Interrogatory responses

Answers to questions 47

ResponseFiled by Connecticut Light and Power Company dba Eversource Energy1 file
Part of docket 26-05-10Open
  • Electric
Application of The Connecticut Light and Power Company d/b/a Eversource Energy to Amend its Rate Schedules

Files1

  1. Page 1

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set NECTA-01 Date Issued September 09, 2026 NECTA-047 Page 1 of 1 Date Filed: September 23, 2026 Witness: David L. Gladey and Jeffrey Richard Request from: New England Connectivity and Telecommunications Association Question: (Make Ready Work & Related Costs) Refer to Exhibit CLP-ADDITIONS-1 at p.75. Provide the following information: a. List and identify all instances where municipalities and CDOT failed to utilize the AldenOne application process and attached without permission/notice. A complete response will identify each pole by pole number. b. Are unauthorized attachments considered within the Company’s determination of whether make ready costs are billable or non-billable and, if so, how? Response: a. The Company cannot track instances where municipalities and CDOT failed to utilize AldenOne (i.e., the system of record) and attach without notifying the Company. To answer this question, Eversource would need to hire a vendor to conduct an unauthorized attachment audit of the Company’s poles in its service territory. b. The PURA-approved form of Pole Attachment Agreement requires Licensees to submit a pole attachment application for all unauthorized attachments. Consequently, any such make-ready costs are billable to the Licensee.

As listed on the current system

Question(s) Answered 47 (Connecticut Light and Power Company dba Eversource Energy) Date Filed: 09/23/2026