Skip to main content

A prototype public docket site for the Connecticut Public Utilities Regulatory Authority

Utility Dockets and Filings

Interrogatory responses

Answers to questions 9, 10

ResponseFiled by The Connecticut Light and Power Company dba Eversource Energy7 files
Part of docket 26-05-10Open
  • Electric
Application of The Connecticut Light and Power Company d/b/a Eversource Energy to Amend its Rate Schedules

Files7

Text of EOE-010 Attachment 2.pdf

Extracted from the file · 65 pages · 201,477 characters

Text of EOE-010 Attachment 3.pdf

Extracted from the file · 70 pages · 208,634 characters

  1. Page 281 of 369

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set EOE-01 Date Issued July 31, 2026 EOE-010 Attachment 4 Page 281 of 369 F. Post- Emergency Event Responsibilities and Reports: G. Equipment Required: • Ensure contractor time sheets are forwarded to appropriate financial personnel • Direct relevant documentation to the Planning Section for disposition • Participate in After Action Review(s) Personal Protective Equipment (PPE): • N/A if in the EOC or other office location Equipment and Supplies: • Phone • Computer Personal: • Appropriate clothing for weather conditions and any personal needs for multiple days away from home H. Position Work Location: Regional EOC or specific reporting area as directed I. Work Period: 8-16 hour work period per day J. Activation Notification: Call Out 1. Applicability: Electric ☒ 2. Primary Documentation: State Emergency Response Plan SUPPLEMENTAL JOB DESCRIPTION INFORMATION EP-ALL-EPJD-OP-20 Gas Rev 1 ☐ Page 2 of 3
  2. Page 282 of 369

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set EOE-01 Date Issued July 31, 2026 EOE-010 Attachment 4 Page 282 of 369 3. Training Requirements: Prerequisites • eLearning: Introduction to Emergency Preparedness at Eversource (EP-303) • eLearning: Introduction to the Incident Command System (EP-304) • eLearning: ARCOS and You (EP-103) • eLearning: Introduction to Business Continuity (EP-201) Initial Training • ARCOS Call Out (EP-102) • ARCOS Siren Notification (EP-101) • Wire Guard & Service Crew Process Training • eLearning: OMS-The Life Cycle of an Outage Event (EP-605) • eLearning: OMS 01-Introduction to OMS (EP-OMS 01) • eLearning: OMS 02-Work Agenda (EP-OMS 02) • eLearning: OMS 03-Sorting and Filtering (EP-OMS 03) • eLearning: OMS 04-Symbology (EP-OMS 04) • eLearning: OMS 05-Viewer (EP-OMS 05) • eLearning: OMS 06-Viewer Maps (EP-OMS 06) • eLearning: OMS 07-Control Tool (EP-OMS 07) • eLearning: OMS 08-Referrals (EP-OMS 08) • eLearning: OMS 09A-Managing Crews (EP-OMS 09A) • eLearning: OMS 9B-Managing Crews (EP-OMS 09B) • eLearning: OMS 10-Trouble Information (EP-OMS 10) • eLearning: OMS 11-Executing Traces (EP-OMS 11) • eLearning: OMS 12-Grouping Events (EP-OMS 12) • eLearning: OMS 13-Damage Assessment (EP-OMS 13) • eLearning: OMS 14-Managing Events (EP-OMS 14) • eLearning: OMS 15-Confirming Outages (EP-OMS 15) • eLearning: OMS 16-Managing Operations (EP-OMS 16) • eLearning: OMS 17-Viewing Summaries (EP-OMS 17) • eLearning: OMS-Completing Events (EP-606) • Initial EP OMS Training (EP-603) Refresher Training • 4. Required System / Drives Access: EP-ALL-EPJD-OP-20 EP OMS Training - Refresher (EP-603R) Eversource N:\ Drive Rev 1 Page 3 of 3
  3. Page 283 of 369

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set EOE-01 Date Issued July 31, 2026 EOE-010 Attachment 4 Page 283 of 369 EP-ALL-EPJD-OP-21 , Rev. 1 All Hazards Emergency Response Program Effective Date: 09/03/2020 Approval Date: 11/09/2016 Service Crew Coordinator EMERGENCY POSITION JOB DESCRIPTION INFORMATION A. Position Title: Service Crew Coordinator B. Reports To: Service Crew Unit Leader 1. Direct Reports: None C. Position Duties and Responsibilities: The Service Crew Coordinator is responsible to assign and dispatch service crews within an assigned area to restore house services. D. Pre-Event Preparations: • Discuss availability with Service Crew Unit Leader • Ensure knowledge and understanding of the Outage Management System (OMS) including the damage assessment and referral processes • Log in to OMS to validate credentials and to ensure technology is up-to-date • Make notifications and activate personnel within branch • Update Service Crew Unit Leader on mobilization activities • Develop and maintain an accurate work plan for house service jobs and ensure changes in arrival, repair, and restoration times made in the field are reflected in the OMS • Record in OMS temporary repairs that require work by customer electricians for repair and municipal inspections before completing the event with follow-up required in the OMS • Ensure damage locations that involve telephone or third party equipment have been documented in OMS and have been effectively communicated to other utilities before closing out the job • Provide periodic updates to the Unit Leader and participate in scheduled situational briefings and calls • Direct relevant documentation to the Planning Section for disposition • Participate in After Action Review(s) E. F. Duties, Responsibilities, and Actions During an Emergency Event: Post- Emergency Event Responsibilities and Reports: Personal Protective Equipment (PPE): G. Equipment Required: • N/A if in AWC Equipment and Supplies: • Phone • Computer Personal: • Appropriate clothing for weather conditions and any personal needs for multiple days away from home H. Position Work Location: Area Work Center or specific reporting location as directed I. Work Period: 8-16 hour work period per day J. Activation Notification: Call Out Ensure you are using the current revision by verifying it against the controlled electronic copy located in the Emergency Response Program Documentation Database.
  4. Page 284 of 369

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set EOE-01 Date Issued July 31, 2026 EOE-010 Attachment 4 Page 284 of 369 SUPPLEMENTAL JOB DESCRIPTION INFORMATION 1. Applicability: Electric ☒ 2. Primary Documentation: State Emergency Response Plan 3. Training Requirements: Gas ☐ Prerequisites • eLearning: Introduction to Emergency Preparedness at Eversource (EP-303) • eLearning: Introduction to the Incident Command System (EP-304) • eLearning: ARCOS and You (EP-103) • eLearning: Introduction to Business Continuity (EP-201) Initial Training • eLearning: OMS Customer Outage Communications (ETRs) (EP-604) • eLearning: OMS-The Life Cycle of an Outage Event (EP-605) • eLearning: OMS 01-Introduction to OMS (EP-OMS 01) • eLearning: OMS 02-Work Agenda (EP-OMS 02) • eLearning: OMS 03-Sorting and Filtering (EP-OMS 03) • eLearning: OMS 04-Symbology (EP-OMS 04) • eLearning: OMS 05-Viewer (EP-OMS 05) • eLearning: OMS 06-Viewer Maps (EP-OMS 06) • eLearning: OMS 07-Control Tool (EP-OMS 07) • eLearning: OMS 08-Referrals (EP-OMS 08) • eLearning: OMS 09A-Managing Crews (EP-OMS 09A) • eLearning: OMS 9B-Managing Crews (EP-OMS 09B) • eLearning: OMS 10-Trouble Information (EP-OMS 10) • eLearning: OMS 11-Executing Traces (EP-OMS 11) • eLearning: OMS 12-Grouping Events (EP-OMS 12) • eLearning: OMS 13-Damage Assessment (EP-OMS 13) • eLearning: OMS 14-Managing Events (EP-OMS 14) • eLearning: OMS 15-Confirming Outages (EP-OMS 15) • eLearning: OMS 16-Managing Operations (EP-OMS 16) • eLearning: OMS 17-Viewing Summaries (EP-OMS 17) • eLearning: OMS-Completing Events (EP-606) • Wire Guard & Service Crew Process Training • Initial EP OMS Training (EP-603) Refresher Training • 4. Required System / Drives Access: EP-ALL-EPJD-OP-21 EP OMS Training - Refresher (EP-603R) Eversource N:\ Drive Rev 1 Page 2 of 2
  5. Page 285 of 369

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set EOE-01 Date Issued July 31, 2026 EOE-010 Attachment 4 Page 285 of 369 EP-ALL-EPJD-OP-22 , Rev. 0 All Hazards Emergency Response Program Effective Date: 10/13/2016 Approval Date: 10/13/2016 Service Crew Supervisor EMERGENCY POSITION JOB DESCRIPTION INFORMATION A. Position Title: Service Crew Supervisor B. Reports To: Service Crew Unit Leader 1. Direct Reports: Service Crew C. Position Duties and Responsibilities: The Service Crew Supervisor is responsible for supervising the service crews that perform restoration of pole-to-house services in a geographical area. D. Pre-Event Preparations: • Ensure all required PPE is in order • Fully charge all portable devices • Assess availability, activate, and deploy unit personnel as directed • Ensure technology and equipment at assigned work locations is tested and operational • Understand the provisions of Union Agreements as they are interpreted under emergency operations • Ensure house service kits are distributed as necessary to field personnel. Confirm materials and have restocked as necessary • Ensure pre-job safety briefings are being conducted • Take action to prevent/stop unsafe acts • Execute work plan for house service jobs; ensure changes in arrival, repair, and restoration times are reflected in the OMS • Ensure service crews make every effort to notify customers as appropriate regarding followup work or leave a door hanger indicating such • Ensure temporary repairs that require follow-up work by customer electricians for repair and municipal inspections are communicated and documented in OMS before closing the job • Ensure damage locations that involve telephone or third party equipment have been documented in OMS • Provide periodic updates to the Service Crew Unit Leader • Ensure contractor time sheets are forwarded to appropriate financial personnel • Direct relevant documentation to the Planning Section for disposition • Participate in After Action Review(s) E. F. Duties, Responsibilities, and Actions During an Emergency Event: Post- Emergency Event Responsibilities and Reports: G. Equipment Required: Personal Protective Equipment (PPE): • Reflective vest, safety shoes, hard hat Equipment and Supplies: • Phone • Computer Personal: • Appropriate clothing for weather conditions and any personal needs for multiple days away from home Ensure you are using the current revision by verifying it against the controlled electronic copy located in the Emergency Response Program Documentation Database.
  6. Page 286 of 369

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set EOE-01 Date Issued July 31, 2026 EOE-010 Attachment 4 Page 286 of 369 H. Position Work Location: Assigned Field Location I. Work Period: 8-16 hour work period per day J. Activation Notification: Call Out 1. Applicability: Electric ☒ 2. Primary Documentation: State Emergency Response Plan 3. Training Requirements: SUPPLEMENTAL JOB DESCRIPTION INFORMATION Gas ☐ Prerequisites • eLearning: Introduction to Emergency Preparedness at Eversource (EP-303) • eLearning: Introduction to the Incident Command System (EP-304) • eLearning: ARCOS and You (EP-103) • eLearning: Introduction to Business Continuity (EP-201) Initial Training • Wire Guard & Services Crew Process Training Refresher Training • 4. Required System / Drives Access: EP-ALL-EPJD-OP-22 Eversource N:\ Drive Rev 0 Page 2 of 2
  7. Page 287 of 369

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set EOE-01 Date Issued July 31, 2026 EOE-010 Attachment 4 Page 287 of 369 EP-ALL-EPJD-OP-31 , Rev. 0 All Hazards Emergency Response Program Effective Date: 7/8/2016 Approval Date: 7/8/2016 Transmission Branch Director EMERGENCY POSITION JOB DESCRIPTION INFORMATION A. Position Title: Transmission Branch Director (CT and MA position only) B. Reports To: Operations Section Chief 1. Direct Reports: • Field Group Manager • Dispatch Group Manager C. Position Duties and Responsibilities: The Transmission Branch Director coordinates and manages the damage assessment and restoration activities associated with the Transmission System during an emergency event. The Transmission Branch manages field restoration personnel including coordination and communication with the System Operator and the Operations Branch Directors. D. Pre-Event Preparations: • Ensure the staffing rosters for the Transmission Branch positions are up-to-date and ready to be used • Support the Operations Section Chief in conducting the annual Section Meeting with all appropriate personnel to ensure they are prepared and trained to carry out their Emergency Positions • Following activation of the IMT, activate any required Transmission Branch personnel, develop staffing schedule, and provide initial staffing plans to Operations Section Chief and the Planning Section • Conduct an initial briefing and routine update meetings and briefings with Transmission Branch personnel • Ensure the Transmission Branch staff has a dedicated area to set up in the ICC/EOC or nearby location and has all of the necessary equipment, supplies, and support • Inform the Operations Section Chief of any Transmission Branch resource requirements • Ensure the provisions of Eversource union agreements are observed • Collaborate with the Vegetation Management Unit Leader and gather contact information required for tree crew coordination and assistance • Verify and arrange for helicopter availability • Notify the Operations Section Chief when the Branch is operational Ensure you are using the current revision by verifying it against the controlled electronic copy located in the Emergency Response Program Documentation Database.
  8. Page 288 of 369

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set EOE-01 Date Issued July 31, 2026 EOE-010 Attachment 4 Page 288 of 369 E. F. Duties, Responsibilities, and Actions During an Emergency Event: Post- Emergency Event Responsibilities and Reports: G. Equipment Required: • Ensure safety of tactical operations and exercise emergency authority to stop and prevent unsafe acts • Ensure the necessary actions are implemented to achieve the IAP goals • Inform the Operations Section Chief if additional Transmission Branch resources are required and coordinate with Logistics Resource Acquisition • Develop a preliminary assessment of Transmission circuits and lines that are impacted • Develop damage assessment strategy and priority and collaborate with the Planning Section to assign DA Patrol Team (using helicopter and foot patrols as necessary) are assigned to patrol the required areas • Coordinate with the applicable Dispatch Authority to perform the necessary switching and tagging • Ensure the appropriate and effective distribution of transmission restoration crews among the damage locations based on priorities and IAP restoration objectives • Provide continual assessment of restoration progress and allocate resources as necessary • Ensure that the positions within the Transmission Branch execute their specific duties and responsibilities • Support the development of a Demobilization Plan to return to normal business operations • Direct relevant documentation to the Planning Section for disposition. • Ensure outside contractor time sheets are forwarded to appropriate financial personnel. • Participate in After Action Review(s) Personal Protective Equipment (PPE): • N/A if in the ICC Equipment and Supplies: • Phone • Computer Personal: • Appropriate clothing for weather conditions and any personal needs for multiple days away from home H. Position Work Location: Incident Command Center I. Work Period: 8-16 hour work period per day J. Activation Notification: Call Out 1. Applicability: Electric ☒ 2. Primary Documentation: State Emergency Response Plan SUPPLEMENTAL JOB DESCRIPTION INFORMATION EP-ALL-EPJD-OP-31 Gas Rev 0 ☐ Page 2 of 3
  9. Page 289 of 369

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set EOE-01 Date Issued July 31, 2026 EOE-010 Attachment 4 Page 289 of 369 3. Training Requirements: Prerequisites • eLearning: Introduction to Emergency Preparedness at Eversource (EP-303) • eLearning: Introduction to the Incident Command System (EP-304) • eLearning: ARCOS and You (EP-103) • eLearning: Introduction to Business Continuity (EP-201) Initial Training • Refresher Training • 4. Required System / Drives Access: EP-ALL-EPJD-OP-31 Eversource N:\ Drive Rev 0 Page 3 of 3
  10. Page 290 of 369

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set EOE-01 Date Issued July 31, 2026 EOE-010 Attachment 4 Page 290 of 369 All Hazards Emergency Response Program Effective Date: 7/8/2016 EP-ALL-EPJD-OP-32 , Rev. 0 Approval Date: 7/8/2016 Field Group Manager (CT & MA) EMERGENCY POSITION JOB DESCRIPTION INFORMATION A. Position Title: Field Group Manager (CT & MA) B. Reports To: Transmission Branch Director 1. Direct Reports: Field Supervisors C. Position Duties and Responsibilities: The Field Group Manager coordinates and manages Damage Assessment (DA) and field activities associated with repairs to the transmission system. D. Pre-Event Preparations: • Ensure adequate field personnel are available for the expected duration of the event • Following activation of the IMT, activate any required Field Group personnel, develop a staffing schedule, and provide initial staffing plans to the Operations Section Chief and the Logistics Section • Conduct an initial briefing and routine update meetings and briefings with Field Group personnel • Ensure the provisions of Eversource union agreements are observed • Ensure all of the Field Group equipment is ready for use and operational (that is, bucket trucks, lifts, off road vehicles, test equipment, cranes, and other rental equipment) • Collaborate with the Vegetation Management Unit Leader and gather contact information required for tree crew coordination and assistance • Verify with the Logistics Services Branch Director, as needed, that there are an adequate number of vehicles (including possible rentals), whether vehicle wheel chains are necessary, if there is an adequate stock of poles, cross arms, and conductor, and so on, and that the stock is reasonably distributed • Ensure safety of tactical operations and exercise emergency authority to stop and prevent unsafe acts • Oversee repairs and restoration of transmission lines and equipment consistent with the work plan • Inform the Transmission Branch Director if additional resources are required • Coordinate with the applicable Dispatch Authority to perform the necessary switching and tagging and requirements • Ensure the appropriate and effective distribution of the Transmission restoration crews among the damage locations based on the estimated time to restore each line • Provide continual assessment of restoration progress and allocate resources as necessary • Direct relevant documentation to the Planning Section for disposition • Participate in After Action Review(s) • Ensure outside contractor time sheets are forwarded to appropriate financial personnel E. F. Duties, Responsibilities, and Actions During an Emergency Event: Post- Emergency Event Responsibilities and Reports: Ensure you are using the current revision by verifying it against the controlled electronic copy located in the Emergency Response Program Documentation Database.

Text of EOE-010 Attachment 5.pdf

Extracted from the file · 108 pages · 301,258 characters

As listed on the current system

Question(s) Answered 9, 10 (The Connecticut Light and Power Company dba Eversource Energy) Date Filed: 08/14/2026

This filing on the current system (opens in a new tab)