Interrogatory responses
Answers to questions 377
Filed by Connecticut Light and Power Company dba Eversource Energy2 files
Part of docket 26-05-10Files2
OCC-377_Final.pdf
PDF · 159 KB · 4 pagesText searchable
Download OCC-377_Final.pdfRead the text of OCC-377_Final.pdf
OCC-377 Attachment 1.pdf
PDF · 1001 KB · 1 pageText searchable
Download OCC-377 Attachment 1.pdfRead the text of OCC-377 Attachment 1.pdf
The Connecticut Light and Power Company
d/b/a Eversource Energy
Docket No. 26-05-10
Set OCC-05
Date Issued August 12, 2026
OCC-377
Page 1 of 4
Date Filed: August 28, 2026
Witness:
Brendan J. O’Brien, Garrett J. Murray, John P. DiPaola-Tromba, Sean D.
Redding and Jenna M. Turner
Request from: Office of Consumer Counsel
Question:
Vegetation Management. Refer to WP C-3.31.
a. Provide the actual amounts in the same format for each of the years 2021, 2022, 2023, 2024,
2025 and the Rate Year.
b. Provide an explanation and calculations showing how each rate year adjustment was derived.
c. Provide documentation (contracts, invoices, quotes) supporting each of the Rate Year
increases in Column E.
Response:
a. Please refer to OCC-377, Attachment 1, for the actual amounts provided for each of the
years 2021-2025 and the Rate Year:
b. Please refer to WP C-3.31, columns I, K, and M. The calculations for the Rate Year
adjustments (column M) were derived by subtracting the Rate Year 1 Ending 6/30/28
amount (column K) by the Test Year Pro Forma amount (Column I).
c. Please refer to the response to OCC-102 i for the drivers of the proposed increases from the
test year to the proposed budget in the Rate Year. The Company is currently under the final
year of a four-year contract covering the term 2023-2026. Contracts, invoices, and quotes
cannot be provided for the proposed Rate Year ending 6/30/2028. In May 2026, the
Company commenced the RFP process for the next multi-year contract commencing
January 1, 2027. Vendors are currently preparing their bid submissions. The Company
anticipates finalizing its VMP contract by November 2026 and will update its proposed
VMP work plan in this case based on that final contract pricing (Exhibit CLP-VMP-1, page
39, lines 11-16).
Prior Referenced Response:
i
OCC-102 Question:
(VMP/Budget)
Provide a budget breakdown, including allocation and actuals, for prior years, across the same line items provided in
the proposed program budget for 2027 as outlined in Exhibit CLP-VMP-2 page 25 of 29 (noting that there is a VMP
costs by program component on page 26 of Exhibit CLP-VMP-1, but it does not use all the same line items making
The Connecticut Light and Power Company
d/b/a Eversource Energy
Docket No. 26-05-10
Set OCC-05
Date Issued August 12, 2026
OCC-377
Page 2 of 4
comparison a challenge).
a. For each line item with an increase in the proposed 2027 from the actual 2025 expenditure, explain and
qualify all the drivers of the proposed increase.
b. The 2027 budget breakdown, provided on Exhibit CLP-VMP-2 page 25 of 29, totals 89.6mill, the same as
the total request in the . What will the contribution from Frontier of 13.5M be spent on?
c. Please provide the Company’s analysis demonstrating that the proposed budget does not result in diminishing
returns each year?
d. Provide any analyses comparing the benefits achieved during the initial ETT cycle to those achieved during
subsequent cycles.
OCC-102 Response:
Please refer to Exhibit OCC-102, Attachment 1, for the requested breakdown of the 2025 cost (Exhibit CLP-VMP-1,
page 26) and the proposed budget for 2027 (Exhibit CLP-VMP-2, page 25).
a.
The following program components are new programs and do not have a direct Test Year comparison: Risk
Tree Removals (“RTR”), Reliability Tree Work (“RTW”), and LiDAR.
The following programs had increases from the Test Year actual in 2025 to the proposed budget in 2027:
•
The Roadside Schedule Maintenance increase reflects the estimated costs for a four-year scheduled
maintenance cycle with contractor increases due to inflation. The proposed plan shifts away from
prioritization and field assessment towards a strategy of maintaining the entire circuits all at once.
This approach is driven by the LiDAR pilot results showing high levels of vegetation encroachment
3 years post trimming on circuits due for scheduled maintenance the following year. The budget
was developed using cost per mile estimates that include contractor rate increases. Actual costs will
be updated at the completion of the current RFP for 2027-2030 vegetation management pricing.
•
The RTR budget is converted funds from previous Enhanced Tree Removal (“ETR”) capital dollars
to expense dollars.
•
Distribution Rights-of-Way (“D ROW”) is being funded with previous Customer Focus Enhanced
Tree Trimming (“ETT”) and Expense funds to support the scheduled distribution ROWs cycle for
side trimming and brush control, including maintenance ETT where ETT specification was
achieved.
•
Emergency is a planned budget to cover blue sky emergency tree contractor call outs to outage and
non-outage tree OMS events. The 2027 proposed budget is an increase over the 2025 actual,
however the proposed budget has remained steady at $2,000,000 for several years. The emergency
program spend is highly weather dependent and the budget must account for busier years.
•
Vines was increased to allow for two years of backbone circuit miles to be treated instead of one
year. The circuit backbones that are not due for mid-cycle or scheduled maintenance will be treated
for vines each year. Through this approach, all backbone miles will be covered for vine treatment
every year.
•
Emergent Work has been increased to support the volume of customer and tree warden inquiries
regarding dead and declining trees and in anticipation of increased tree stress and mortality due to
beech leaf disease and spotted lanternfly.
The Connecticut Light and Power Company
d/b/a Eversource Energy
Docket No. 26-05-10
Set OCC-05
Date Issued August 12, 2026
OCC-377
Page 3 of 4
•
Mid-Cycle is a historic program that is being funded again given the results of the LiDAR analysis.
The LiDAR analysis shows there is encroachment across the system that should be addressed sooner
due to consent limitations and varying tree growth rates. The program will support hot spot trimming
across approximately 1,000 to 1,200 miles of backbone each year.
•
CT DOT Program is moving from Capital to Expense and has increased due to projected increases
in contractor costs.
•
LiDAR is a new remote sensing technology program that will facilitate the annual collection of
ground-based LiDAR collection of the upcoming year’s scheduled maintenance circuits as well as
off-cycle backbone miles for Midcycle and RTW prioritization. This program has been added
following a successful pilot of ground based LiDAR highlighting how this data-driven approach can
improve prioritization of the VMP.
•
Other expenses has been increased to support Energy Saving Trees Arbor Day locations, right-tree,
right-place education, transformer enclosure maintenance, and other smaller programs.
b.
Please refer to Exhibit CLP-VMP-1 at page 44 on lines 16-21. The Company is presenting the total VMP
annual budget that aligns with its workplan. However, a portion of this annual budget will be recovered from
Frontier Communications. Pursuant to the agreement between Eversource and Frontier Communications, the
Company is reimbursed for 15 percent of all vegetation management O&M costs. This reduces the total
annual VMP costs to be recovered from customers in base rates from $89.6 million to approximately $77
million.
c.
The nature of utility vegetation management is to remove and maintain encroaching vegetation within defined
and approved specifications along the electric system to maintain system reliability; however, due to the
natural system in which the VMP operates, and the continual growth of vegetation in CT, the cost of
maintaining the encroachment is incurred annually through the Scheduled Maintenance Trimming (“SMT”)
program. Trees removed through the proposed Risk Tree Removal (“RTR”) and Reliability Tree Work
(“RTW”) programs would no longer need to be maintained in future cycles and would not result in
diminishing returns.
d.
Please refer to Exhibit CLP-VMP-4. The University of Connecticut 2022 Study, A Statistical Framework for
Evaluating the Effectiveness of Vegetation Management in Reducing Power Outages Caused during Storms
in Distribution Networks, demonstrates that, “enhanced vegetation management is particularly helpful in
reducing trouble spots for lower severity storms, with reductions between 45.8% and 63.8%, and substantially
reduces trouble spots during the most severe events when vegetation management is particularly
comprehensive, demonstrating a 37.3% reduction when compared with circuits with little to no enhanced
tree trimming.” (Exhibit CLP-VMP-4, at 15). The reliability improvements indicated were observed in
individual storm events as well as in annual totals. The University of Connecticut 2022 study further
elaborates that, “this analysis provides a better understanding of how more rigorous vegetation management
standards (applying ETT) help reduce outages at an individual event level, for both the more frequent events
and those less frequent, stronger storms, which may also occur more frequently in the future due to climate
change.” (id.).
The Company’s redesigned RTW program will allow the Company to address the locations on scheduled
circuits where overhang and ETT clearances were not previously achieved on the portion of those circuits
The Connecticut Light and Power Company
d/b/a Eversource Energy
Docket No. 26-05-10
Set OCC-05
Date Issued August 12, 2026
OCC-377
Page 4 of 4
that serve the most customers and are highly susceptible to tree-related outages, particularly in relation to
circuit backbones that were addressed through the ETT program over 20 years ago.
Please refer to Exhibit CLP-VMP-2, on page 19, where the Company summarized aspects of the RTW
program. Previous ETT programs between 2004 and 2026 did not allow for previously completed zones to
be readdressed if full clearance was limited by permissions. The RTW program will be key in preventing
vegetation outages from outside zone overhanging limb fall-in and inside zone tree fall-in on high priority
line segments with the goal of achieving clearance of 10 ft of vegetation from ground to sky where permission
allows. By targeting the zones with overhang that serve the highest number of customers through the RTW
program, risk will be mitigated.
As listed on the current system
Question(s) Answered 377 (Connecticut Light and Power Company dba Eversource Energy) Date Filed: 08/28/2026