Interrogatory responses
Answers to questions 936
Filed by Connecticut Light and Power Company dba Eversource Energy1 file
Part of docket 26-05-10Files1
OCC-936_Final.pdf
PDF · 121 KB · 1 pageText searchable
Download OCC-936_Final.pdfRead the text of OCC-936_Final.pdf
The Connecticut Light and Power Company
d/b/a Eversource Energy
Docket No. 26-05-10
Set OCC-26
Date Issued October 05, 2026
OCC-936
Page 1 of 1
Date Filed: October 19, 2026
Witness:
Leanne M. Landry and Jeffrey D. Turano
Request from: Office of Consumer Counsel
Question:
Customer Advances. Refer to the response to OCC-677. Provide the expected in service dates for
each of the five projects and the amount of the advance received for each project.
Response:
While preparing this response it was determined that only four projects with customer advances
were received since December of 2025, totaling $11.6M. In OCC-677 i the Company had
inadvertently stated 5 projects for $14.5M. Please refer to the table below for expected in service
dates, and advance amounts received for each project.
Project
Number
CD02572
CD01591
CD02462
CD02339
Project Description
Amazon Distribution Warehouse Wtbry
Corbin Drive - Darien - New Service
Tilcon NS on Black Rock 11H Sub
CT Transit-26 Elm Ct-New Service
Advance
Amount
($8,136,075)
($584,981)
($2,366,288)
($537,839)
Estimated In
Service Date
12/31/2026
3/30/2027
3/30/2027
3/30/2027
Prior Referenced Response:
i
OCC-677 Question:
Customer Advances. Refer to the response to OCC-270, Attachment 2. Explain the large increase in customer
advances beginning in December 2025 through June 2026 over the prior years balances.
OCC-677 Response:
Since the beginning of December 2025, five new customer requests needing line extensions per the NB-12 policy
were received, totaling $14.5M. These projects are currently in construction.
As listed on the current system