Docket 97-04-10
Application of The Southern New England Telephone Company for Approval of Total Service Long Run Incremental Cost Studies and Rates for Unbundled Elements
Decisions and notices2
What the Authority has issued in this docket, newest first.
Filings161
31 filings of the selected types
Extension of time to file Interrogatories for AT&T and MCI and to comply with DPUC order.
Req Extension of time to 10/24/97 to file interrogs
Requests - SNET Provide Certain Relevant Information to The Parties Immediately
Requests - ext. of time to file revised Cost Studies.
Req Modification to the Schedule
Request that the September 30, 1997 hearing be cancelled.
MCI req. an extension of time to file prefiled tetimony two weeks sfter SNET file imterrogdtoyy responses
Req an Extension of time until Aug 8, 97 to respond to Interrogs
Req. an ext of time to respond to interrogatories TE- 12 through TE-27
Req. an ext. of time to respond to Cox CT Telcom, LLC interrogatories
Req qn Extension of time to file testimony
Req an Extension of time to June 18, 97 to file Reply comments
Req. that the Dept. accept MCI's proposal for an extension of the schedule
Req. P.O. For the Disclosure of Bellcore Cost Models
Req Hearing be rescheduled to third week of Aug
Motion for Party Status
About this docket
- Docket number
- 97-04-10
- Status
- Closed May 20, 1998
- First filing
- April 4, 1997
- Latest filing
- August 20, 1999
- Public filings
- 161
- Documents
- On the current system
Search this docket
Reading a docket
- Motions ask the Authority for something; each gets a ruling.
- Interrogatories are written questions, usually from Authority staff; the answers are filed as responses.
- A draft decision comes before the final decision; participants may file exceptions to it.