The Connecticut Light and Power Company
d/b/a Eversource Energy
Docket No. 26-05-10
Set OCC-16
Date Issued September 10, 2026
OCC-634
Page 1 of 3
Date Filed: September 28, 2026
Witness:
Christopher E. Colorio, Mark P. Baldwin, John G. Griffin and Leanne M.
Landry
Request from: Office of Consumer Counsel
Question:
(Storm MN25K - Timesheets) Refer to Exhibit ACCT-2 (CLP-13A-16) (MN25K). The following
pertains to invoices #3634R, 3635R, 3633R, 3648R, 3646R, and 3644R (p. 30-173) and invoices
#3630R, 3643R1, 3639R2, and 3636R1 (208-285):
a. Several timesheets (ex. p. 38) contain missing information within the ‘Work Distribution’
section. Explain how the Company verified and justified the work performed for the hours
stated in box 12 (Work Time) without event information to indicate time worked.
b. Several timesheets (ex. p. 37) contain a difference in hours worked in boxes 6 and 7 (start
time and end time) compared to boxes 24 and 25 (event start time and event end time).
Explain what work occurred during the time differential including the event details, the
event start time, the event end time, and any documentation over the work performed. Cite
to the contract provision contained in the contracts provided in Response to OCC-44
explaining that the tasks noted should be logged as work and not standby.
Response:
a. Reviewing the specified timesheets, there is no significant missing information within the
“Work Distribution” section. The timesheets are not live documents that can be used to
track the crews on a minute-by-minute basis, nor is the timesheet the method by which the
Company manages the crews or assures that the crew is working how and where they are
supposed to be. The timesheets are used to track the time spent on the system primarily
from a work status perspective and are typically filled out after the day’s work is done with
reference to the major work assignments. It is not realistic to expect that the crews will
record every activity that they have engaged in during the day with specificity because this
would detract severely from the job at hand, which is the emergency response and
restoration of power while maintaining paramount attention to the personal safety of these
critical resources.
The Company manages the crews through the oversight of the employee dispatching the
crews and the External Field Resource Coordinator (EFRC), who is physically in the field
with the crews, each assuring that the crews are properly engaged and assigned work to
restore the system from storm damage. The linemen who are filling out the timesheets are
primarily focused on ensuring that their crews are working safely in a dynamic
The Connecticut Light and Power Company
d/b/a Eversource Energy
Docket No. 26-05-10
Set OCC-16
Date Issued September 10, 2026
OCC-634
Page 2 of 3
environment that is full of potentially lethal hazards. The EFRC is the Company
representative that is responsible for signing the timesheets and they have personal
knowledge of the work that the crews have performed and the activities they have engaged
in, particularly in relation to the hours stated in boxes 6 and 7. The Company also verifies
that crews were actively engaged in storm restoration activities through operational
oversight, dispatch records, crew assignments, and direct EFRC field supervision. As a
result, the Company is able to confirm that the hours recorded in Box 12 reflect time during
which the crews were performing restoration-related work or restoration-support activities,
regardless of whether a specific event number was recorded within the Work Distribution
section.
Importantly, the crews are on a working status from the time they are directed to report for
duty until restoration activities are completed and they are released from duty at the end of
the shift. They do not get paid by the specific restoration “event” that they are assigned to
and they will not be actively working an “event” every hour of a work shift. There is time
that must be taken at the start and end of the day and between active restoration “events”
to complete all of the steps necessary to assure safe conditions in the field while they work
the event. These activities include, but are not limited to, receiving work assignments,
conducting safety briefings, performing required vehicle inspections, obtaining and staging
materials, traveling to and between work locations, assessing damage, coordinating
switching activities, establishing safe work zones, and completing job site closeout
activities.
For the Resource Management Teams identifying jobs and deploying crews, and for the
EFRC, the critical focus is to follow procedures, keep the crews safe, and keep them
moving efficiently throughout the working shift. In this context, there is no bright line that
separates one event from another and dissects the day from an “event” perspective. All
activities, whether in preparation for restoration work or actively performing restoration
work, are proper work activities undertaken during the work shift and will not necessarily
be specified on the timesheet. Accordingly, the absence of detailed event information
within portions of the Work Distribution section does not indicate that work was not
performed during those hours.
b. Please refer to subpart (a), above.
Further, all contractor crews and non-Connecticut based Company employees working
storm restoration in Connecticut are required to be lodged in hotel rooms. Prior to
beginning their first job of the day, the crews eat a meal, conduct safety briefings, perform
U.S. Department of Transportation mandated pre-trip inspections on their trucks, and
restock their trucks as necessary with material needed for their day. This takes time and
The Connecticut Light and Power Company
d/b/a Eversource Energy
Docket No. 26-05-10
Set OCC-16
Date Issued September 10, 2026
OCC-634
Page 3 of 3
the crews are methodical because they don’t want to get out into the field without the right
equipment or materials.
The crews may start the work shift by driving from their hotel rooms to the job site and
depending on the availability of hotel rooms, that can add an additional 30 minutes or more.
During this period, the crews remain under Company direction, available for assignment,
and engaged in activities necessary to support restoration operations.
At the end of their last job of the day, the crews are required to clean up their job site,
properly store all equipment and tools, eat a meal after performing physical labor all day
in situations where their personal safety is continually at risk and often in unforgiving
conditions; and drive back to their hotel rooms, which again, could be 30 minutes or more
away from the jobsite. Therefore, intervals of time at the start and end of the work shift
and between restoration “events” are an expected and necessary part of the work shift, for
which the crews are paid. Within a work shift, the crews do not get paid differently for
different types of work. Therefore, from a field perspective, the start and stop time is the
critical datapoint for the timesheet.
Refer to p. 4495 of OCC-044, Attachment 2 CONFIDENTIAL, Exhibit A - Pricing
Schedule. Emergency Response Working Rates for Labor are defined as the agreed labor
rates payable from the commencement of applicable Emergency Response Work through
to termination of such Emergency Response Work, excluding rest time during the
Emergency Response Work. The crews were not in a period of rest or otherwise
unavailable to perform work.
During the periods reflected by the difference between Boxes 6 and 7 and Boxes 24 and
25, crews remained under Company direction and were engaged in activities such as safety
briefings, vehicle inspections, travel to and between assignments, material procurement
and staging, damage assessment, job site cleanup, and other restoration-support functions
necessary to facilitate emergency restoration work.
Accordingly, the Company considers this time to be payable Working Time, consistent
with the contractual definition of Emergency Response Working Rates, rather than standby
time. The event start and end times recorded on the timesheet identify a particular
restoration assignment and do not capture the full range of restoration-support activities
performed during the shift. Because the crews remained in working status from the time
they reported for duty until they were released from duty, the differential is payable as
working time and not standby time.