Docket No. 25-03-11
January 2026
CorrespondenceJanuary 30, 2026 · Day Pitney LLP2026.01.30 Ltr. J. Gaudiosi, DG Connecticut Solar III January 2026 PURA Update, CT PURA Docket No. 25-03-11