Interrogatory responses

Answers to questions 30, 33, 36, 37, 40

ResponseFiled by Connecticut Light and Power Company dba Eversource Energy13 files
Part of docket 26-05-10Open
  • Electric
Application of The Connecticut Light and Power Company d/b/a Eversource Energy to Amend its Rate Schedules

Files13

Text of EOE-033_final.pdf

Extracted from the file · 2 pages · 2,411 characters

Text of EOE-036 Attachment 1.pdf

Extracted from the file · 5 pages · 10,251 characters

Text of EOE-036_final.pdf

Extracted from the file · 1 page · 605 characters

Text of EOE-037_final.pdf

Extracted from the file · 1 page · 1,678 characters

Text of EOE-037 Attachment 1.pdf

Extracted from the file · 1 page · 1,360 characters

Text of EOE-037 Attachment 1.xlsx

Sheet names, column headings and text cells; numbers left out

Text of EOE-040_final.pdf

Extracted from the file · 1 page · 1,218 characters

  1. Page 89 of 108

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set EOE-01 Date Issued July 31, 2026 EOE-040 Attachment 1 Page 89 of 108 Emergency Response Plan Electric System Operations - CT Attachment 1 – Incident Command System (Sheet 1 of 2) Incident Command System (ICS) Features and Principles 1. Structure The ERP employs ICS as the basis for the IMT. Trained personnel are assigned the roles and responsibility for key functions within the ICS structure to manage a wide range of incidents from a simple utility outage to a major disaster, such as a hurricane or blizzard. Regardless of the scale of the incident, the number of personnel and resources marshaled for the response, or the number of departments or organizations involved, utilization of ICS structure ensures that Eversource is positioned for an effective response with the safe, efficient use of resources. 2. Span of Control One of the central principles of ICS is span of control. Span of control refers to the number of direct subordinates that any one supervisor has during an incident. Realizing that each subordinate represents a separate task or process and that a supervisor can only effectively manage a given amount of work, ICS defines a reasonable span of control ranging from 3-7 direct reports, therefore, each supervisor should have no more than seven direct subordinates in the ICS structure. 3. Chain of Command and Unity of Command Chain of command is reflected in an orderly line of authority within the ranks of the ICS structure. Unity of command signifies that every individual in the ICS structure has a designated supervisor to whom he or she reports for the duration of the incident. 4. Scalability An ICS structure is scalable to an event of any size assuming that there are sufficient personnel trained and qualified to fill the critical job positions in the command structure. It is the responsibility of each layer of management within the structure to ensure the span of control is appropriate and determine whether additional functions or resources are needed. 5. Decision Making ICS pushes decision making down to the lowest level possible by ensuring that the incident is managed by objectives and the staff in the command structure are qualified to make the decisions outlined within the Plan that they have been given the authority to make. One aspect of ICS that is important when interacting with other utilities and non-utility stakeholders is the use of plain language or common nomenclature. Title conventions for Eversource’s ICS positions are shown below in Table 4 and the hierarchy is shown in Table 5. Table 4 - Eversource ICS Terminology ICS Staff/Section Incident Commander Command Staff General Staff Operations Section Planning Section Logistics Section EP-CT-ELEC-PLN-2000 Organization Incident Commander All Teams All Branch Group Strike Team or Task Force Field Crew (District) Branch Unit Damage Assessment Patrollers** Team Branch Unit Team 89 of 108 Title Incident Commander Officer Coordinator *** Chief Director Manager* Leader Supervisor* Director Leader Coordinator* Coordinator Director Leader Coordinator Support Deputy Assistant Deputy Deputy Assistant Deputy Deputy Rev 5
  2. Page 90 of 108

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set EOE-01 Date Issued July 31, 2026 EOE-040 Attachment 1 Page 90 of 108 Emergency Response Plan Electric System Operations - CT Attachment 1 – Incident Command System (Sheet 2 of 2) Table 5 - ICS Hierarchy Title Organization Reports To Support Incident Commander Incident Commander N/A Deputy Officer Command Staff Commander Assistant Chief General Staff Commander Deputy Director Branch Chief Deputy Manager * Operations Director/Chief Assistant Leader (EOC) Unit Director/Chief Leader (District) Unit Director Leader (District) Strike Team, Task Force Manager * Supervisor (Operations) * Field Crew Manager * Supervisor (Planning) ** Damage Assessment Leader Coordinator *** “Team” Leader/(Officer) Eversource Customizations: * Manager or Leader normally reports to Supervisor ** Planning normally does not have field personnel *** A Coordinator reports to an Officer if not qualified as an Assistant Officer EP-CT-ELEC-PLN-2000 90 of 108 Rev 5
  3. Page 91 of 108

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set EOE-01 Date Issued July 31, 2026 EOE-040 Attachment 1 Page 91 of 108 Emergency Response Plan Electric System Operations - CT Attachment 2 – Crosswalk Table of PURA Requirements (Sheet 1 of 12) 2012 Recommendations Order # Performance Standard CT ERP Section Page PURA Docket No. 12-06-09 Davies, Witt 1, 2.a.ii & vi Event Classification: Event Level Matrix (ELM) 1.2, 2.4.1, 2.8, 3.1, 0, 10.2, Table 1 Table 2 9, 16, 23, 34, 75, 86, 17, 19 PURA Docket No. 12-06-09 Witt 3.6 During an Emergency Event this includes, at a minimum, implementing all applicable components of the ERP related to restoration of service. 1.2 9 2.a.i The ERP for each EDC should incorporate the structure and process of the National Incident Management System (NIMS) and utilize the Incident Command System (ICS) to permit decentralization and re-centralization of command and control throughout an Emergency Event in order to provide optimum and efficient response and utilization of resources. 1.4, 2.2 11, 13 CL&P should review the existing procedures concerning restoration strategies to confirm alignment and consistency. Additionally, CL&P should provide input into tasks and objectives in order to ensure that future exercises incorporate multiple strategies within an operating area. 2.4 15 1. Each EDC shall conduct an exercise using the procedures set forth in the utility's ERP. If the EDC uses the plan during such 12 month period in responding to an Emergency Event, the utility must then complete an exercise within 18 months;2. Each EDC shall annually evaluate its response to an exercise or major outage. The evaluation shall be provided to the PURA within 60 days after the exercise or event. 2.10.4, 8.2 26, 84 PURA Docket PURA Docket No. 12-06-09 Witt Davies PURA Docket No. 12-06-09 EP-CT-ELEC-PLN-2000 2.c.i.1 91 of 108 Rev 5
  4. Page 92 of 108

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set EOE-01 Date Issued July 31, 2026 EOE-040 Attachment 1 Page 92 of 108 Emergency Response Plan Electric System Operations - CT Attachment 2 – Crosswalk Table of PURA Requirements (Sheet 2 of 12) PURA Docket PURA Docket No. 12-06-09 PURA Docket No. 12-06-09 PURA Docket No. 12-06-09 EP-CT-ELEC-PLN-2000 2012 Order # Recommendations Performance Standard CT ERP Section Page 2.a.iv The ERP shall include guidelines for setting priorities for service restoration. In general, the EDC shall set priorities such that service is restored first to critical customers, and second such that the largest number of customers can receive service in the shortest amount of time. This provision does not prohibit an EDC from simultaneously restoring critical customers, the largest number of blocks of customers, and performing other restoration activities as described in its ERP. 2.11.1 28 2.a.iv Each EDC shall abide by the guidelines and priorities for service restoration contained in its ERP. In general, the utility shall set priorities so that service is restored first to critical customers, and second so that the largest number of customers can receive service in the shortest amount of time, but this provision does not prohibit a utility from simultaneously restoring critical customers, the largest number or blocks of customers, and performing other restoration activities described in its ERP. 2.11.1 28 2.a.vi The ERP must also specify mutual assistance protocols and prioritization. These could include: utilization of holding company resources, contract crew reservations, local utility assistance, and organizations the EDC belongs to and participates in, such as the North East Mutual Assistance Group (NEMAG), Edison Electric Institute (EEI) Restore Power, and others as appropriate. 2.11.4 31 92 of 108 Rev 5
  5. Page 93 of 108

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set EOE-01 Date Issued July 31, 2026 EOE-040 Attachment 1 Page 93 of 108 Emergency Response Plan Electric System Operations - CT Attachment 2 – Crosswalk Table of PURA Requirements (Sheet 3 of 12) PURA Docket PURA Docket No. 12-06-09 PURA Docket No. 12-06-09 PURA Docket No. 12-06-09 EP-CT-ELEC-PLN-2000 2012 Order # Recommendations Performance Standard CT ERP Section Page Davies, Witt 2.a.vi The ERP must be designed to provide for mutual assistance parameters that describe how the EDC intends to employ resources available pursuant to mutual assistance agreements for emergency response. Mutual assistance shall be requested when the EDC reasonably believes that local resources are inadequate to assure timely restoration of service or public safety, or if mutual assistance would substantially improve restoration times or mitigate safety hazards. The ERP should include a storm matrix for various storm levels that identify the necessary mutual aid and/or contractor resources necessary to restore customers within a prescribed time period range. Additionally, the matrix should identify different types of storms and establish resource requirements specific to those types of Emergency Events. 2.11.4 31 2.a.vi The ERP must stipulate at what level of outage or anticipated outage level the EDC will request mutual assistance, taking into account travel times from remote resources, so as to ensure sufficient resources to rapidly and efficiently provide restoration. 2.11.4a 31 2.a.iii The ERP shall describe the process for assessing damage and, where appropriate, the use of contingency resources required to expedite a response to the emergency. The ERP should also specify the mode(s) of delivery of damage assessments. 3.4.4 46 Davies, Witt 93 of 108 Rev 5
  6. Page 94 of 108

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set EOE-01 Date Issued July 31, 2026 EOE-040 Attachment 1 Page 94 of 108 Emergency Response Plan Electric System Operations - CT Attachment 2 – Crosswalk Table of PURA Requirements (Sheet 4 of 12) PURA Docket PURA Docket No. 12-06-09 PURA Docket No. 12-06-09 PURA Docket No. 12-06-09 EP-CT-ELEC-PLN-2000 2012 Recommendations Order # Davies Witt Performance Standard CT ERP Section 2.a.vi The ERP shall recognize the need to communicate mutual assistance activities with specified state and local agencies. 3.10.2c, 3.11.2c 71, 74 3 Each EDC shall train designated personnel each calendar year in preparation for events. The training shall be designed to overcome problems identified in the evaluations of responses to an event or exercise and shall reflect any relevant changes to the EDC's plan; 8.2 84 2.c.i.4 Each EDC shall provide no less than ten days prior notice of its annual exercise to the PURA, the Department of Emergency Services and Public Protection, the chief elected official of each municipality in its service territory and any state-established emergency office(s) for the region(s) in which the exercise is to be performed, and to appropriate local authorities. 8.2 84 94 of 108 Page Rev 5
  7. Page 95 of 108

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set EOE-01 Date Issued July 31, 2026 EOE-040 Attachment 1 Page 95 of 108 Emergency Response Plan Electric System Operations - CT Attachment 2 – Crosswalk Table of PURA Requirements (Sheet 5 of 12) PURA Docket PURA Docket No. 12-06-09 EP-CT-ELEC-PLN-2000 2012 Order # Recommendations Performance Standard CT ERP Section Page Witt, Two Storm Every three calendar years, each EDC shall conduct or participate in a comprehensive emergency exercise to test and evaluate major components of its plan and shall invite a crosssection of the following, or their representatives, located within the EDC's service territory, to the exercise: • Chief elected official and other elected officials; • County/regional emergency management directors; • Fire and police departments; • Community organizations such as the American Red Cross, which have participated in prior such exercises or which the EDC reasonably concludes should participate in such exercises; and • the PURA. 2. Each EDC shall participate in each statewide emergency preparedness drill conducted by the state in which the state extended an invitation for participation to the EDC; 3. The large-scale exercises that are held every three years should consider the highest level event covered in the ERP, for example, a Level 4 event, with up to 70% of its customers suffering an extended outage; and 4. Provide after-action and lessons-learned reports to the EDC's participants and any other participants whom the EDC recommends should modify or improve their performance, and file these with PURA within 60 days following each exercise. 8.2 84 2.c.ii.1 95 of 108 Rev 5
  8. Page 96 of 108

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set EOE-01 Date Issued July 31, 2026 EOE-040 Attachment 1 Page 96 of 108 Emergency Response Plan Electric System Operations - CT Attachment 2 Crosswalk Table of PURA Requirements (Sheet 6 of 12) PURA Docket 2012 Order # Recommendations Performance Standard CT ERP Section Page 8.2 84 PURA Docket No. 12-06-09 2.c.i.5 5. The EDC shall participate in other emergency exercises, which are conducted by the state or any state-established emergency office for one or more regions in the EDC's service territory, that is designed to address problems on electric distribution facilities or services and to which the utility has been invited to participate. PURA Docket No. 12-06-09 2 Each EDC will also file the ERP in full when there have been any material changes in the ERP. 9.2 85 2 Submit ERP to the PURA for reviews of emergency plans every two years, on or before July 1st, pursuant to the General Statutes of Connecticut (Conn. Gen. Stat.) §16-32e. 10.2 86 2.a.vi Each EDC shall annually notify the PURA by July 1st of the mutual aid groups to which it belongs and whether there have been changes in the membership of those groups or material changes in the rules of those groups within the previous 12 months. 10.2 86 PURA Docket No. 12-06-09 PURA Docket No. 12-06-09 EP-CT-ELEC-PLN-2000 96 of 108 Rev 5
  9. Page 97 of 108

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set EOE-01 Date Issued July 31, 2026 EOE-040 Attachment 1 Page 97 of 108 Emergency Response Plan Electric System Operations - CT Attachment 2 Crosswalk Table of PURA Requirements (Sheet 7 of 12) PURA Docket 2012 Rec Order # PURA Docket No. 20-08-03 N/A 1 PURA Docket No. 20-08-03 N/A 2 EP-CT-ELEC-PLN-2000 Performance Standard No later than June 30, 2021, Eversource and UI shall separately submit for the Authority’s review, modification, and approval updated ERPs incorporating all of the changes discussed herein. In this filing, the EDCs shall provide two sets of ERPs: a version with redline edits and a clean version. Such changes shall include the modifications to the ERP Event Level Classification Matrix outlined in Section IV.D.8. The updated matrix shall include the number of total, internal, and external resources to be available at the onset of the storm, as well as the peak number of crews expected during the storm restoration process for each event level for the following categories of resources by number of crews and full time equivalent staff: a. Line Crews; b. Service Crews; c. Damage Assessors; d. Tree/Line Clearance/ Vegetation Mgt Crews; e. Liaisons; and f. Large customer account representatives (See, Section IV.G.1.). The EDCs shall also develop a process for identifying and tracking life support customers, which are customers that require electrical service for life-maintaining conditions. The EDCs shall incorporate into their respective ERPs filed for the Authority’s review, modification, and approval on or before June 30, 2021, a formal process to contact life support customers before, during, and after storm events. Specifically, the formal process must include steps to: contact all life support customers more than 24 hours before the onset of a major storm; track the status of electric service to life support customers; regularly update each municipality served by the EDC of the life support customers without power in their town; and provide daily communications to life support customers without power during the storm restoration process 97 of 108 CT ERP Section Page 2, Table 1 Table 2 12, 17, 19 3.10 69 Rev 5
  10. Page 98 of 108

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Set EOE-01 Date Issued July 31, 2026 EOE-040 Attachment 1 Page 98 of 108 Emergency Response Plan Electric System Operations - CT Attachment 2 Crosswalk Table of PURA Requirements (Sheet 8 of 12) PURA Docket 2012 Rec Order Performance Standard # PURA Docket No. 20-08-03 N/A 3 PURA Docket No. 20-08-03 N/A 4 EP-CT-ELEC-PLN-2000 No later than June 30, 2021, Eversource and UI shall separately perform and submit to the Authority a study to determine the number of damage assessors needed to assist in the identification of Make Safe locations and restoration duties within the first 48 hours of storm onset for each of the event levels in its Event Level Matrix. Based on the findings of the study, UI and Eversource shall include in their respective updated ERPs the range of damage assessors likely needed in the event level classification, as directed in Order No. 1. Until further notice, the Authority directs Eversource and UI to include in their storm preparedness resource acquisition activities the ability to acquire enough line resources and liaisons sufficient to dedicate one of each to any potentially affected municipality in its territory who requests such. This requirement shall apply to any Event Level 4 or higher. a. In the case of Make Safe liaisons, Eversource and UI shall provide a Make Safe liaison that is in addition to the town liaison and will be dedicated solely during response to coordinate blocked roads with the towns until all Make Safe roads are cleared or until such a time as the EDC and town has conferred and determined that the town no longer needs a dedicated Make Safe liaison. b. In the case of line resources, Eversource and UI shall have on hand line resources in advance of an event sufficient to provide one lineworker crew for each towns that request one. UI shall continue to provide a dedicated line 98 of 108 CT ERP Section Page 3.2, 3.6, Table 1 Table 2 34, 53, 17, 19 3.2, 3.6, Table 1 Table 2 34, 53, 17, 19 Rev 5

Text of EOE-040 Attachment 2.pdf

Extracted from the file · 108 pages · 299,821 characters

Text of EOE-040 Attachment 3.pdf

Extracted from the file · 328 pages · 663,868 characters

As listed on the current system

Question(s) Answered 30, 33, 36, 37, 40 (Connecticut Light and Power Company dba Eversource Energy) Date Filed: 08/14/2026