Interrogatory responses

Answers to questions 379, 380, 381, 382, 383

ResponseFiled by Connecticut Light and Power Company dba Eversource Energy11 files
Part of docket 26-05-10Open
  • Electric
Application of The Connecticut Light and Power Company d/b/a Eversource Energy to Amend its Rate Schedules

Files11

Search terms highlighted
Eversource rate increase is on 18 pages across 3 files of the text below, highlighted. Go to the first matchClear highlighting
Words on different pages
Words on different pages
Words on different pages

Text of EOE-381_Final.pdf

Extracted from the file · 2 pages · 3,490 characters

Words on different pagesRead the text of EOE-381_Final.pdf

Text of EOE-382_Final.pdf

Extracted from the file · 1 page · 2,648 characters

Words on different pagesRead the text of EOE-382_Final.pdf

Text of EOE-383_Final.pdf

Extracted from the file · 4 pages · 10,383 characters

Words on different pagesRead the text of EOE-383_Final.pdf
6 pages match
  1. Page 107 of 125

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 13, 2026 EOE-383 Attachment 1 Page 107 of 125 Docket No. 11-09-09 Page 103 Video service was restored to the Certificate Holders’ separate service areas between September 2, 2011 for AT&T, to September 8, 2011, for all Comcast service areas. AT&T and Comcast Responses to Question No. 5, Tropical Storm Irene Letter. MetroCast stated that the video service in the vast majority of its service area had been restored by September 5, 2011, while Charter indicated that service had been restored by September 6, 2011, but much of its two areas had video service restored well before that date. MetroCast and Charter Responses to Question No. 5, Tropical Storm Irene Letter. The Certificate Holders stated that credits or refunds would be provided if subscribers notified them that they had experienced qualifying outages. Certificate Holders Responses to Question No. 6, Tropical Storm Irene Letter. As was the case with Tropical Storm Irene, the number of subscribers who experienced qualifying outages as a result of the October Storm varied significantly by Certificate Holder, with Verizon indicating that only three subscribers experienced qualifying outages, and for Comcast 156,140. Verizon and Comcast Responses to Question No. 1, November 17, 2012 Authority Letter (October Storm Letter). Cox again indicated that it could not estimate the number of subscribers that experienced such service interruptions. The average duration of the length of qualifying outages also varied widely. For example, Charter stated that the average duration of qualifying outages in its two service areas ranged from “very limited” to “almost a week,” and Verizon indicated that the average duration was 69 hours. Charter and Verizon Responses to Question No. 2, October Storm Letter. Cox stated that it was unable to calculate the average duration, but that most downed drops were repaired within 24 hours and all were repaired within 36 hours of being notified by a subscriber of a video service problem. Cox Response to Question No. 2, October Storm Letter. The number of subscribers who experienced lengthy video outages determined, in part, the amount refunded by each Certificate Holder. Because the damage from the October Storm was least severe in the eastern part of the State, MetroCast provided $137.10 in credits and refunds, while Cox and Comcast provided $1,127,000 and $1,300,000 in credits and refunds, respectively, with Cox stating the amount refunded included credits and refunds for services other than video, such as its phone and Internet products. Cox and Comcast Responses to Question No. 3, October Storm Letter. As was the case with Irene-related credits and refunds, October Storm-related credits and refunds were normally issued in the billing cycle following a report by a subscriber that a qualifying outage had been experienced. Certificate Holders’ Responses to Question No. 4, October Storm Letter. MetroCast and TVC stated that they did not lose power for an extended period of time as a result of damage caused by the October Storm. MetroCast Response to Question 5, October Storm Letter; TVC Response to Interrogatory CA-14. The latest that video service in a separate service area was completely restored was November 15, 2011. Comcast and Charter Responses to Question No. 5, October Storm Letter. As was the case with Irene-related credits and refunds, the Certificate Holders stated that, for subscribers to be provided refunds and credits for having experienced qualifying outages, they had to notify their certificated video provider. Certificate Holders’ Responses to Question No. 6, October Storm Letter.
  2. Page 108 of 125

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 13, 2026 EOE-383 Attachment 1 Page 108 of 125 Docket No. 11-09-09 Page 104 The Authority notes that making direct comparisons among the Certificate Holders to their responses to the Tropical Storm Irene Letter and October Storm Letter is difficult for the following reasons. First, the number of subscribers served by different Certificate Holders varies widely. For example, Verizon provides video service to Greenwich only, while AT&T’s service area is statewide and Comcast provides video service in 84 municipalities. Second, individual service areas vary with respect to topography and the amount of video-related plant and facilities affected by the two storms. Third, although both storms caused some damage throughout the entire state, the damage was not distributed evenly. Finally, electric power to the state was restored over extended periods of time after the 2011 Storms. Therefore, some video service areas, or parts thereof, were restored more quickly than others, which affected the duration of the extended service interruptions and the amounts of the required credits and refunds. The Authority finds that the Certificate Holders were in substantial compliance with the credit and refund obligations of state law for qualifying outages that subscribers experienced as a result of both storms.50 The Department reminds all Certificate Holders that the only exception to the requirement that they provide credits or refunds to subscribers who experience qualifying outages is if the video service interruption was caused by the subscriber. The loss of commercial power is not justification for the Certificate Holders to decline or refuse to provide the required credits and refunds to subscribers experiencing qualifying video service outages. An impediment to ensuring that all subscribers who are entitled to credits or refunds is that subscribers must first notify their certificated video provider that they have experienced a qualifying outage. After the notification, Certificate Holders provide the credit or refund, normally applying it to the billing cycle after the subscriber provided the notification, with Comcast and MetroCast first verifying that the outage had occurred. Certificate Holders do not always automatically know which of their subscribers experience qualifying outages and do not generally provide credits or refunds unless subscribers take the first step and notify them. Because subscribers must take the first step to receive a credit or refund to which they are entitled, it is incumbent upon all Certificate Holders to be in compliance with the statutory requirement that at the time of initial subscription and annually thereafter, they provide subscribers with, among other information, a description of their credit policies.51 The description must include a prominent statement saying that, in the event of a video service outage lasting 24 or more consecutive hours, the affected subscriber must notify the company to receive a credit or refund. The notice must also include a statement regarding how many days after a qualifying outage a subscriber has to notify his or her video provider that such an interruption has been experienced. 50 The Authority notes that TVC initially indicated that it would not issue credits and refunds to subscribers whose video service was interrupted for 24 or more consecutive hours as a result of damage caused by Tropical Storm Irene. TVC Response to Question No. 3, Tropical Storm Irene Letter. By its December 11, 2011 response to the Authority’s November 16, 2011 letter, TVC indicated that it would provide credits and refunds, as required by statute. 51 For CVFA holders, the requirement is at Conn. Gen. Stat. Section 16-331j, and for CCFA holders, the requirement is at Conn. Gen. Stat. Section 16-331u.
  3. Page 109 of 125

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 13, 2026 EOE-383 Attachment 1 Page 109 of 125 Docket No. 11-09-09 Page 105 All Certificate Holders will be required to file with the Authority, a copy of the informational notices required by statute annually by July 1, beginning in 2013. L. GAS COMPANIES 1. Description of the Storms, Outages and Damage to Natural Gas Company Infrastructure. a. Tropical Storm Irene In preparation for Tropical Storm Irene, Southern Connecticut Gas Company (SCG), Connecticut Natural Gas Company (CNG), and Yankee Gas Services Company (Yankee or YGS; collectively, Natural Gas Companies) began discussions and meetings days prior to the storm in order to initiate precautionary measures. The Natural Gas Companies were in communication with the Authority’s Gas Pipeline Safety Unit (GPSU) as Tropical Storm Irene approached. The Natural Gas Companies kept the GPSU informed of their identified issues and their associated response throughout Storm Irene. Natural Gas Companies Responses to Interrogatory GPS-001. YGS Tropical Storm Irene preparation consisted of the following steps: Initiated system-wide conference calls several days prior to the storm to initiate and track precautionary measures being taken; Yankee's director of field operations participated in CL&P's storm preparation conference calls; Filled vehicles and equipment with fuel prior to the storm; Moved vehicles and equipment out of areas prone to flooding; Stored or secured equipment stored outside; Placed additional employees on-call; In some instances, provided on-call employees with hotel accommodations within the service territory to facilitate timely response to emergencies; Rented satellite phones for Pressure Management employees; Had service mechanics bring home company vehicles to ensure timely response to emergencies; and Staffed an ad hoc emergency operations center in Dispatch with Operations, Safety, management and support staff throughout the duration of the storm. YGS Response to Interrogatory GPS-001. CNG and SCG Storm Irene preparation consisted of the following steps: Gassing up all vehicles – service vans, crew trucks, fitter wagons, poor pressure truck, and backhoes at the main operations facility and satellite stations; SCG established a satellite location at its Trumbull LP facility; Prepared all pumps – check oil, fill with gas, gaskets in place, suction and discharge hoses; Prepared all generators – check oil, fill with gas, ground fault interrupters (GFIs), extension cords;
  4. Page 110 of 125

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 13, 2026 EOE-383 Attachment 1 Page 110 of 125 Docket No. 11-09-09 Page 106 Load tested all gate station emergency generators; Put additional technicians on-call with take home vehicles; Staffed Backup Gas Control Center; Added additional staffing at liquefied natural gas (LNG) plants; Filled storage bins to capacity – sand, stone, Wespro; Sand bags – how many in stock; Batteries – flashlights; Identified regulators with water problems; Pumped regulator vaults as necessary; Prepared drip list – ensure pumps are tested and ready; Inventory Hazardous-waste drums; Back filled all jobs in progress if possible and remove plates from the roadway; Reviewed Greenwich needs – equipment, personnel; Secured facility – pipe storage, loose materials stored outdoors, equipment; Backup communications – portables radios, cell phones, landlines; Personnel requirements; Procurement card assignments; and Implemented calling tree (order of escalation of calls and validation of all storm personnel phone numbers). CNG and SCG Responses to Interrogatory GPS-001. The natural gas systems in Connecticut fared very well before, during and after Tropical Storm Irene. Significant pre-planning on the part of the Natural Gas Companies, coupled with the fact that the majority of the natural gas infrastructure is buried, attributed to minimizing potential issues such as outages. Tropical Storm Irene resulted in a minimal number of gas outages. YGS had 428 customers whose natural gas service was interrupted. This is approximately 0.3% of YGS customers. Of those interruptions, 363 were due to a down electric line that damaged YGS gas distribution pipe (gas main) in Oxford, Connecticut. YGS customers were restored within four days. YGS Response to Interrogatory GPS-002. CNG had 252 customers whose service was turned off, mostly due to basement flooding in the Greenwich area. This is approximately 0.2% of CNG’s customers. The Greenwich gas customers were restored within 24 hours. CNG did not experience any customer outages in the greater Hartford area. CNG Responses to Interrogatory GPS-001 and GPS-002. SCG experienced interruption of gas service to 11 customers, mostly due to basement flooding. This is approximately 0.008% of SCG’s customers. SCG customers’ service was restored within four days. SCG Responses to Interrogatory GPS-002 and GPS-003. Most customers were restored with gas service as soon as the water levels receded and the customer’s gas systems were deemed safe for restoration. b. October Storm YGS is aware that snowstorms do not typically cause significant operational issues for natural gas companies. Accordingly, in preparation for the October Storm, YGS took normal precautionary measures for adverse weather conditions such as
  5. Page 111 of 125

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 13, 2026 EOE-383 Attachment 1 Page 111 of 125 Docket No. 11-09-09 Page 107 fueling vehicles and sharing a winter storm safety message with all employees. YGS pre-staged portable generators at the gate stations that were not equipped with automatic emergency generators in preparation for possible power outages. YGS Response to Interrogatory GPS-013. CNG and SCG October Storm preparations consisted of the same steps as those listed above for Tropical Storm Irene. CNG and SCG Responses to Interrogatory GPS-013. The Natural Gas Companies were in communication with the Authority’s GPSU as the October Storm approached and kept the GPSU informed of their identified issues and their associated responses throughout the storms. The October Storm caused only one gas outage. YGS had one customer whose gas service was interrupted due to minor flooding in Suffield, Connecticut. The customer’s gas service was restored in one day. 2. Emergency Response and Outage Restoration The Natural Gas Companies follow their Emergency Plans during an emergency event. The Emergency Plans provide written procedures to be followed during an event that requires immediate attention. The Emergency Plans procedures reduce the hazards to the public and minimizes the interruption of gas service to customers. The Natural Gas Companies have not experienced an outage of the magnitude that the electric utility companies experienced during the 2011 Storms. The Natural Gas Companies’ Emergency Plans do not adequately address the time it would take to restore gas customers after a large scale natural gas outage. The process of isolating each gas customer, purging the gas lines back in service, and then relighting each individual customer is extremely time consuming and should be reflected in each of the Natural Gas Companies’ Emergency Plans. Data examined from a 1989 outage of about 7,500 Torrington customers showed that one mechanic could isolate one customer per hour. The restoration process equated to about one customer restored per two hours per mechanic. YGS Late Filed Exhibit No. 036. Pursuant to Public Act 12-148, the Natural Gas Companies are required to submit copies of their updated Emergency Plans by July 1, 2012, to the Authority. Among other things, these updated Emergency Plans must include provisions for the Natural Gas Companies to respond to service outages affecting more than 10%, 30%, 50% and 70% of their customers. The Authority will review the Natural Gas Companies’ Emergency Plans and address any concerns in Docket 12-06-11. Throughout the 2011 Storms, many fueling stations were without electrical power which prevented them from being able to dispense fuel to vehicles. The Natural Gas Companies were affected by lack of available fuel in certain areas of the state during the October Storm. YGS stated that it had some difficulties obtaining gasoline in its East Windsor work area. Tr. 3/26/12, p. 592. CNG stated that during the October Storm it had some challenges obtaining gasoline in the Hartford area. Tr. 3/26/12, p. 596. The Natural Gas Companies did not have issues with providing diesel fuel to their equipment. The dispensing of diesel fuel is allowed to be performed through a process called “wet hosing.” Wet hosing is a process of fueling vehicles from tank trucks, where the tank trucks are driven to the yards or sites where the vehicles to be fueled are kept
  6. Page 112 of 125

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 13, 2026 EOE-383 Attachment 1 Page 112 of 125 Docket No. 11-09-09 Page 108 when they are not in use. This allowed the Natural Gas Companies to have their diesel equipment refueled on-site at their work center locations. Natural Gas Companies Responses to Interrogatory GPS-028. The Natural Gas Companies are continuing to evaluate additional locations to utilize temporary above ground fuel tanks for gasoline and options for fueling vehicles at municipally owned fueling stations within their service territories that have back up power supply. Id. The Authority will continue to monitor the Natural Gas Companies’ progress on this issue through an associated order. 3. Communication/Interfacing Municipalities with Customers, Utilities, and The Natural Gas Companies maintain communication with the GPSU in the event of an emergency or a gas incident. If there were a major incident the Natural Gas Companies are required to notify the GPSU of the event. YGS Response to Interrogatory GPS-009. During the 2011 Storms, the Natural Gas Companies were in contact with the GPSU on a daily basis. The Natural Gas Companies updated the GPSU on the status of outages and their restoration process along with any other issues with regard to maintaining gas service to their customers. The Natural Gas Companies did not receive any complaints from municipal officials regarding its communications during and after the 2011 Storms. Natural Gas Companies Responses to Interrogatory GPS-009. 4. External Assistance The Natural Gas Companies maintain a mutual aid agreement with the Northeast Gas Association (NGA), the American Gas Association (AGA), and the Southern Gas Association (SGA). In the event of a gas outage requiring personnel from the Northeast region, the Natural Gas Companies would have the ability to request assistance through the NGA Mutual Assistance Plan. The NGA Mutual Assistance Plan provides details as to what equipment can be provided and the number of personnel that would be available to assist. The NGA would coordinate the personnel, supplies and/or equipment from the member companies. The responsiveness of mutual assistance in nearby regions is a great benefit of the NGA. If additional personnel are needed from beyond the geographical reach of the northeast, a request would go to the SGA and/or the AGA. Natural Gas Companies Responses to Interrogatory GPS-027. 5. Loss of Electrical Power The Natural Gas Companies maintain communications with their gas distribution systems through a communication system called Supervisory Control and Data Acquisition (SCADA). SCADA is a computer-based system or systems that collects and displays information about a pipeline facility and may have the ability to send commands back to the pipeline facility. The Natural Gas Companies’ SCADA systems require electrical power and telecommunications capability in order to maintain monitoring and control capability of the gas distribution systems. The Natural Gas Companies lost electrical service to some of their gate stations and therefore lost communications to those sites. Many of the gate stations have automatic generators. Those that do not have automatic generators were supplied with portable generators.
  7. Page 113 of 125

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 13, 2026 EOE-383 Attachment 1 Page 113 of 125 Docket No. 11-09-09 Page 109 Many remotely monitored data points were without power, so the SCADA systems were not fully functional; however, in most areas the remaining functioning data points provided enough information for the Natural Gas Companies to adequately monitor their respective system’s integrity. In areas with insufficient data point information, the Natural Gas Companies dispatched personnel to monitor the systems until communications were restored. Natural Gas Companies Responses to Interrogatories GPS-005 and GPS-017. The use of fixed backup generators and portable generators met the needs of the Natural Gas Companies in order to maintain gas service and adequate monitoring of the gas distribution systems. Tr. 3/26/12, pp. 586 and 587. 6. Company Proposed Preparation and Restoration Improvement Initiatives The Natural Gas Companies’ facilities performed extremely well during the 2011 Storms. There was a minimal number of gas outages experienced. Despite this, the Natural Gas Companies conducted preparedness meetings and post-2011 Storm meetings to assess lessons learned. Lessons learned for SCG and CNG were to have multiple sources of communication and to have committed fuel suppliers for backup generators. SCG and CNG Response to Interrogatory GPS-010. In addition, SCG and CNG will be performing emergency drills in 2012 with limited communication ability and limited vehicle fueling options incorporated into the drill. SCG and CNG Response to Interrogatory GPS-022. YGS created a list of action items stemming from the 2011 Storms debriefing and lessons learned. YGS Response to Interrogatory GPS-022. The Authority expects the Natural Gas Companies to thoroughly review each of their lessons learned and to enact changes as necessary. Through associated orders, the Authority will therefore require the submission of a report on the status of each of the lessons learned and action items discussed in the Natural Gas Companies Responses to Interrogatories GPS-010 and GPS-022. The report should be a brief discussion as to what was done to close the action item or what is being done to address the concern. M. WATER COMPANIES The Authority regulates nine Class A water companies (Companies)52 and they all participated in this case with the submission of interrogatory responses and providing testimony in the hearing held on March 26, 2012. As a whole, the Companies performed very well in terms of their ability to limit service interruptions in number and duration. United and Heritage were the only two companies to experience outages. The outages represent six tenths of one percent of the total customer base of the nine companies. While there were some problems that could have been handled differently, their overall ability to provide service following the 2011 Storms can be attributed primarily to the effectiveness of the Standby Power Regulations for Water Companies (Regulations) Sections 16-11-99 through 16-11-99d of the Conn. Agencies Regs. The overwhelming cause of service interruptions was a 52 Aquarion Water Company of Connecticut (Aquarion), Avon Water Company (Avon), Connecticut Water Company (CWC), Hazardville Water Company (Hazardville), Heritage Village Water Company (Heritage), Jewett City Water Company (Jewett City), Torrington Water Company (Torrington), United Water Connecticut (United), Valley Water Systems Inc. (Valley)
  8. Page 114 of 125

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 13, 2026 EOE-383 Attachment 1 Page 114 of 125 Docket No. 11-09-09 Page 110 direct or indirect result of the loss of commercial power from the EDCs. The Connecticut Water Company (CWC) summarized what worked for most of the companies with the statement, “the advance preparation, emergency response planning, availability of standby power, interconnections, operational flexibility, considerable internal coordination, and sharing of staff and resources within the company made this possible.” CWC Response to Interrogatory WA-1. 1. Regulations of Connecticut State Agencies Section 16-11-99 a. Components of the Regulations The following are excerpts from the Regulations that describe the key components that had a direct impact on the water companies’ ability to provide continuous supplies of water during and immediately following the 2011 Storms. Each company shall provide permanently installed gasoline, propanefueled, natural gas or oil-fired standby power equipment at such facility locations as are necessary to provide sufficient standby power capacity. "Sufficient Standby Power Capacity" shall mean the ability of a company to supply 100% of the average daily demand of its system, or of each division if the company's system is comprised of multiple divisions. "Average Daily Demand" (ADD) shall mean the normal water usage of the system as determined for the most representative twenty-four (24) hour period of record. Portable generators with sufficient standby power capacity may be considered acceptable as an alternative to an on-site generator. Such portable generators may be used only if there are suitable controls, connections and manual or automatic switches in the pumphouse. Portable generators shall be owned or leased at all times by the company, by a subsidiary of the company, by the parent of the company, or by a corporation with the same parent as the company. Portable generators must be ready to provide power within four hours of an electrical outage, unless the company has sufficient atmospheric storage, for up to twenty-four hours without electric power, but in no event shall standby power not be provided more than twenty-four hours after the occurrence of an electrical outage. Sufficient fuel storage capacity shall be provided for the generation of
  9. Page 115 of 125

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 13, 2026 EOE-383 Attachment 1 Page 115 of 125 Docket No. 11-09-09 Page 111 standby power by permanently installed standby power equipment for at least twenty-four (24) hours, and by portable generators for at least eight (8) hours. Each company shall test standby power equipment. Each company shall perform maintenance of its standby power equipment 2. Storm Preparation Aquarion, CWC, Torrington, and Jewett City conducted pre-storm inspections of key components of their systems such as river crossings, dams and valve locations. Tr. 3/26/12, pp. 678-681. While larger facilities can have sufficient fuel storage for five to seven days of continuous operation, the 2011 Storms’ unprecedented impact on commercial power made refueling in nearly all instances a necessity. Accessibility was just as hard for the fuel companies and the water companies had to monitor their fuel resources to be sure deliveries were made. Id., p. 684. Some water company staff was responsible to deliver gasoline in cans and there were cases of company personnel needing to travel great distances to find gas. Id., pp. 713 and 714. CWC testified that its ability to have qualified staff on hand to ensure that its facilities were monitored and to notify customers, was critical in its ability to deliver water. Id., p. 715. The CWC witness also suggested that operational flexibility was key to meeting supply requirements. Such flexibility was in the areas of customary and planned operational changes and staffing. 3. Communications a. Inability to Communicate with the EDCs Every company experienced difficulty communicating with its EDC. Id., pp. 714719. There was only one instance, testified to by Aquarion, that had satisfactory results. Id., p. 660. In that instance, UI responded to a location in Stratford in a timely fashion to de-energize a line that allowed access for a generator to be refueled. There was no other favorable report made. Any level of a working relationship between the companies and the EDCs prior to the 2011 Storms was not apparent at the time of the 2011 Storms. Most of the Companies testified to having had some level of a historic working relationship with a representative of the EDC in any given region of its service territory. Id., pp. 714-719. The general consensus was that all the established working relationships developed over, in some instances, years, were for naught. Id., pp. 716720. CWC reported a lessons learned exercise with CL&P, post Tropical Storm Irene, that was expected to provide for a free flow of information between companies. Following the October Storm, that free flow of information did not work, as the information was jumbled and not always accurate. Id., p. 716. The companies testified that they prefer timely and accurate information which they could then rely on and plan around rather than the misinformation and inconsistent reporting that occurred following the 2011 Storms. Id., p. 736.
  10. Page 116 of 125

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 13, 2026 EOE-383 Attachment 1 Page 116 of 125 Docket No. 11-09-09 Page 112 The following excerpts from the transcript illustrate the problems the companies experienced in trying to communicate with CL&P: (Heritage) “So we would just like to talk to someone so that they know that, number one, they know that we have a problem; number two, we would want them to know that we're one customer, but by not taking care of us, you've got 600 customers that are going to be without water very shortly if you don't something, that type of thing. And unfortunately, we don't get to talk to anyone about it. And the information when we did talk to someone, the information we got was totally bogus. Yeah, we'll be there by the end of the day, and the end of the day came and the next day came and the next day came. It's like, you know, let us know exactly what's going on so we can do what we have to do accordingly. Don't give us bogus information that doesn't help our situation. So it was very frustrating.” Tr. 3/26/12, pp. 717 and 718. (Hazardville/Jewett City) “We usually have a liaison or a contact, but that seems to always change whenever you need it, that number doesn't work or the contact is not there or it's a different person.” Tr. 3/26/12, p. 718. (United) “We contacted CL&P by phone numerous times. We went to their locations on numerous times to try to get answers, and we were unsuccessful. I felt that we were getting pushed aside. We just wanted to know what they were doing, because we could work together. We weren't even successful in that.” Tr. 3/26/12, p. 736. Based on the evidence in the record, and the difficulty the water companies experienced in trying to obtain accurate and needed communication from CL&P during the outages, the Authority determines that CL&P’s communication with these service providers was less than suitable and adequate. b. Wireless Communications It was nearly unanimous that cellular phones were the primary means of communication within the companies. Id., pp. 97 and 98. Valley primarily used 2-way radio and others had pagers for back-up purposes. Id., p. 95. There were no complaints with Verizon and few with Sprint. However, some of the companies complained about AT&T Mobility. Id., pp. 696 and 697. The inability to communicate by cell phone while in remote locations made it necessary for company personnel to meet at strategic locations to discuss recovery operations. United Response to Interrogatory EN-11. 4. Company Deficiencies and areas of Concern for the Authority a. Insufficient Generation and Appurtenances Avon and United were in a situation where their usual number of portable generators was insufficient, even when rotation of the units between facilities was

Text of EOE-383 Attachment 2.pdf

Extracted from the file · 182 pages · 461,233 characters

Text of EOE-383 Attachment 3.pdf

Extracted from the file · 55 pages · 132,814 characters

Text of EOE-383 Attachment 4.pdf

Extracted from the file · 2 pages · 4,635 characters

Text of EOE-383 Attachment 5.pdf

Extracted from the file · 7 pages · 11,175 characters

As listed on the current system

Question(s) Answered 379, 380, 381, 382, 383 (Connecticut Light and Power Company dba Eversource Energy) Date Filed: 10/27/2026