Interrogatory responses

Answers to questions 5, 13, 20

ResponseFiled by Connecticut Light and Power Company dba Eversource Energy10 files
Part of docket 26-05-10Open
  • Electric
Application of The Connecticut Light and Power Company d/b/a Eversource Energy to Amend its Rate Schedules

Files10

Text of NECTA-020_Final.pdf

Extracted from the file · 1 page · 1,075 characters

Text of NECTA-020 Attachment 1.pdf

Extracted from the file · 1 page · 179 characters

Text of NECTA-020 Attachment 2.pdf

Extracted from the file · 9 pages · 9,146 characters

Text of NECTA-020 Attachment 3 REDACTED.pdf

Extracted from the file · 7 pages · 7,964 characters

Text of NECTA-020 Attachment 4.pdf

Extracted from the file · 5 pages · 2,573 characters

Text of NECTA-020 Attachment 5.pdf

Extracted from the file · 6 pages · 12,657 characters

  1. Page 1

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued September 9, 2026 NECTA-020 Attachment 6 Page 1 of 8 KEY DESIGN DECISION MX_ALDEN ONE_MD_POLE WORK DETAILS, POLE WORK STATUS UPDATES 02/20/2023 Proprietary and Confidential | Copyright © 2023 Accenture. All rights reserved 1
  2. Page 2

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued September 9, 2026 NECTA-020 Attachment 6 Page 2 of 8 AGENDA KDD Summary Current State Business Process Future State Diagram Appendix Current State Diagram Proprietary and Confidential | Copyright © 2023 Accenture. All rights reserved 2
  3. Page 3

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued September 9, 2026 NECTA-020 Attachment 6 Page 3 of 8 KDD SUMMARY (MAXIMO ALDEN ONE) Interface Overview: The purpose of the integration is to notify the joint pole and attachment owners when there is pole install, transfer, removal and abandon work carried out. Maximo publishes the Work Order and CUE information(NS1) into IFACE Table when work order is approved. Informatica (middleware) reads the data from IFACE table and creates a flat file in Alden One Interface format and transfer the file(FTP) through BIZ Manager to AldenOne Server. AldenOne interface process the data and creates conversation ref number (NS2) and sends the information back to Maximo via ETL. Basis Maximo receives ref number (NS2), it changes the status of Pre-requisite PRE544 to COMP. Once Maximo header work order status is changed to FCOMP, the record (NS3) is integrated to AldenOne via ETL. Alden One receives the FCOMP status for the work and then sends back NS4 confirmation to Maximo. Maximo receives the NS4 confirmation and changes the work order Pre-requisite PRE659 to COMP. Key Decision: No Major issues identified and ETL to be repointed. Decision to be Made Design Decision Made Details Repoint vs. Rebuild Repoint Database connection needs to be ​Repointed.​ Realtime vs. Batch Batch Work orders are processed in batch from Maximo to Alden One and Pre-requisite status is integrated to Maximo from Alden One in batch. Recommended Technology Informatica, ETL Frequency/Schedule Once a day ETL(Outbound): Weekdays - Once a day, Mon,Tue,Wed,Thu,Fri; 8:00 PM EST ETL(Inbound): Weekdays -Once a day , Mon,Tue,Wed,Thu,Fri; 10:00 PM EST Proprietary and Confidential | Copyright © 2023 Accenture. All rights reserved 3
  4. Page 4

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued September 9, 2026 NECTA-020 Attachment 6 Page 4 of 8 CURRENT STATE BUSINESS PROCESS System automated update Manual update AldenOne Maximo Start Maximo Maximo Maximo Maximo Maximo Work Order CUE design is created and Joint Pole CU is added with attributes Work Order CUE design is estimated and approved. WO is approved NS2 sent back to Maximo in file format. Upon receiving, PRE544 moved to COMP. Work completed and WO moved to FCOMP NS4 confirmation received, and Conversation Number populated in Maximo. PRE659 moved to COMP MX Status: INIT MX Status: APPR MX Status: WTBS, RDISP, INPRG MX Status: FCOMP MX Status: COMP AldenOne AldenOne AldenOne processes data and creates conversation record (NS1, NS2) Alden One receives the FCOMP status for the work (NS3 received) MX Status: APPR MX Status: FCOMP Work Order continues its lifecycle Proprietary and Confidential | Copyright © 2023 Accenture. All rights reserved 4
  5. Page 5

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued September 9, 2026 NECTA-020 Attachment 6 Page 5 of 8 NH EON BUSINESS PROCESS System automated update Manual update Maximo Start Maximo Maximo Maximo Work Order CUE design is created and Joint Pole CU is added with attributes Work Order CUE design is estimated and approved. WO is approved Conversation number manually entered into Maximo from AldenOne. MX Status: INIT MX Status: APPR AldenOne AldenOne AldenOne processes data and creates conversation record MX Status: APPR MX Status: WTBS, RDISP, INPRG Maximo As-built completed and work order moved to PCLOSE MX Status: PCLOSE, PENDCAN, CANCLOSE AldenOne AldenOne receives status update for Asbuilt or work order cancellation. Along with flag for design and as built differences MX Status: PCLOSE, PENDCAN, CANCLOSE Proprietary and Confidential | Copyright © 2023 Accenture. All rights reserved 5
  6. Page 6

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued September 9, 2026 NECTA-020 Attachment 6 Page 6 of 8 FUTURE STATE DIAGRAM – SAME AS CURRENT STATE Maximo MIF Interface (IFACE) Table 1 Cron Job 8 Maximo DB Maximo 2 3 4 Work order Work order Flat file Managed File Transfer Pre-requisite Status 7 Pre-requisite Status Extract Transform Load Informatica Flat file 5 Receives Work orders and notifies joint pole and attachment owners 6 EDI Biz Manager Alden One Proprietary and Confidential | Copyright © 2023 Accenture. All rights reserved 6
  7. Page 7

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued September 9, 2026 NECTA-020 Attachment 6 Page 7 of 8 APPENDIX Additional Documentation: • Maximo Detailed Analysis (Link to analysis document) • INT_MX_ALDEN ONE_MD_Pole Work Details, Pole Work Status Updates.docx (sharepoint.com) • Middleware Detailed Analysis (Link to analysis document) • ETL Analysis - Maximo Aldenone Maximo - Item Id 35.docx (sharepoint.com) Recent deployed fix in Prod(SCTASK0402999): Updates from Maximo to Alden One system are triggered when status of the work order is changed to APPR and FCOMP. But from past some time updates from Maximo to Alden one was not going in APPR status when Workorder status is progressed continuously through workflow. Incident no: INC0702843. ○Applied Fix: Changed code in script WAM_OBJ_INTTRG_ALDENONE to send eligible workorders to Alden One when status of workorder is changed to APPR. Proprietary and Confidential | Copyright © 2023 Accenture. All rights reserved 7
  8. Page 8

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued September 9, 2026 NECTA-020 Attachment 6 Page 8 of 8 CURRENT STATE DIAGRAM Maximo MIF Interface (IFACE) Table 1 Cron Job 8 2 3 4 Work order Work order Flat file Managed File Transfer Pre-requisite Status 7 Maximo DB Maximo Pre-requisite Status Extract Transform Load Informatica Flat file 5 6 EDI Biz Manager Receives Work orders and notifies joint pole and attachment owners Alden One Proprietary and Confidential | Copyright © 2023 Accenture. All rights reserved 8

As listed on the current system

Question(s) Answered 5, 13, 20 (Connecticut Light and Power Company dba Eversource Energy) Date Filed: 09/23/2026

This filing on the current system (opens in a new tab)