Interrogatory responses
Answers to questions 2, 4
Filed by Connecticut Light and Power Company dba Eversource Energy2 files
Part of docket 26-05-10Files2
ALLCO-002_Final.pdf
PDF · 162 KB · 2 pagesText searchable
Download ALLCO-002_Final.pdfRead the text of ALLCO-002_Final.pdf
ALLCO-004_Final.pdf
PDF · 147 KB · 2 pagesText searchable
Download ALLCO-004_Final.pdfRead the text of ALLCO-004_Final.pdf
The Connecticut Light and Power Company
d/b/a Eversource Energy
Docket No. 26-05-10
Set ALLCO-01
Date Issued August 20, 2026
ALLCO-002
Page 1 of 2
Date Filed: September 14, 2026
Witness:
Brendan J. O’Brien, Garrett J. Murray, Leanne M. Landry and Jeffrey D.
Turano
Request from: ALLCO
Question:
State the total dollar amount of CIAC and interconnection-related payments collected from DER
and QF interconnection customers in each year 2018 through 2025, and explain precisely how
those amounts are reflected in (a) rate base, (b) the Test Year revenue requirement, and (c) the
Rate Year revenue requirement proposed in this docket, identifying the specific schedules and
workpapers.
Response:
CL&P objects to this request on the ground that it is an improper effort by Allco to use this rate
case proceeding to obtain discovery for purposes of a lawsuit that it filed against the Company on
August 10, 2026, in the United States District Court for the District of Connecticut (Civil Action
No. 3:26-cv-1277), outside of and in contravention of the rules of procedure that govern discovery
in that lawsuit.
Without waiving said objection, please refer to the Company’s response to ALLCO-001 i for CIAC
year-end balances from 2018 through 2025. CIAC and interconnection-related payments received
by the Company reduce the cost of construction or plant placed in service. CIAC is recognized as
an offset to the underlying capital project. CIAC would not be considered a component of rate
base until the underlying capital project is placed in service. At that time, the underlying capital
project costs in rate base would be wholly offset by CIAC at the time of final project billing and
reconciliation. In the Company’s next cost of service update, the rate base and the Rate Year
revenue requirement will reflect the CIAC and the underlying capital project cost for projects
placed in service.
Prior Referenced Response:
i
ALLCO-001 Question:
Identify each FERC account in which the Company records CIAC and other amounts collected from interconnection
customers for interconnection studies, upgrades, and overheads, and state the balance in each such account at the end
of each year 2018 through 2025 and as of the most recent month available.
The Connecticut Light and Power Company
d/b/a Eversource Energy
Docket No. 26-05-10
Set ALLCO-01
Date Issued August 20, 2026
ALLCO-002
Page 2 of 2
ALLCO-001 Response:
CL&P objects to this request on the ground that it is an improper effort by Allco to use this rate case proceeding to
obtain discovery for purposes of a lawsuit that it filed against the Company on August 10, 2026, in the United States
District Court for the District of Connecticut (Civil Action No. 3:26-cv-1277), outside of and in contravention of the
rules of procedure that govern discovery in that lawsuit.
Without waiving said objection, the Company records CIAC activity from interconnection customers to FERC
Account No. 252500. The table below summarizes the end of year balance in FERC Account No. 252500 from 2018
through June 2026.
As listed on the current system
Question(s) Answered 2, 4 (Connecticut Light and Power Company dba Eversource Energy) Date Filed: 09/14/2026