Question:
(MS24F-VENDOR-LINE) Refer to Exhibit ACCT-2 CLP-6, and Confidential Exhibit ACCT-2
CLP-6A-4, pp. 88-107. The Company reported six incremental charges in the combined amount
of $1,121,268 for the Conexus Energy Group LLC vendor. The Company provided invoices for
five of the six charges but failed to provide signed Eversource Contractor Storm Daily Time &
Work Reports or Eversource Contractor Storm Mobilization & Demobilization Time reports
(collectively timesheets). Respond to the following:
a. Provide the omitted signed timesheets for the charges included in Rows 154-158. If the
documents cannot be provided, explain how the Company validated the accuracy of the
billed activity.
b. Referring to pp. 98-99 (i.e., supporting Row 159), explain why the vendor was permitted
to bill for lodging when they were mobilized out of Beacon Falls, CT. As part of the
response, identify if the lodging expense was due to contractual obligations and specify if
the vendor was lodged at a hotel. If lodged at a hotel, identify the location.
c. Referring to pp. 100-102, explain why the vendor was permitted to bill for 2 hours of travel
time between Beacon Falls, CT and Milford, CT, a distance of approximately 20 miles.
d. Referring to pp. 103-107, the timesheets provided identify the first assignment dispatch
time of 8:34, approximately 2.5 hours after the vendor’s start time (i.e., box 6). Explain
why the vendor did not record activity as standby until the initial assignment. As part of
response, please identify the incremental impact of the vendor’s billing of equipment for
2.5 hours.
Response:
Referring to Exhibit ACCT-2 CLP-6, Outside Contractors- Vendors, Lines 154-159, vendor
Conexus Energy Group LLC, invoices totaling the amount of $1,121,268.
a. Please refer to the following attachments for timesheets supporting charges for lines 154158:
• EOE-286, Attachment 1, for timesheets for invoice 24153, line 154.
• EOE-286, Attachment 2, for timesheets for invoice 24153, line 155.
The Connecticut Light and Power Company
d/b/a Eversource Energy
Docket No. 26-05-10
Set EOE-06
Date Issued September 22, 2026
EOE-286
Page 2 of 2
•
•
•
EOE-286, Attachment 3, for timesheets for invoice 240155, line 156.
EOE-286, Attachment 4, for timesheets for invoice 240152, line 157.
EOE-286, Attachment 5, for timesheets for invoice 240151, line 158.
b. As documented in EOE-286, Attachment 6, crews were mobilized from Connecticut, New
Jersey, and Massachusetts and directed by Eversource to arrive by 2200 hours on April 3
and self-lodge in preparation for a 06:00 start time. Beacon Falls, CT is the contractor’s
laydown yard, not the crews’ originating locations. The contractor self-lodged in Milford,
CT, as reflected on the timesheet (box 16, Ending Location). Lodging was necessary to
ensure resources were positioned and available for restoration activities and billed at the
agreed-upon $85 per-person per diem rate.
c. The two hours of reported travel should not be interpreted solely as travel between Beacon
Falls and Milford, CT. As documented in Confidential EOE-286, Attachment 6, crews
were mobilized from locations throughout Connecticut, New Jersey, and Massachusetts.
Although initially secured to support Massachusetts, Eversource redirected these resources
to Connecticut prior to mobilization due to greater storm impacts. The reported travel time
reflects mobilization related travel associated with positioning these resources, while
Milford, CT represents the lodging location recorded at the conclusion of the workday.
d. The contractor’s 06:00 start time reflects when crews were activated and required to be
prepared and available for restoration activities. Although the initial field assignment was
dispatched at 08:34, the crews were not on standby as defined under the applicable contract.
During this period, crews were actively engaged in restoration preparation, including
equipment and material readiness, safety coordination, and deployment related activities.
The absence of an immediate field assignment does not constitute standby when crews are
performing compensable restoration related activities. Accordingly, the working rate was
applicable to both labor and equipment, and there was no incremental equipment
overbilling associated with the approximately 2.5-hour period.