Interrogatory responses
Answers to questions 103
Filed by Connecticut Light and Power Company dba Eversource Energy1 file
Part of docket 26-05-10Files1
ALLCO-103_Final.pdf
PDF · 102 KB · 2 pagesText searchable
Download ALLCO-103_Final.pdfRead the text of ALLCO-103_Final.pdf
The Connecticut Light and Power Company
d/b/a Eversource Energy
Docket No. 26-05-10
Set ALLCO-09
Date Issued September 21, 2026
ALLCO-103
Page 1 of 2
Date Filed: October 08, 2026
Witness:
Warren R. Boutin, Leanne M. Landry and Jeffrey D. Turano
Request from: ALLCO
Question:
For each calendar year 2017 through 2025, state the number of distributed-generation
interconnection projects for which construction was completed, and, of those, the number for
which a final accounting or reconciliation of actual costs against amounts collected was performed
and the number for which a final accounting report was issued to the interconnecting customer.
Identify the written policy or procedure governing when a final accounting is performed and when
a report is issued to the customer, including any standard interval after project completion, and
produce it. If no written policy exists, state so and describe the practice and who administers it.
Response:
CL&P objects to this request on the ground that it is an improper effort by ALLCO to use this rate
case proceeding to obtain discovery for purposes of a lawsuit that it filed against the Company on
August 10, 2026, in the United States District Court for the District of Connecticut (Civil Action
No. 3:26-cv-1277), outside of and in contravention of the rules of procedure that govern discovery
in that lawsuit.
Without waiving said objection, the final accounting process is performed manually and is not
tracked or maintained in PowerClerk. The data is entered and tracked across multiple systems.
Accordingly, the requested information is inconsistent or not available in Power Clerk and would
require a manual review of the underlying records.
Section 1.2 of the PURA-approved Interconnection Guidelines states, in part, “At the conclusion
of the project, the EDC will reconcile actual vs. estimated cost and reimburse or bill the Generator
accordingly. Cost estimates provided to applicants will be subject to a six-month true-up.” Please
also refer to the Company’s response to ALLCO-005 i.
Prior Referenced Response:
i
ALLCO-005 Question:
Provide an aging schedule of all unpaid interconnection-cost refunds owed to interconnection customers as of the most
recent date available, showing for each: the project, the date the refund obligation was determined, the amount, and
the reason payment has not been made; and describe the Company’s policy, procedure, and standard timeline for
paying such refunds.
The Connecticut Light and Power Company
d/b/a Eversource Energy
Docket No. 26-05-10
Set ALLCO-09
Date Issued September 21, 2026
ALLCO-103
Page 2 of 2
ALLCO-005 Response:
CL&P objects to this request on the ground that it is an improper effort by Allco to use this rate case proceeding to
obtain discovery for purposes of a lawsuit that it filed against the Company on August 10, 2026, in the United States
District Court for the District of Connecticut (Civil Action No. 3:26-cv-1277), outside of and in contravention of the
rules of procedure that govern discovery in that lawsuit.
Without waiving said objection, the standard timeline for paying interconnection-cost refunds is set forth in Section
5.3.2 of the PURA-approved form of Interconnection Agreement.
As listed on the current system
Question(s) Answered 103 (Connecticut Light and Power Company dba Eversource Energy) Date Filed: 10/08/2026