Interrogatory responses
Answers to questions 54, 56
Filed by The Connecticut Light and Power Company3 files
Part of docket 26-05-10Files3
BETP-054_Final.pdf
PDF · 131 KB · 2 pagesText searchable
Download BETP-054_Final.pdfRead the text of BETP-054_Final.pdf
BETP-054 Attachment 1.pdf
PDF · 584 KB · 2 pagesText searchable
Download BETP-054 Attachment 1.pdfRead the text of BETP-054 Attachment 1.pdf
BETP-056_Final.pdf
PDF · 87 KB · 2 pagesText searchable
Download BETP-056_Final.pdfRead the text of BETP-056_Final.pdf
The Connecticut Light and Power Company
d/b/a Eversource Energy
Docket No. 26-05-10
Set DEEP-01
Date Issued October 06, 2026
BETP-054
Page 1 of 2
Date Filed: October 27, 2026
Witness:
Jared A. Lawrence
Request from: Department of Energy and Environmental Protection
Question:
(AMI) Please provide a detailed breakdown of what subcomponents and their respective costs
constitute the $432 million in back office system expenses necessary to begin AMI deployment.
Response:
The $432 million figure was reviewed within the AMI Stakeholder Review of the BCA Refresh in
May 2026, please refer to BETP-054, Attachment 1, for a copy of the slide of the referenced figure.
The $432 million in back-office system costs represents the rounded cumulative total of the
projected six-year nominal capital and O&M costs for the Meter Data Management System
(“MDMS”), Customer Information System (“CIS”), and Load Settlement. The cost estimates were
developed using actual costs, ongoing costs, and indicative estimates, as applicable to each system.
Please refer to Table 1 below 1 for a cumulative total of all capital and O&M projected costs, and
refer to Exhibit CLP-AMI-3, page 16.
Table 1
Back Office System
6-Year
Nominal 6-Year
Nominal Totals
Capital
O&M*
Data $63,000,000
$21,000,000
$74,000,000
System
Meter
Management
(MDMS)
Customer Information $212,500,00
System (CIS)
Load Settlement
$28,800,000
Total
$304,300,000
1
Note: these figures are rounded.
$102,400,000
$314,900,000
$4,000,000
$127,400,000
$32,800,000
$431,700,000
The Connecticut Light and Power Company
d/b/a Eversource Energy
Docket No. 26-05-10
Set DEEP-01
Date Issued October 06, 2026
BETP-054
Page 2 of 2
The following provides a high-level breakdown of the costs by back-office system and the basis
for each estimate. For additional detail regarding the underlying cost components, assumptions,
and calculation methodology, see Exhibit CLP-AMI-3, Section D.3 – Back-Office Systems.
•
MDMS – $63.0 million capital and $21.0 million O&M. The estimate is based on actual
upfront and ongoing Massachusetts AMI Program costs for implementing and maintaining
MDMS, repurposed for Connecticut. These costs include application software, interfaces,
procurement and contracting services, system implementation services, consulting
services, internal labor, hardware, program management, data conversion, training, and
ongoing service and maintenance fees. For a full breakdown of all costs, please refer to
pages: 127–132.
•
CIS – $212.5 million capital and $102.4 million O&M. The estimate is based on
indicative Massachusetts CIS replacement and integration costs, modeled for Connecticut,
including system integration, software and licensing, data conversion, implementation, and
ongoing support. For a full breakdown of all costs, please refer to pages: 135–140.
•
Load Settlement – $28.8 million capital and $4.0 million O&M. The estimate is based
on indicative estimates informed by similar estimates performed for the Massachusetts
AMI Program, including labor, hardware, software, procurement and contracting, system
integration, data conversion, and ongoing maintenance and licensing. For a full breakdown
of all costs, please refer to pages: 142–143.
As listed on the current system
Question(s) Answered 54, 56 (The Connecticut Light and Power Company) Date Filed: 10/27/2026