Correspondence re Incomplete Application
Files1
26-05-10 Comment on Completeness of Application.pdf
PDF · 270 KB · 2 pagesText searchable
Download 26-05-10 Comment on Completeness of Application.pdfRead the text of 26-05-10 Comment on Completeness of Application.pdf
Kimberly White
Direct Dial: [phone removed]
Email: [email removed]
August 5, 2026
Public Utilities Regulatory Authority
Ten Franklin Square
New Britain, Connecticut 06051
Re:
Docket No. 26-05-10 – Application of CL&P dba Eversource Energy to Amend its
Rate Schedule
Dear Commissioners:
The Office of Consumer Counsel (“OCC”) and the Office of Education, Outreach, and
Enforcement (“EOE”) respectfully submit to the Public Utilities Regulatory Authority
(“Authority”) this comment regarding the completeness of the Application filed by Eversource
Energy (“Eversource”) on July 14, 2026, requesting a rate increase.
The Authority has not currently indicated whether or not the Application is complete.
Without a ruling from the Authority that the Application is incomplete, OCC and EOE had to begin
discovery to protect the limited review time afforded by the statutory deadline. Further, OCC and
EOE jointly filed a proposed schedule with Eversource, but as that proposal indicated, the
proposed schedule should not be read as OCC and EOE taking a position on the completeness of
the Application.1
To the contrary, after initial review, OCC and EOE have multiple reasons to believe the
Application may be incomplete. First, the Application still lacks the public filing of many
components, as noted in Motion No. 9 and its Ruling. Second, and more importantly, the
Application contains storm costs and their supporting documentation through only March 2025.
It is unclear if the Application is seeking to recover the full storm costs for 2025, but Exhibit CLPREVREQ-2, WP C-3.26, cell E32, refers to “Actual Costs” in 2025 and bases the requested storm
reserve funding on those costs averaged with storm costs from other years. If Eversource intends
to request recovery of the full 2025 storm costs or uses the full 2025 storm costs to set ongoing
rates, those costs must be included in the Application.2 As seen in Docket No. 25-12-13 and from
the 2024 storms presented herein, the evidence supporting storm costs is substantial. If the
Authority determines the Application is now complete but Eversource waits until later in this
proceeding to file the remaining 2025 invoices, OCC and EOE will be prejudiced by the lack of
time to conduct a meaningful review.
The statutory timeframe for a rate case already offers woefully little time to review the
1
OCC and EOE proposed a schedule for the Authority to consider if it considered the Application complete. From
OCC’s and EOE’s perspective, the proposed schedule did not presume the Application was complete, but rather,
protected their interests in scheduling if the Authority was issuing a schedule at this time.
2
Interrogatory OCC-143 asked if Eversource intends to recover more 2025 storm costs in this proceeding. Its response
is due on August 13, 2026.
Application of a utility whose rates have remained unreviewed for almost a decade. Allowing
Eversource to string out its filing over months and further limit the time of that review harms
ratepayers and curtails OCC’s and EOE’s ability to thoroughly review the filing. The term
“complete” must have some meaning.
OCC and EOE thank the Authority for its consideration as it proceeds with the scheduling
conference.
Respectfully submitted,
STATE OF CONNECTICUT
OFFICE OF CONSUMER COUNSEL
CLAIRE E. COLEMAN
CONSUMER COUNSEL
By: /s/ Kimberly White
Kimberly White
Attorney
10 Franklin Square
New Britain, CT 0605[phone removed]
OFFICE OF EDUCATION, OUTREACH, &
ENFORCEMENT
By: /s/ Britany Wyman
Brittany Wyman
Attorney
10 Franklin Square
New Britain, CT 0605[phone removed]
CERTIFICATE OF SERVICE
I do hereby certify that on this day the foregoing document was filed with the
Public Utilities Regulatory Authority, and copies thereof were served upon each person designated
on the official service list in this proceeding in accordance with R.C.S.A. § 16-1-15.
Dated at New Britain, Connecticut this 5th day of August, 2026.
/s/Kimberly White
Commissioner of the Superior Court
An Affirmative Action/Equal Employment Opportunity Employer
As listed on the current system
Corres. 08/05/2026 [26-05-10] (OCC) - Correspondence re Incomplete Application