Interrogatory responses

Answers to questions 55, 56, 59

ResponseFiled by Connecticut Light and Power Company dba Eversource Energy5 files
Part of docket 26-05-10Open
  • Electric
Application of The Connecticut Light and Power Company d/b/a Eversource Energy to Amend its Rate Schedules

Files5

The searchable text of a spreadsheet keeps the sheet names, column headings and text cells. Download the file for the figures.

  1. Part 1

    [Sheet: 14M GRP SHARE Cost Allocation] Substation | Station | Level 2 DER Application (MVA) | Level 1 DER Applications (MVA) | DER Group Study (MVA) | Reserved Operational Capacity (MVA) | Enabled Electrification (MVA) | Enabled Level 1 DER Capacity (MVA) | Enabled Level 2 DER Capacity - Group Study (MVA) | Enabled Level 2 DER Capacity- Post Group Study (MVA) | Substation Tracy 14M Mansfield 12J Brooklyn 30Y New Bulk Station Distribution Line | Station | Level 2 DER Application (MVA) | Level 1 DER Applications (MVA) | DER Group Study (MVA) | Reserved Operational Capacity (MVA) | Incremental New Operational Capacity | Enabled Level 1 DER Capacity (MVA) | Enabled Level 2 DER Capacity - Group Study (MVA) | Enabled Level 2 DER Capacity- Post Group Study (MVA) | Distribution Line Cost Allocation | Cost Allocation - Substations | Cost Allocation - Distribution Line Group Study - Distribution and DER Customer Substation Capacity/Cost Allocation | Group Study - Distribution and DER Customer Distribution Line Capacity/Cost Allocation Station | MVA | Investment | Distribution | MVA | Investment ($M) | ($M) Enabled Load Allocation - Distribution Customer Benefit | Enabled Load Allocation - Distribution Customer Benefit Enabled Reliability Benefit - Distribution Customer Benefit | Enabled Reliability Benefit - Distribution Customer Benefit Enabled Future Small DER - Distribution Customer Benefit (Including Future Small DG) | Enabled Future Small DER - Distribution Customer Benefit (Including Future Small DG) Enabled DER by Total Investments - DER Customer Benefit | Enabled DER by Total Investments - DER Customer Benefit Enabled Queue Large DER (Group Study Large DER) | Enabled Queue Large DER (Group Study Large DER) Enabled Future Large DER (Future Large DERs) | Enabled Future Large DER (Future Large DERs) Prospective Share Fee $ 392 /kW [Sheet: 14R GRP SHARE Cost Allocation] Substation | Station | Level 2 DER Application (MVA) | Level 1 DER Applications (MVA) | DER Group Study (MVA) | Reserved Operational Capacity (MVA) | Enabled Electrification (MVA) | Enabled Level 1 DER Capacity (MVA) | Enabled Level 2 DER Capacity - Group Study (MVA) | Enabled Level 2 DER Capacity- Post Group Study (MVA) | Substation Campville 14R Canton 5R Still River 55G & BESS Distribution Line | Station | Level 2 DER Application (MVA) | Level 1 DER Applications (MVA) | DER Group Study (MVA) | Reserved Operational Capacity (MVA) | Incremental New Operational Capacity | Enabled Level 1 DER Capacity (MVA) | Enabled Level 2 DER Capacity - Group Study (MVA) | Enabled Level 2 DER Capacity- Post Group Study (MVA) | Distribution Line Cost Allocation | Cost Allocation - Substations | Cost Allocation - Distribution Line Group Study - Distribution and DER Customer Substation Capacity/Cost Allocation | Group Study - Distribution and DER Customer Distribution Line Capacity/Cost Allocation Station | MVA | Investment | Distribution | MVA | Investment ($M) | ($M) Enabled Load Allocation - Distribution Customer Benefit | Enabled Load Allocation - Distribution Customer Benefit Enabled Reliability Benefit - Distribution Customer Benefit | Enabled Reliability Benefit - Distribution Customer Benefit Enabled Future Small DER - Distribution Customer Benefit (Including Future Small DG) | Enabled Future Small DER - Distribution Customer Benefit (Including Future Small DG) Enabled DER by Total Investments - DER Customer Benefit | Enabled DER by Total Investments - DER Customer Benefit Enabled Queue Large DER (Group Study Large DER) | Enabled Queue Large DER (Group Study Large DER) Enabled Future Large DER (Future Large DERs) | Enabled Future Large DER (Future Large DERs) Prospective Share Fee $ 192 /kW [Sheet: 13B SHARE Cost Allocation] Substation | Station | Level 2 DER Application (MVA) | Level 1 DER Applications (MVA) | DER Group Study (MVA) | Reserved Operational Capacity (MVA) | Enabled Electrification (MVA) | Enabled Level 1 DER Capacity (MVA) | Enabled Level 2
  2. Part 2

    DER Capacity - Group Study (MVA) | Enabled Level 2 DER Capacity- Post Group Study (MVA) | Substation Frybrook 13B Distribution Line | Station | Level 2 DER Application (MVA) | Level 1 DER Applications (MVA) | DER Group Study (MVA) | Reserved Operational Capacity (MVA) | Incremental New Operational Capacity | Enabled Level 1 DER Capacity (MVA) | Enabled Level 2 DER Capacity - Group Study (MVA) | Enabled Level 2 DER Capacity- Post Group Study (MVA) | Distribution Line Cost Allocation | Cost Allocation - Substations | Cost Allocation - Distribution Line Group Study - Distribution and DER Customer Substation Capacity/Cost Allocation | Group Study - Distribution and DER Customer Distribution Line Capacity/Cost Allocation Station | MVA | Investment | Distribution | MVA | Investment ($M) | ($M) Enabled Load Allocation - Distribution Customer Benefit | Enabled Load Allocation - Distribution Customer Benefit Enabled Reliability Benefit - Distribution Customer Benefit | Enabled Reliability Benefit - Distribution Customer Benefit Enabled Future Small DER - Distribution Customer Benefit (Including Future Small DG) | Enabled Future Small DER - Distribution Customer Benefit (Including Future Small DG) Enabled DER by Total Investments - DER Customer Benefit | Enabled DER by Total Investments - DER Customer Benefit Enabled Queue Large DER (Group Study Large DER) | Enabled Queue Large DER (Group Study Large DER) Enabled Future Large DER (Future Large DERs) | Enabled Future Large DER (Future Large DERs) Prospective Share Fee $ 308 /kW

Text of ALLCO-059_Final.pdf

Extracted from the file · 2 pages · 4,909 characters

As listed on the current system

Question(s) Answered 55, 56, 59 (Connecticut Light and Power Company dba Eversource Energy) Date Filed: 09/22/2026