Interrogatory responses
Answers to questions 11
Files6
CLF-011 Attachment 14.pdf
PDF · 3.1 MB · 23 pagesText searchable
Download CLF-011 Attachment 14.pdfRead the text of CLF-011 Attachment 14.pdf
CLF-011 Attachment 15.pdf
PDF · 2.8 MB · 13 pagesText searchable
Download CLF-011 Attachment 15.pdfRead the text of CLF-011 Attachment 15.pdf
CLF-011 Attachment 16.pdf
PDF · 4.6 MB · 20 pagesText searchable
Download CLF-011 Attachment 16.pdfRead the text of CLF-011 Attachment 16.pdf
CLF-011 Attachment 17.pdf
PDF · 4.3 MB · 142 pagesText searchable
Download CLF-011 Attachment 17.pdfRead the text of CLF-011 Attachment 17.pdf
CLF-011 Attachment 18.pdf
PDF · 2.1 MB · 22 pagesText searchable
Download CLF-011 Attachment 18.pdfRead the text of CLF-011 Attachment 18.pdf
CLF-011 Attachment 19.pdf
PDF · 1.9 MB · 18 pagesText searchable
Download CLF-011 Attachment 19.pdfRead the text of CLF-011 Attachment 19.pdf
Page 93 of 142
The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued August 13, 2026 CLF-011 Attachment 17 Page 93 of 142 Hearing Exhibit 102, Attachment GKJ-2 Proceeding No. 25A-____EG Page 93 of 142 Year Premiselevel Peak Hour Gas Impact (mscfh) RB-4 Peak Hour Gas Impact (mscfh) RX-7 Peak Hour Gas Impact (mscfh) RG-12 Peak Hour Gas Impact (mscfh) Electric Grid Impacts (kW) Marginal Electric Capacity Costs Program + Incentive Costs Total Program + Electric Infrastructure Costs 2032 377 254 87 10 30,839 $21,648,220 $102,855,043 $124,503,262 2033 454 306 105 12 41,205 $31,177,571 $133,638,398 $164,815,970 While Hybrid Portfolio 1 was able to meet the full required shortfall, the results of Hybrid Portfolio 1 showed relatively high costs of NPA solutions, along with an underutilization of supplemental supply expected in the later years. Higher utilization of the supplemental supply would allow for a smaller (and lower cost) NPA portfolio, by eliminating some of the additional NPA solutions after the shortfall is closed. As a result of these findings in Hybrid Portfolio 1, the team decided to explore further cost optimization in the development of Hybrid Portfolio 2. 5.2.2 Hybrid Portfolio 2 As discussed above, the installation of large quantities of NPA measures has a higher cost than continued use of supplemental supply. Therefore, it was determined to reduce the scope of the NPA portfolio after the initial four years of installation and eliminate high-cost measures and reduce the size of the NPA portion in Hybrid Portfolio 2 after this point to solve the constraint, with continued consistent utilization of supplemental supply in the later years. The resulting Hybrid Portfolio 2 supports system reliability while reducing capitalized gas infrastructure spend. To optimize the cost of Hybrid Portfolio 2, the PA team applied a more stringent measure-level costeffectiveness screen to installations occurring after 2029. This rigorous screen resulted in many higher cost measures, including most full electrification measures, to have their incremental NPA incentives eliminated from Hybrid Portfolio 2 after 2029. The team continued to model additional adoption of gas furnaces, without incentives, as required by federal code after 2028. Figure 5-14, Figure 5-15, and Figure 5-16 show the peak hour gas capacity delivered by Hybrid Portfolio 2 over time for the different measure types by building sector, compared to the shortfall in Breckenridge, Keystone, and Grand Lake, respectively, while adding in contribution from supplemental supply. It’s important to recognize that the peak hour capacity delivered is based on extreme conditions used in gas modeling. As a result, there’s a distinction between usage of always-on NPA solutions, including EE and building electrification, and the usage of dispatchable resources, like DR and the supplemental supply solutions. 93Page 94 of 142
The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued August 13, 2026 CLF-011 Attachment 17 Page 94 of 142 Hearing Exhibit 102, Attachment GKJ-2 Proceeding No. 25A-____EG Page 94 of 142 Figure 5-14: Hybrid Portfolio 2 Peak Hour Gas Capacity Delivered to RB-4 (Breckenridge) 94Page 95 of 142
The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued August 13, 2026 CLF-011 Attachment 17 Page 95 of 142 Hearing Exhibit 102, Attachment GKJ-2 Proceeding No. 25A-____EG Page 95 of 142 Figure 5-15: Hybrid Portfolio 2 Peak Hour Gas Capacity Delivered to RX-7 (Keystone) 95Page 96 of 142
The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued August 13, 2026 CLF-011 Attachment 17 Page 96 of 142 Hearing Exhibit 102, Attachment GKJ-2 Proceeding No. 25A-____EG Page 96 of 142 Figure 5-16: Hybrid Portfolio 2 Peak Hour Gas Capacity Delivered to RG-12 (Grand Lake) 8 7 Transport Commercial Peak Gas Savings (mscfh) 6 5 4 Residential 3 2 1 0 2025 BE 2026 EE 2027 Behavior 2028 DR 2029 2030 2031 Gas Equipment 2032 2033 Temporary Measures Shortfall In consultation with the Company’s implementation team, the team decided to reduce the area served in this portfolio to focus on the areas with the highest concentration of potential savings. The PA team determined that installations in Area 2, Area 3, and Upper Grand Lake, collectively deliver over 85% of the achievable potential benefits in Breckenridge, Keystone, and Grand Lake. As such, the Company’s implementation team and PA team determined that the eligible area for implementation will include Area 2, Area 3, and Upper Grand Lake, which includes Summit County and the towns of Grand Lake, Leadville, Red Cliff, and Minturn. As a result, the same potential for savings is expected, but realized over a small geography. By concentrating program marketing effort in a smaller area, the team believes that it will be able to meet the NPA goals more cost-effectively. The supplemental supply equipment allows for operational contingency against potentially slower than predicted NPA technology adoption, reduces stranded asset risk as compared to piping reinforcements, and provides peak hour demand shaving, as seen in Figure 5-17. 96Page 97 of 142
The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued August 13, 2026 CLF-011 Attachment 17 Page 97 of 142 Hearing Exhibit 102, Attachment GKJ-2 Proceeding No. 25A-____EG Page 97 of 142 Figure 5-17: Hybrid Portfolio 2 Design Day Peak Hour Demand in 2033 Table 5-5 below shows the cumulative impacts and costs associated with the NPA portion of Hybrid Portfolio 2. The NPA portion has a direct utility cost of $290,000 per mscfh. The NPA-related costs of Hybrid Portfolio 2 are less than half the NPA-related cost of Hybrid Portfolio 1, while the supplemental supply and temporary measures are anticipated to have similar costs. While the savings include savings from furnaces after the federal standard goes into effect in 2029, the costs do not include costs from furnaces after this point in time. Table 5-5: Hybrid Portfolio 2 NPA Cumulative Impacts and Costs by Year Year Premiselevel Peak Hour Gas Impact (mscfh) RB-4 Peak Hour Gas Impact (mscfh) RX-7 Peak Hour Gas Impact (mscfh) RG-12 Peak Hour Gas Impact (mscfh) Electric Grid Impacts (kW) Marginal Electric Capacity Costs Program + Incentive Costs Total Program + Electric Infrastructure Costs 2025 27 19 6 1 1,174 $248,040 $5,573,471 $5,821,511 2026 65 44 15 2 2,715 $830,722 $12,735,168 $13,565,890 2027 107 72 25 3 4,745 $1,866,448 $21,568,011 $23,434,460 2028 153 104 36 4 7,424 $3,516,535 $33,376,197 $36,892,732 2029 199 135 46 5 10,951 $5,994,280 $44,781,454 $50,775,734 2030 209 142 49 6 10,950 $8,521,579 $45,691,415 $54,212,994 2031 219 148 51 6 10,948 $11,099,468 $46,648,431 $57,747,898 2032 229 155 53 6 10,946 $13,728,907 $47,661,588 $61,390,495 2033 239 162 56 7 10,943 $16,410,857 $48,742,311 $65,135,169 5.2.3 Supply Side Measures Supporting the Hybrid Portfolio Given the Electric and NPA-Only alternative portfolios were unable to solve for the capacity constraint, a modular LNG site in Breckenridge and a modular CNG site in Keystone were included as part of the Hybrid Portfolios to support system reliability and growth. 97Page 98 of 142
The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued August 13, 2026 CLF-011 Attachment 17 Page 98 of 142 Hearing Exhibit 102, Attachment GKJ-2 Proceeding No. 25A-____EG Page 98 of 142 Assumptions around the costs associated with these supply side measures, provided by the Company, included temporary LNG and CNG equipment lease payments and modular CNG and LNG costs at Keystone and Breckenridge, respectively. Costs were provided in nominal dollars and reflect the in-service/retire dates. 5.3 Results, and Recommendations Following development and analysis of optimized alternative portfolios, results support recommendation of Hybrid Portfolio 2. Portfolios were developed to optimized for cost and GHG objectives, while meeting operational requirements. Hybrid Portfolio 2 solves the capacity constraints and is the lowest cost option, while also supporting less reliance on gas infrastructure and progress towards end-use decarbonization. Figure 5-18 shows the 10-year long term plan cost estimates for the potential solutions evaluated. Figure 5-18: 10-Year Long Term Plan Cost Estimates19 Hub and Spoke (Maximum Scenario) Hub and Spoke (Minimum Scenario) Electric Portfolio (Infeasible - Capacity Shortfall Not Met) NPA Portfolio 1 (Infeasible - Capacity Shortfall Not Met) NPA Portfolio 2 (Infeasible - Capacity Shortfall Not Met) Hybrid Portfolio 1 Hybrid Portfolio 2 $0 Gas Infrastructure $100 NPA Program $200 ($ millions) $300 $400 Electric Capacity (Marginal) The implementation of the NPA measures and technologies in Hybrid Portfolio 2 results in end-use emissions reductions, with emissions decreasing 150% as compared to the maximum gas infrastructure solution . The PA team performed the cost-benefit analysis of both Hybrid Portfolio 1 and Hybrid Portfolio 2. As seen in Figure 5-19, Hybrid Portfolio 2 resulted in being more cost-effective as compared to Hybrid Portfolio 1 under both the primary modified total resource cost test (EMTRC) and the secondary expanded, rate-payer impact measure test (ERIM). Hybrid Portfolio 2 is more cost effective than Hybrid Portfolio 1 because Hybrid Portfolio 2 eliminates the implementation of higher-cost NPA measures after the initial four years when the constraint is met. Both Hybrid Portfolio 1 and 2 utilize supplemental supply, the difference being Hybrid Portfolio 2 favors utilization of supplemental supply at a consistent level as the lower-cost alternative to more expensive NPA measures. 19 Includes the marginal cost of electric capacity. 98Page 99 of 142
The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued August 13, 2026 CLF-011 Attachment 17 Page 99 of 142 Hearing Exhibit 102, Attachment GKJ-2 Proceeding No. 25A-____EG Page 99 of 142 Figure 5-19: Cost Effectiveness Comparison of Hybrid Portfolios $250,000,000 $200,000,000 $150,000,000 $200 $193 $128 $140 $100,000,000 $50,000,000 $0 Hybrid Portfolio Hybrid Portfolio Hybrid Portfolio Hybrid Portfolio 1 - EMTRC 2 - EMTRC 1 - ERIM 2 - ERIM As seen in Figure 5-20 to 5-22, the modular LNG equipment at the proposed Breckenridge site is assumed to be fully utilized at the equipment maximum flow rate of 285 mscfh in the 2033-‘34 heating season on Design Day. If required, additional LNG equipment can be added if the NPA program adoption is less successful than anticipated. The modular CNG equipment at the proposed Keystone site is assumed to be utilized at a flow rate of 69 mscfh in the 2033-’34 heating season on Design Day. If required, additional modular supplemental supply equipment can be added if the NPA program adoption is less successful than anticipated. Figure 5-20: Hybrid Portfolio 2 Modular LNG Breckenridge 99Page 100 of 142
The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued August 13, 2026 CLF-011 Attachment 17 Page 100 of 142 Hearing Exhibit 102, Attachment GKJ-2 Proceeding No. 25A-____EG Page 100 of 142 Figure 5-21: Hybrid Portfolio 2 Modular CNG Keystone Figure 5-22: Hybrid Portfolio 2 Modular CNG Grand Lake Hybrid Portfolio 2, which includes gas appliances, reflects the implementation of 34,000 customers within the NPA project area with 80% assumed to be residential and 20% commercial. Hybrid Portfolio 2 includes Behavior Response programs (47% of program), Thermostat DR (9%), Gas EE Appliances (13%), Building Shell Measures (4%), and Electrification (1%). Hybrid Portfolio 2, in addition to being cost competitive and alleviating the capacity constraint, provides strategic considerations to the Company, especially as the Company navigates decarbonization in an emerging regulatory landscape. By implementing the Hybrid Portfolio 2, the Company can maintain physical flexibility of resources and planning flexibility over the next ten years. Through 2029, to meet the capacity constraint, the Company can fund and progress NPA measures and solutions, allowing the Company to learn about the implementation of NPAs while alleviating the constraint and progressing their decarbonization targets. 5.4 Electrification Analysis Lastly, to understand the impact of the NPA measures on the electric distribution grid, the electric potential peak impacts at the feeder level were estimated using the portfolio analysis results, using the following steps: 1. For each premise, disaggregate peak hour gas load by end use. For each end use, apply assumed gas combustion efficiency and assumed electric efficiency during peak hours to estimate resulting 100Page 101 of 142
The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued August 13, 2026 CLF-011 Attachment 17 Page 101 of 142 Hearing Exhibit 102, Attachment GKJ-2 Proceeding No. 25A-____EG Page 101 of 142 energy consumption during peak hour. Add up the peak hour electricity consumption to estimate peak hour electricity demand. 2. Estimate the total added electric demand for 100% electrification for each geographic area in the analysis by summing up the premise-level results from step 1. 3. Compile the estimated added electric demand for each geographic area in Hybrid Portfolio 2, after making adjustments for the planned area for implementation (Area 2, Area 3, and Grand Lake). 4. For each geography, derive the ratio of total potential electric demand increase by dividing the results of step 3 by the results of step 4. 5. For each feeder, estimate the added peak electric demand for 100% electrification by summing up the results of step 1 the feeder level. 6. Map each feeder to a geographic area. 7. For each feeder, multiply the results of step 5 by the electric demand increase ratio for the geographic area corresponding to each feeder to get feeder-level winter peak demand increases. The resulting winter peak demand increases from the hybrid NPA solution, for each feeder, by year, are shown in Table 5-6 below. Increases stop after 2029, because electrification measures are assumed to be discontinued in Hybrid Portfolio 2 after 2029, along with other measures with poor cost-effectiveness. 101Page 102 of 142
The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued August 13, 2026 CLF-011 Attachment 17 Page 102 of 142 Hearing Exhibit 102, Attachment GKJ-2 Proceeding No. 25A-____EG Page 102 of 142 Table 5-6. Hybrid Portfolio 2 Winter Peak Demand Increase by Feeder and Year Cumulative Winter Peak Demand Increase by Year (kW) Feeder 2025 2026 2027 2028 2029 2030 2031 2032 2033 BREC2564M 63 145 252 396 585 585 585 585 584 BREC2565M 118 271 473 740 1,091 1,091 1,091 1,090 1,090 BREC2566M 50 116 202 315 461 461 461 461 461 BREC2568M 53 123 214 332 486 486 486 486 486 CLIM2531M 25 58 101 157 228 228 228 228 228 DILL2556M 34 79 137 214 315 315 315 315 315 DILL2557M 34 79 137 214 316 316 316 316 316 DILL2558M 13 30 53 82 120 120 120 120 120 DILL2559M 45 104 181 285 423 423 422 422 422 DILL2591M 6 13 22 34 50 50 50 50 50 GILM2525M 4 9 16 24 36 36 36 36 36 LEAD1205M 3 6 11 17 26 26 26 26 26 LEAD1207M 7 15 27 42 62 62 62 62 62 LEAD1209M 35 81 142 222 327 327 327 327 327 MAYF2541M 28 66 114 177 258 258 258 258 258 MAYF2542M 26 60 105 164 241 241 241 241 241 PTAR2105M 71 163 284 444 655 655 655 654 654 PTAR2107M 79 183 320 501 741 741 741 741 741 SUMM2604M 89 206 359 562 829 829 829 829 828 SUMM2605M 28 65 114 178 263 263 263 263 263 SUMM2606M 30 70 123 191 281 280 280 280 280 5.5 Cost-Benefit Analysis The cost-benefit analysis provides the framework and support for evaluating the preferred Hybrid Portfolio 2 as compared to a gas infrastructure solution.20 The primary cost effectiveness test and the modified total resource cost test measures the net cost and benefits of an alternative portfolio, including both energy savings and non-energy benefits. These include utility incentives, equipment costs, and utility system cost that result from the implementation of NPAs, as well as social impacts such as avoided social emissions cost and other non-energy benefits. To support the alternative portfolio results and recommendation, a primary and secondary cost effectiveness tests were calculated through a cost-benefit analysis framework. A modified total resource cost test, which is modified to include the benefit of avoided social emissions and other non-energy benefits, was utilized as the primary cost effectiveness test. An expanded ratepayer impact measure test was utilized as a secondary test to review the potential impacts to electric and gas customer rates and was expanded to include the benefit of 20 The PA team ran the cost-benefit analysis of both Hybrid Portfolio 1 and Hybrid Portfolio 2. Hybrid Portfolio 2 resulted in being more cost-effective under both the primary modified total resource cost and the secondary expanded, rate-payer impact measure test, leading to Hybrid Portfolio 2 being compared to the baseline gas infrastructure solution within this section. 102
Text of CLF-011 Attachment 18.pdf
Extracted from the file · 22 pages · 55,502 characters
Text of CLF-011 Attachment 19.pdf
Extracted from the file · 18 pages · 27,716 characters
As listed on the current system
Question(s) Answered 11 (Connecticut Light and Power Company dba Eversource Energy) Date Filed: 08/27/2026