Docket 86-03-28RE01
Petition By Putnum Hydropower, Inc. for Contract Approval and Declaratory Rulings Re: Sale of Electricity to The Connecticut Light and Power Company - Buyout
Decisions and notices6
What the Authority has issued in this docket, newest first.
Filings21
21 filings
Draft Decision
Brief, 06/16/2000 ()
Hrgs. closed 9/13/00…
CL&P requests to Amend the Protective Order and supporting Affidavit.
Transcript: Hearing
Transcript: Continued Hearing
Transcript: Confidential Hearing
Transcript: Confidential Hearing
Exhibits 004 - 4 requested
Exhibits 003 - 3 requested
Exhibits 002 - 2 requested
Exhibits 001 - 1 requested
About this docket
- Docket number
- 86-03-28RE01
- Status
- Closed July 26, 2000
- First filing
- April 21, 1999
- Latest filing
- July 26, 2000
- Public filings
- 21
- Documents
- On the current system
Search this docket
Reading a docket
- Motions ask the Authority for something; each gets a ruling.
- Interrogatories are written questions, usually from Authority staff; the answers are filed as responses.
- A draft decision comes before the final decision; participants may file exceptions to it.