Interrogatory responses
Answers to questions 147, 153
Filed by The Connecticut Light and Power Company2 files
Part of docket 26-05-10Files2
ALLCO-147_Final.pdf
PDF · 98 KB · 2 pagesText searchable
Download ALLCO-147_Final.pdfRead the text of ALLCO-147_Final.pdf
ALLCO-153_Final.pdf
PDF · 186 KB · 4 pagesText searchable
Download ALLCO-153_Final.pdfRead the text of ALLCO-153_Final.pdf
The Connecticut Light and Power Company
d/b/a Eversource Energy
Docket No. 26-05-10
Set ALLCO-11
Date Issued September 24, 2026
ALLCO-147
Page 1 of 2
Date Filed: October 20, 2026
Witness:
Warren R. Boutin, Timothy J. Griffin, Leanne M. Landry and Jeffrey D.
Turano
Request from: ALLCO
Question:
(Follow-up to ALLCO-064 — the CIAC Tax Adder and the Notice 2016-36 safe harbor.) The
Company’s response to ALLCO-064 states that it “generally deems distribution system
interconnection payments to be taxable income and are therefore charged a tax adder/gross up,”
that “all CIAC Tax Adders charged on CIAC payments were treated as taxable CIAC (there were
none under the safe harbor),” and that the CIAC Tax Adder “was calculated based on the full cost
estimate of the project, including the Company’s construction overhead costs and loaders.” (a)
State the legal and factual basis for the Company’s position that the safe harbor of Notice 2016-36
does not apply to a generator interconnected to the Company’s distribution system that sells its
output to the Company under a power purchase agreement, a REC contract, or a PURPA legally
enforceable obligation, identifying each requirement of the Notice the Company contends such a
generator fails to meet, and produce every memorandum, opinion, or analysis (including any by
the Company’s Tax Department or outside tax advisers) addressing the application of Notice 201636 or its predecessor Notices to distribution-level generator interconnections. (b) State whether the
Company has ever, since January 1, 2016, evaluated any individual distribution generator
interconnection for eligibility under the safe harbor, and if so identify each and the conclusion
reached. (c) For each Allco Application and each project in the Allco Clusters, state the CIAC Tax
Adder amount charged, the CIAC estimate to which it was applied, the portion of that estimate
consisting of percentage overhead, CIAC, or other loaders, and the CIAC Tax Adder computed on
that loader portion. (d) State the total CIAC Tax Adder collected from distributed generation and
qualifying facility interconnection customers (as distinct from all CIAC customers) in each year
2017 through 2025, and reconcile those amounts to the annual “CIAC Tax Gross-Up” totals in
ALLCO-064, Attachment 1 (which sum to approximately $9.32 million on approximately $97.75
million of CIAC for 2017–2025). (e)The “Gross-Up Refund” column of ALLCO-064, Attachment
1 (Account 1864T0) is zero in every month of every year from 2017 through 2025. State whether
the Company has ever refunded any portion of a CIAC Tax Adder to an interconnection customer
when the final accounting showed actual cost below the estimate on which the Adder was
computed; if not, explain why a tax gross-up computed on estimated overhead that was never
incurred is retained; and state the amount of CIAC Tax Adder attributable to the difference
between estimated and actual cost for each Allco Cluster final accounting. (f) State whether, when
the Company computes the refund owed on a final accounting, the refund includes the CIAC Tax
Adder on the refunded amount, and identify where in the four December 2024 Final Accounting
Reports for the Allco Clusters any such Adder refund appears. (g) State whether the Company has
ever amended a federal income tax return, or claimed a deduction or basis adjustment, on account
The Connecticut Light and Power Company
d/b/a Eversource Energy
Docket No. 26-05-10
Set ALLCO-11
Date Issued September 24, 2026
ALLCO-147
Page 2 of 2
of a CIAC amount that was later refunded, and reconcile the statement in ALLCO-064(e) that
refunds are “typically small amounts” with the $257,260.19 computed for the Allco Clusters.
Response:
CL&P objects to this request on the ground that it is an improper effort by ALLCO to use this rate
case proceeding to obtain discovery for purposes of a lawsuit that it filed against the Company on
August 10, 2026, in the United States District Court for the District of Connecticut (Civil Action
No. 3:26-cv-1277), outside of and in contravention of the rules of procedure that govern discovery
in that lawsuit.
CL&P further objects to this request on the ground that it is not within the scope of the proceeding
to review the Company’s application to amend its existing rates schedules because the
interrogatory either seeks information specific to Allco projects or seeks information that Allco
views as relevant to its specific projects.
CL&P further objects to this request on the ground that it calls for a legal conclusion.
Without waiving said objections, the Company states as follows:
(a) – (c)
The Company has received inquiries, post-June 1, 2016, from distribution generator
interconnection entities regarding the safe harbor. However, unless and until the Company secures
written consent from such a generator, it cannot disclose such generator’s tax compliance strategy
to a third party.
(d)
The Company does not track transaction level data associated with distributed generation
and/or qualifying interconnection customers separate and distinct from all CIAC customers;
therefore, this information cannot be provided as it cannot be queried.
(e)
The Company performs a final reconciliation once the work is completed. If the requested
CIAC payment exceeds actual charges, the customer is refunded the overpayment not including
the CIAC Tax Adder. If the interconnection project was canceled, the Company returns the
estimated CIAC and associated Tax Adder to the customer.
(f)
The refund does not include a pro-rated CIAC Tax Adder in the refunded amount.
(g)
The Company has not filed an amended federal income tax return related to an amount of
CIAC, later refunded.
As listed on the current system