Interrogatory responses
Answers to questions 11
Files6
CLF-011 Attachment 14.pdf
PDF · 3.1 MB · 23 pagesText searchable
Download CLF-011 Attachment 14.pdfRead the text of CLF-011 Attachment 14.pdf
CLF-011 Attachment 15.pdf
PDF · 2.8 MB · 13 pagesText searchable
Download CLF-011 Attachment 15.pdfRead the text of CLF-011 Attachment 15.pdf
CLF-011 Attachment 16.pdf
PDF · 4.6 MB · 20 pagesText searchable
Download CLF-011 Attachment 16.pdfRead the text of CLF-011 Attachment 16.pdf
CLF-011 Attachment 17.pdf
PDF · 4.3 MB · 142 pagesText searchable
Download CLF-011 Attachment 17.pdfRead the text of CLF-011 Attachment 17.pdf
CLF-011 Attachment 18.pdf
PDF · 2.1 MB · 22 pagesText searchable
Download CLF-011 Attachment 18.pdfRead the text of CLF-011 Attachment 18.pdf
CLF-011 Attachment 19.pdf
PDF · 1.9 MB · 18 pagesText searchable
Download CLF-011 Attachment 19.pdfRead the text of CLF-011 Attachment 19.pdf
Page 73 of 142
The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued August 13, 2026 CLF-011 Attachment 17 Page 73 of 142 Hearing Exhibit 102, Attachment GKJ-2 Proceeding No. 25A-____EG Page 73 of 142 Figure 4-72: Achievable Potential by Sector and Measure Type Delivered to RX-7 (Keystone) 120 100 Peak Gas Savings (mscfh) Transport 80 Commercial 60 40 Residential 20 0 2025 2026 2027 2028 BE EE 2029 2030 Behavior DR 73 2031 2032 Gas Equipment 2033Page 74 of 142
The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued August 13, 2026 CLF-011 Attachment 17 Page 74 of 142 Hearing Exhibit 102, Attachment GKJ-2 Proceeding No. 25A-____EG Page 74 of 142 Figure 4-73: Achievable Potential by Sector and Measure Type Delivered to RG-12 (Grand Lake) 14 12 Transport Commercial Peak Gas Savings (mscfh) 10 8 6 Residential 4 2 0 2025 2026 2027 2028 BE EE 2029 2030 Behavior DR 2031 2032 2033 Gas Equipment Achievable potential, delivered to each constraint point from each geographic area was calculated separately. As shown in Table 4-24, the Breckenridge and Keystone are both helped the most by actions taken immediately adjacent to the constraint, with some additional benefits derived from nearby areas. Meanwhile, the Grand Lake constraint can only be solved by actions taken in Grand Lake. The modeling also showed that actions in Area 4 have minimal benefits at the constraint point in the Eastern Mountain Gas System, which should not be surprising, given that Area 4 is in the Southern Mountain System, with only a very limited connection to the Eastern Mountain Gas System. Table 4-24: Achievable Potential by Geographic Area of Installation RB-4 (Breckenridge) (mscfh) RX-7 (Keystone) (mscfh) RG-12 (Upper Grand Lake) (mscfh) Total (mscfh) Area 2 - Breckenridge 155 7 0 162 Area 2 - Keystone 35 56 0 91 Area 3 46 15 0 60 Other Area 2 28 12 0 40 Other Area 1 21 8 0 29 Geographic Area 74Page 75 of 142
The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued August 13, 2026 CLF-011 Attachment 17 Page 75 of 142 Hearing Exhibit 102, Attachment GKJ-2 Proceeding No. 25A-____EG Page 75 of 142 Geographic Area RB-4 (Breckenridge) (mscfh) RX-7 (Keystone) (mscfh) RG-12 (Upper Grand Lake) (mscfh) Total (mscfh) Area 1 – Other Grand Lake 19 7 0 26 Area 1 - Grand Lake Top 8 3 12 23 Area 4 6 2 0 8 Total 306 105 12 423 4.7 NPA DSM Solution Development Conclusions The NPA DSM solution development effort resulted in a series of conclusions that feed directly into the design of NPA portfolios. These conclusions are reiterated below for convenience. 4.7.1 Building Type, End Use Disaggregation, and Geographic Area Analysis Conclusions Conclusion 1: Based on analysis of existing peak hour gas demand, single family residential buildings were identified as having the highest peak hour loads, with master-metered multifamily and lodging the commercial areas with the highest peak hour loads. • Implication for Portfolio and Plan Development: The development of the portfolios and plan should focus on residential solutions first. Within commercial areas, the portfolios and plan should focus extra effort on master-metered multifamily and lodging. Conclusion 2: Space heating is by far the largest end use contributing to peak hour consumption. • Implication for Portfolio and Plan Development: Space heating should be the focus of NPA portfolio and plan development, with a particular focus on residential space heating. Conclusion 3: Areas 2 and 3 in Summit County including Breckenridge, Keystone, other parts of Area 2, and Area 3 deliver the highest fraction of peak hour reductions to Breckenridge and Keystone. The immediate area around Grand Lake (Grand Lake Top) is the only area that can deliver peak hour reductions to the Grand Lake constraint. • Implication for Portfolio and Plan Development: The delivery of NPA solutions should focus on Area 2 and Area 3, including Summit County and the area running from Minturn to Leadville, including the towns of Minturn, Red Cliff, and Leadville, plus surrounding area, as well as the immediate area around Grand Lake. 4.7.2 Residential Survey Conclusions Conclusion 4: Survey respondents in the mountains were much more likely to rent out their home on a shortterm basis than respondents on the front range. Conclusion 5: Survey respondents in the mountains had higher income and education than respondents on the front range. • Implication for Portfolio and Plan Development: Messaging and marketing should be adjusted to reflect the different homeowner demographics in the mountains. Conclusion 6: Many more homes in the mountains have boilers when compared to the front range. Conclusion 7: Very few homes in the mountains have cooling currently or are looking to add cooling. 75Page 76 of 142
The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued August 13, 2026 CLF-011 Attachment 17 Page 76 of 142 Hearing Exhibit 102, Attachment GKJ-2 Proceeding No. 25A-____EG Page 76 of 142 • Implication for Portfolio and Plan Development: Marketing heat pumps to customers in the mountains will need to focus more on ductless heat pumps installed at homes with boilers and selling other benefits besides comfort from cooling. Conclusion 8: A large majority of survey respondents are unfamiliar with existing Company program offerings and other incentive opportunities. • Implication for Portfolio and Plan Development: Increased marketing focused on program awareness may be helpful. Conclusion 9: Respondents were highly sensitive to upfront costs of equipment in their willingness to participate. Willingness to participate did not change appreciably above 100% of costs being covered. Conclusion 10: Respondent were less sensitive to increases in operating costs, with 50% of customers willing to install a free heat pump, even with an increase in operating costs of $1,000 per year. • Implication for Portfolio and Plan Development: Offering 100% incentives will dramatically increase willingness to participate, even if operating costs are going up significantly. 4.7.3 Commercial Survey Conclusions Conclusion 11: A significant number of respondents indicated they were somewhat likely to add to cooling. • Implication for Portfolio and Plan Development: This represents an opportunity to sell some businesses on the cooling benefits of heat pumps. Conclusion 12: 20% of respondents had snow melt systems connected to a boiler and 7% had outdoor fireplaces. • Implication for Portfolio and Plan Development: This represents an opportunity for facility-specific DR actions. Conclusion 13: 80% of respondents were interested in installing a free heat pump, even with an increase in operating costs. • Implication for Portfolio and Plan Development: 100% incentives may motivate people to adopt heat pumps, even with an increase in operating costs. 4.7.4 Contractor/Builder Interview Conclusions Conclusion 14: Builders and contractors reported low familiarity and low trust of heat pumps. They are concerned about the opportunity to completely displace gas heating due to high altitudes and cold mountain temperatures. • Implication for Portfolio and Plan Development: The interviews indicated that significant training and preparation of market structure will be needed as manufacturers, distributors, and architects will need to lead the contractors and builders to choose new electrification technologies. 4.7.5 Potential Conclusions Conclusion 15: Technical potential: Electrification measures have the highest technical potential, allowing for technical potential to eliminate almost 100% of existing gas load. • Implication for Portfolio and Plan Development: In the long run, electrification has the highest potential, so preparing the market for electrification will be required for large reductions in the long run. Conclusion 16: Economic supply curves: Electrification measures have high costs, driven primarily by cost of capacity increases. • Implication for Portfolio and Plan Development: If electrification measures can be developed with lower peak demand impacts (e.g. using other backup systems besides electric resistance), economics of electrification can be significantly reduced. 76Page 77 of 142
The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued August 13, 2026 CLF-011 Attachment 17 Page 77 of 142 Hearing Exhibit 102, Attachment GKJ-2 Proceeding No. 25A-____EG Page 77 of 142 Conclusion 17: Achievable potential: The highest potential comes from high efficiency gas equipment, electrification, and DR. • Implication for Portfolio and Plan Development: Plan should develop solutions for all three of these areas and not exclude any of them from the solution. 77Page 78 of 142
The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued August 13, 2026 CLF-011 Attachment 17 Page 78 of 142 Hearing Exhibit 102, Attachment GKJ-2 Proceeding No. 25A-____EG Page 78 of 142 5 Alternative Portfolios Alternative portfolios, comprised of a variety of measures to alleviate the capacity constraint, were developed for specific geographies based on the underlying customer types. The alternative portfolios were optimized for the lowest cost, while meeting operational requirements. To develop portfolios, a multistep approach was implemented, as demonstrated in Figure 5-1. Figure 5-1: Alternative Portfolio Development Process Five alternative portfolios were developed for the Eastern Mountain Gas System. The alternative portfolios included an Electric Portfolio, several NPA-Only Portfolios, and several Hybrid Portfolios. The alternative portfolio analysis focused on the least cost among all achievable potential solutions. A baseline gas infrastructure project was supplied by the Company for comparative purposes to measure the success of the alternative portfolios. Each alternative portfolio was evaluated based on its ability to meet the capacity constraint in the Eastern Mountain Gas System. If an alternative portfolio was able to meet the capacity constraint, then the cost effectiveness of the portfolio was assessed using a cost benefit analysis framework. Five potential alternative portfolios were considered for alleviating the capacity constraint in the Eastern Mountain Gas System. The alternative portfolios can be divided into two categories: 1. Demand Side Portfolios – these alternative portfolios included an Electric Portfolio and two NPA-Only Portfolios, differing in their inclusion of gas consuming appliance incentives and transport customers. 2. Two Hybrid Portfolio options combing NPA portfolios with supplemental supply infrastructure. Once assembled, the alternative portfolios were evaluated under four criteria through an iterative process. The first threshold an alternative portfolio must successfully pass was whether the alternative portfolio could meet the capacity constraint and close the gap within 10 years. If the alternative portfolio could not achieve this baseline, the portfolio was removed from additional consideration. If the portfolio was able to close the capacity constraint within 10 years, the alternative portfolio was analyzed using the cost-benefit analysis tool to assess 1) program and incentive costs, 2) electric system impacts, and 3) emission impacts. Additionally, the Company provided a baseline gas infrastructure solution to test the other alternative portfolios for cost effectiveness. These alternative portfolios and their potential for alleviating the capacity constraint in the Eastern Mountain Gas System are presented in the following sections. 78Page 79 of 142
The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued August 13, 2026 CLF-011 Attachment 17 Page 79 of 142 Hearing Exhibit 102, Attachment GKJ-2 Proceeding No. 25A-____EG Page 79 of 142 5.1 Demand Side Portfolios The three alternative portfolios considered as demand side portfolios were the Electric Portfolio and two NPAOnly Portfolios. The NPA-Only Portfolios can be further broken down into additional portfolios, inclusive and exclusive of transport customers and LDC growth. Electric Only Portfolio The Electric Only Portfolio was a portfolio comprised of only customer side solutions (i.e. NPA measures and technologies) including DR, building electrification, and non-equipment gas EE measures for residential and commercial customers, not including transport customers. The portfolio excluded incentives for gas consuming equipment. While gas demand response and building shell measures are not strictly electrification measures, they are included in the electric portfolio as they do not promote gas infrastructure or gas appliance installation. This potential alternative portfolio was analyzed to determine whether the capacity constraint could be solved without the need for gas consuming appliance incentives. Figure 5-2, Figure 5-3, and Figure 5-4 below show the peak hour savings contribution to the Electric Only Portfolio over time for the different measure types by building sector, compared to the shortfall in Breckenridge, Keystone, and Grand Lake, respectively. Figure 5-2: Electric Portfolio Peak Hour Impacts Delivered to RB-4 (Breckenridge) 500 450 400 Peak Gas Savings (mscfh) 350 Persisting Shortfall 300 250 200 Commercial 150 100 Residential 50 0 2025 2026 2027 BE 2028 EE 2029 2030 Behavior 79 2031 DR 2032 2033 ShortfallPage 80 of 142
The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued August 13, 2026 CLF-011 Attachment 17 Page 80 of 142 Hearing Exhibit 102, Attachment GKJ-2 Proceeding No. 25A-____EG Page 80 of 142 Figure 5-3: Electric Portfolio Peak Hour Savings Delivered to RX-7 (Keystone) 140 120 Persisting Shortfall Peak Gas Savings (mscfh) 100 80 Commercial 60 40 Residential 20 0 2025 2026 2027 2028 BE EE 2029 2030 Behavior 80 2031 DR 2032 2033 ShortfallPage 81 of 142
The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued August 13, 2026 CLF-011 Attachment 17 Page 81 of 142 Hearing Exhibit 102, Attachment GKJ-2 Proceeding No. 25A-____EG Page 81 of 142 Figure 5-4: Electric Portfolio Peak Hour Savings Delivered to RG-12 (Grand Lake) 10 9 Commercial 8 Peak Gas Savings (mscfh) 7 6 5 Residential 4 3 2 1 0 2025 2026 2027 2028 BE EE 2029 2030 Behavior 2031 DR 2032 2033 Shortfall Table 5-1 below shows a summary of cumulative program impacts by year. Electric capacity costs make up a significant portion of the overall direct utility costs associated with this portfolio. The resulting portfolio has direct utility costs of $425,000 per mscfh delivered in 2033.10 10 The direct utility costs include electric capacity costs, incentive costs, and program administration and marketing costs. The costs per mscfh are calculated by dividing the 2033 value for “Total Program + Electric Capacity Costs” by the sum of 2033 RB-4 Peak Hour Gas Impact, RX-7 Peak Hour Gas Impact, and RG-12 Peak Hour Gas Impact. 81Page 82 of 142
The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued August 13, 2026 CLF-011 Attachment 17 Page 82 of 142 Hearing Exhibit 102, Attachment GKJ-2 Proceeding No. 25A-____EG Page 82 of 142 Table 5-1: Electric NPA Portfolio Cumulative Impacts and Costs by Year Year Premiselevel Peak Hour Gas Impact (mscfh)11 RB-4 Peak Hour Gas Impact (mscfh)12 RX-7 Peak Hour Gas Impact (mscfh)13 RG-12 Peak Hour Gas Impact (mscfh)14 Electric Grid Impacts (kW)15 Marginal Electric Capacity Costs16 Program + Incentive Costs17 Total Program + Electric Capacity Costs18 2025 17 11 4 1 982 $185,459 $ 3,212,344 $3,397,803 2026 43 28 10 1 2,262 $621,181 $ 7,425,854 $8,047,035 2027 68 45 15 2 3,949 $1,397,116 $12,856,411 $14,253,526 2028 96 63 22 3 6,191 $2,637,916 $19,848,203 $22,486,120 2029 126 83 29 4 9,156 $4,509,717 $28,701,532 $33,211,249 2030 160 105 36 5 13,047 $7,230,142 $39,819,603 $47,049,745 2031 199 130 45 6 18,102 $11,080,277 $53,694,417 $64,774,695 2032 245 160 56 8 24,607 $16,418,642 $70,926,054 $87,344,696 2033 299 195 68 9 32,933 $23,705,823 $92,214,523 $115,920,346 While the Electric Portfolio did have the achievable potential to solve the shortfall in Grand Lake in 2029 and beyond, it did not have the achievable potential to solve the capacity shortfall within the next 10 years in Breckenridge or Keystone. Therefore, this portfolio was omitted from further analysis. Realizing an Electric Only Portfolio would not be viable in meeting the capacity constraint, the PA team determined that energy efficient gas appliances would likely be required to further reduce the shortfall, leading to the development of the NPA-Only Portfolios. NPA-Only Portfolios After determining the Electric Portfolio was insufficient for alleviating the capacity constraint in the Eastern Mountain Gas System, the PA team tested the potential of including gas equipment EE and including combination transport gas customers who are also the Company’s electric customers in two additional portfolios. With the addition of gas appliance incentives, the team examined the achievable potential of the NPA-Only alternative portfolios to assess if the capacity constraint could be alleviated with the addition of energy efficient gas appliances. Given the magnitude of the capacity shortfall, the team modeled uptake when customers were given 100% of incremental costs for technologies that reduced their peak load. Thus, the 11 Premise-level Peak Hour Gas Impact is defined by the reductions in peak gas that occurs at the premise level, with reductions defined as positive. This is before adjusting for the impact at constraint points, as discussed in section 4.3. 12 RB-4 Peak Hour Gas Impact is defined as the peak hour gas impacts achieved at the shortfall location RB-4 in Breckenridge, with reductions defined as positive. It is calculated by multiplying Premise-level Peak Hour Gas Impact in each geographic area by the associated Peak Demand Ratios as explained in section 4.3. 13 RX-7 Peak Hour Gas Impact is defined as the peak hour gas impacts achieved at the shortfall location RX-7 in Keystone, with reductions defined as positive. It is calculated by multiplying Premise-level Peak Hour Gas Impact in each geographic area by the associated Peak Demand Ratios as explained in section 4.3. 14 RG-12 Peak Hour Gas Impact is defined as the peak hour gas impacts achieved at the shortfall location RG-12 in Grand Lake, with reductions defined as positive. It is calculated by multiplying Premise-level Peak Hour Gas Impact in each geographic area by the associated Peak Demand Ratios as explained in section 4.3. 15 Electric Grid Impacts are defined as the expected winter peak demand impacts associated with the NPA solution, with increases defined as positive. 16 Marginal Electric Capacity Costs are calculated by multiplying Electric Grid Impacts by annual cost of generation, transmission, and distribution capacity. 17 Program and Incentive Costs are defined as the expected incentive costs paid to program participating customers by the Company, plus the incremental program administration and marketing costs associated with the NPA. 18 Total Program + Electricity Capacity Costs represent the total direct utility costs and are calculated by adding the Marginal Electric Capacity Costs and the Program and Incentive Costs. 82
Text of CLF-011 Attachment 18.pdf
Extracted from the file · 22 pages · 55,502 characters
Text of CLF-011 Attachment 19.pdf
Extracted from the file · 18 pages · 27,716 characters
As listed on the current system
Question(s) Answered 11 (Connecticut Light and Power Company dba Eversource Energy) Date Filed: 08/27/2026