The Connecticut Light and Power Company
d/b/a Eversource Energy
Docket No. 26-05-10
Set EOE-01
Date Issued July 31, 2026
EOE-019
Page 1 of 2
Date Filed: August 14, 2026
Witness:
Donald J. Scacco Jr., Christopher E. Colorio, and Mark P. Baldwin
Request from: Office of Education, Outreach, and Enforcement
Question:
(STORM EVENT TIMING) Provide an unlocked Excel spreadsheet that details the following
information for each storm event included within the Company’s application:
a. Event
b. Storm Start Date
c. Storm End Date
d. Date/time of ERP declaration
e. Date/time of 95% restoration
f. Date/time of 99% restoration
g. Date/time of communicated demobilization
h. Date/time of actual demobilization
i. Date/time of initial external vendor (line crew) billing
j. Date/time of final external vendor (line crew) billing
k. Date/time of initial external vendor (vegetation crew) billing
l. Date/time of final external vendor (vegetation crew) billing
Response:
Please refer to EOE-019, Attachment 1, and EOE-019, Attachment 2. For demobilization, the
Company has provided the earliest communicated demobilization to any vendor and the latest
actual vendor demobilization for each event. For external line and vegetation vendor billing, the
Company has provided the first vendor billing date and the final vendor billing date for the event,
representing the beginning and end of vendor billing activity across all vendors. Please note that
the Company does not utilize or track a metric of 95% restoration. The Company utilizes the
terminology of “substantially complete,” which the Company considers to occur at 99%
restoration.
Regarding subparts (i) and (j), the Company sends detailed hiring emails that indicate exactly what
time external line crew vendors should be ready to work through a detailed hiring mobilization
email. The same process is done when we send an email to the external line crew vendor of when
their restoration has concluded and they are released to start their demobilization back to their
home location. In the EOE-019 Attachment 1, the Company indicates when the first external line
contractor crews were to be ready to work and when the last external line contractor was notified
of their release time. There may be some hours on either end to allow for travel, but since we
know when they were asked to be ready for work and when they were released, we can identify if
The Connecticut Light and Power Company
d/b/a Eversource Energy
Docket No. 26-05-10
Set EOE-01
Date Issued July 31, 2026
EOE-019
Page 2 of 2
the hours charged for travel were within the range expected based the distance they had to mobilize
to and demobilize to when the invoice is reviewed.
Subparts (k) and (l), regarding external vendor (vegetation crew) billing, were compiled via a
manual review of 1,500+ invoices and all vegetation crew invoices may not fall within the
datetimes provided.