Docket 97-01-15
DPUC Review of Electric Companies Cost of Service and Unbundled Tariffs
Decisions and notices7
What the Authority has issued in this docket, newest first.
Filings106
Showing 51–100 of 106 filings
- OCC
To CL&P, questions 54 thru 81
OCC in receipt of ltr from CL&P of Aug 13, 97
Transcript: Hearing
Req to reschedule hrg to 8/21/97
Req. the Dept. Deny UI's request.
Motion to extend schedule or exclude pre-filed testimony of OCC
Req to Extend Schedule or Exclude Pre-Filed Testimony of OCC
Ltr re: CL&P received Fax after close of bus on Monday Aug 11, 97
Direct Testimony of James D. Cotton & Steven W. Ruback
Requests cost for OCC's consultants be billed 50/50
Regarding consultant costs.
- CL&P and UI
Corres. 07/25/1997 () - OCC recommended that cost of soncultant be divided equally between companies (CL&P and UI)
- PRO
To CL&P, questions 99 thru 99
- EL-OCC
To CL&P & OCC, questions 1 thru 3
- AG-EL
To UI, questions 1 thru 7
Unbundled proposal
Unbundling proposal
Regarding OCC Consultant
Company will not be submitting alternative unbundling proposal ,reserves the right to cross examiine all witnesses.
About this docket
- Docket number
- 97-01-15
- Status
- Closed July 29, 1998
- First filing
- January 22, 1997
- Latest filing
- September 13, 2006
- Public filings
- 106
- Documents
- On the current system
Search this docket
Reading a docket
- Motions ask the Authority for something; each gets a ruling.
- Interrogatories are written questions, usually from Authority staff; the answers are filed as responses.
- A draft decision comes before the final decision; participants may file exceptions to it.