The Connecticut Light and Power Company
d/b/a Eversource Energy
Docket No. 26-05-10
Set OCC-02
Date Issued July 30, 2026
OCC-182
Page 1 of 2
Date Filed: August 13, 2026
Witness:
David L. Gladey and Jeffrey Richard
Request from: Office of Consumer Counsel
Question:
(Poles) Please summarize the process by which a wireline communication attacher gets to attach
its facilities to a utility pole, from the pole attachment permit application, to engineering, makeready and actual attachment. In each step of the process, please state Eversource’s role as SPA.
Response:
Throughout the pole attachment process, Eversource, in its capacity as the Single Pole
Administrator (“SPA”), serves as the central administrative coordinator, facilitating the
progression of attachment requests from application through licensing while coordinating with
engineering organizations, pole owners, attachers, the Incumbent Local Exchange Carrier
(“ILEC”), contractors, and other stakeholders to support compliance with PURA’s established
procedures and timelines.
The pole attachment process generally consists of the following phases:
1. Application Submission - A prospective wireline communications attacher submits a pole
attachment application through Alden One. The SPA's role is to receive the application,
review it for administrative completeness, request additional information as necessary, and
initiate the attachment process.
2. Application Review and Engineering Coordination - Following receipt of a complete
application and applicable fees, the application progresses through the required
engineering review and field survey process conducted by Eversource and the ILEC, if
attachers are applying for attachment on joint owned poles. The SPA's role is to administer
the application workflow, coordinate the progression of the application through the
required review stages, and facilitate communication among the responsible parties.
3. Engineering Review and Make Ready – Eversource and the ILEC Engineering personnel
evaluate the proposed attachment and determine whether make-ready work is required to
accommodate the requested attachment while maintaining applicable safety and
engineering standards. The SPA's role is to coordinate the engineering and make-ready
process, communicate engineering outcomes, administer applicable billing associated with
make-ready work, and monitor the application's progression.
The Connecticut Light and Power Company
d/b/a Eversource Energy
Docket No. 26-05-10
Set OCC-02
Date Issued July 30, 2026
OCC-182
Page 2 of 2
4. Make-Ready Construction - Required make-ready work is performed by the appropriate
utility, communications entity, or contractor, as applicable. The SPA's role is to coordinate
the administrative progression of the attachment request, facilitate communication among
the responsible parties, and monitor completion of required process milestones.
5. Attachment and Licensing - Following completion of all required make-ready activities
and satisfaction of applicable requirements, the attacher installs its facilities and the
attachment process is completed. The SPA's role is to verify that all required process
milestones have been satisfied, administer the licensing process, complete any required
administrative closeout activities, and maintain the associated records.