Skip to main content

A prototype public docket site for the Connecticut Public Utilities Regulatory Authority

Utility Dockets and Filings

Interrogatory responses

Answers to questions 379, 380, 381, 382, 383

ResponseFiled by Connecticut Light and Power Company dba Eversource Energy11 files
Part of docket 26-05-10Open
  • Electric
Application of The Connecticut Light and Power Company d/b/a Eversource Energy to Amend its Rate Schedules

Files11

Search terms highlighted
Eversource rate increase is on 18 pages across 3 files of the text below, highlighted. Go to the first matchClear highlighting
Words on different pages
Words on different pages
Words on different pages

Text of EOE-381_Final.pdf

Extracted from the file · 2 pages · 3,490 characters

Words on different pagesRead the text of EOE-381_Final.pdf

Text of EOE-382_Final.pdf

Extracted from the file · 1 page · 2,648 characters

Words on different pagesRead the text of EOE-382_Final.pdf

Text of EOE-383_Final.pdf

Extracted from the file · 4 pages · 10,383 characters

Words on different pagesRead the text of EOE-383_Final.pdf
6 pages match
  1. Page 109 of 125

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 13, 2026 EOE-383 Attachment 1 Page 109 of 125 Docket No. 11-09-09 Page 105 All Certificate Holders will be required to file with the Authority, a copy of the informational notices required by statute annually by July 1, beginning in 2013. L. GAS COMPANIES 1. Description of the Storms, Outages and Damage to Natural Gas Company Infrastructure. a. Tropical Storm Irene In preparation for Tropical Storm Irene, Southern Connecticut Gas Company (SCG), Connecticut Natural Gas Company (CNG), and Yankee Gas Services Company (Yankee or YGS; collectively, Natural Gas Companies) began discussions and meetings days prior to the storm in order to initiate precautionary measures. The Natural Gas Companies were in communication with the Authority’s Gas Pipeline Safety Unit (GPSU) as Tropical Storm Irene approached. The Natural Gas Companies kept the GPSU informed of their identified issues and their associated response throughout Storm Irene. Natural Gas Companies Responses to Interrogatory GPS-001. YGS Tropical Storm Irene preparation consisted of the following steps: Initiated system-wide conference calls several days prior to the storm to initiate and track precautionary measures being taken; Yankee's director of field operations participated in CL&P's storm preparation conference calls; Filled vehicles and equipment with fuel prior to the storm; Moved vehicles and equipment out of areas prone to flooding; Stored or secured equipment stored outside; Placed additional employees on-call; In some instances, provided on-call employees with hotel accommodations within the service territory to facilitate timely response to emergencies; Rented satellite phones for Pressure Management employees; Had service mechanics bring home company vehicles to ensure timely response to emergencies; and Staffed an ad hoc emergency operations center in Dispatch with Operations, Safety, management and support staff throughout the duration of the storm. YGS Response to Interrogatory GPS-001. CNG and SCG Storm Irene preparation consisted of the following steps: Gassing up all vehicles – service vans, crew trucks, fitter wagons, poor pressure truck, and backhoes at the main operations facility and satellite stations; SCG established a satellite location at its Trumbull LP facility; Prepared all pumps – check oil, fill with gas, gaskets in place, suction and discharge hoses; Prepared all generators – check oil, fill with gas, ground fault interrupters (GFIs), extension cords;
  2. Page 110 of 125

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 13, 2026 EOE-383 Attachment 1 Page 110 of 125 Docket No. 11-09-09 Page 106 Load tested all gate station emergency generators; Put additional technicians on-call with take home vehicles; Staffed Backup Gas Control Center; Added additional staffing at liquefied natural gas (LNG) plants; Filled storage bins to capacity – sand, stone, Wespro; Sand bags – how many in stock; Batteries – flashlights; Identified regulators with water problems; Pumped regulator vaults as necessary; Prepared drip list – ensure pumps are tested and ready; Inventory Hazardous-waste drums; Back filled all jobs in progress if possible and remove plates from the roadway; Reviewed Greenwich needs – equipment, personnel; Secured facility – pipe storage, loose materials stored outdoors, equipment; Backup communications – portables radios, cell phones, landlines; Personnel requirements; Procurement card assignments; and Implemented calling tree (order of escalation of calls and validation of all storm personnel phone numbers). CNG and SCG Responses to Interrogatory GPS-001. The natural gas systems in Connecticut fared very well before, during and after Tropical Storm Irene. Significant pre-planning on the part of the Natural Gas Companies, coupled with the fact that the majority of the natural gas infrastructure is buried, attributed to minimizing potential issues such as outages. Tropical Storm Irene resulted in a minimal number of gas outages. YGS had 428 customers whose natural gas service was interrupted. This is approximately 0.3% of YGS customers. Of those interruptions, 363 were due to a down electric line that damaged YGS gas distribution pipe (gas main) in Oxford, Connecticut. YGS customers were restored within four days. YGS Response to Interrogatory GPS-002. CNG had 252 customers whose service was turned off, mostly due to basement flooding in the Greenwich area. This is approximately 0.2% of CNG’s customers. The Greenwich gas customers were restored within 24 hours. CNG did not experience any customer outages in the greater Hartford area. CNG Responses to Interrogatory GPS-001 and GPS-002. SCG experienced interruption of gas service to 11 customers, mostly due to basement flooding. This is approximately 0.008% of SCG’s customers. SCG customers’ service was restored within four days. SCG Responses to Interrogatory GPS-002 and GPS-003. Most customers were restored with gas service as soon as the water levels receded and the customer’s gas systems were deemed safe for restoration. b. October Storm YGS is aware that snowstorms do not typically cause significant operational issues for natural gas companies. Accordingly, in preparation for the October Storm, YGS took normal precautionary measures for adverse weather conditions such as
  3. Page 111 of 125

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 13, 2026 EOE-383 Attachment 1 Page 111 of 125 Docket No. 11-09-09 Page 107 fueling vehicles and sharing a winter storm safety message with all employees. YGS pre-staged portable generators at the gate stations that were not equipped with automatic emergency generators in preparation for possible power outages. YGS Response to Interrogatory GPS-013. CNG and SCG October Storm preparations consisted of the same steps as those listed above for Tropical Storm Irene. CNG and SCG Responses to Interrogatory GPS-013. The Natural Gas Companies were in communication with the Authority’s GPSU as the October Storm approached and kept the GPSU informed of their identified issues and their associated responses throughout the storms. The October Storm caused only one gas outage. YGS had one customer whose gas service was interrupted due to minor flooding in Suffield, Connecticut. The customer’s gas service was restored in one day. 2. Emergency Response and Outage Restoration The Natural Gas Companies follow their Emergency Plans during an emergency event. The Emergency Plans provide written procedures to be followed during an event that requires immediate attention. The Emergency Plans procedures reduce the hazards to the public and minimizes the interruption of gas service to customers. The Natural Gas Companies have not experienced an outage of the magnitude that the electric utility companies experienced during the 2011 Storms. The Natural Gas Companies’ Emergency Plans do not adequately address the time it would take to restore gas customers after a large scale natural gas outage. The process of isolating each gas customer, purging the gas lines back in service, and then relighting each individual customer is extremely time consuming and should be reflected in each of the Natural Gas Companies’ Emergency Plans. Data examined from a 1989 outage of about 7,500 Torrington customers showed that one mechanic could isolate one customer per hour. The restoration process equated to about one customer restored per two hours per mechanic. YGS Late Filed Exhibit No. 036. Pursuant to Public Act 12-148, the Natural Gas Companies are required to submit copies of their updated Emergency Plans by July 1, 2012, to the Authority. Among other things, these updated Emergency Plans must include provisions for the Natural Gas Companies to respond to service outages affecting more than 10%, 30%, 50% and 70% of their customers. The Authority will review the Natural Gas Companies’ Emergency Plans and address any concerns in Docket 12-06-11. Throughout the 2011 Storms, many fueling stations were without electrical power which prevented them from being able to dispense fuel to vehicles. The Natural Gas Companies were affected by lack of available fuel in certain areas of the state during the October Storm. YGS stated that it had some difficulties obtaining gasoline in its East Windsor work area. Tr. 3/26/12, p. 592. CNG stated that during the October Storm it had some challenges obtaining gasoline in the Hartford area. Tr. 3/26/12, p. 596. The Natural Gas Companies did not have issues with providing diesel fuel to their equipment. The dispensing of diesel fuel is allowed to be performed through a process called “wet hosing.” Wet hosing is a process of fueling vehicles from tank trucks, where the tank trucks are driven to the yards or sites where the vehicles to be fueled are kept
  4. Page 112 of 125

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 13, 2026 EOE-383 Attachment 1 Page 112 of 125 Docket No. 11-09-09 Page 108 when they are not in use. This allowed the Natural Gas Companies to have their diesel equipment refueled on-site at their work center locations. Natural Gas Companies Responses to Interrogatory GPS-028. The Natural Gas Companies are continuing to evaluate additional locations to utilize temporary above ground fuel tanks for gasoline and options for fueling vehicles at municipally owned fueling stations within their service territories that have back up power supply. Id. The Authority will continue to monitor the Natural Gas Companies’ progress on this issue through an associated order. 3. Communication/Interfacing Municipalities with Customers, Utilities, and The Natural Gas Companies maintain communication with the GPSU in the event of an emergency or a gas incident. If there were a major incident the Natural Gas Companies are required to notify the GPSU of the event. YGS Response to Interrogatory GPS-009. During the 2011 Storms, the Natural Gas Companies were in contact with the GPSU on a daily basis. The Natural Gas Companies updated the GPSU on the status of outages and their restoration process along with any other issues with regard to maintaining gas service to their customers. The Natural Gas Companies did not receive any complaints from municipal officials regarding its communications during and after the 2011 Storms. Natural Gas Companies Responses to Interrogatory GPS-009. 4. External Assistance The Natural Gas Companies maintain a mutual aid agreement with the Northeast Gas Association (NGA), the American Gas Association (AGA), and the Southern Gas Association (SGA). In the event of a gas outage requiring personnel from the Northeast region, the Natural Gas Companies would have the ability to request assistance through the NGA Mutual Assistance Plan. The NGA Mutual Assistance Plan provides details as to what equipment can be provided and the number of personnel that would be available to assist. The NGA would coordinate the personnel, supplies and/or equipment from the member companies. The responsiveness of mutual assistance in nearby regions is a great benefit of the NGA. If additional personnel are needed from beyond the geographical reach of the northeast, a request would go to the SGA and/or the AGA. Natural Gas Companies Responses to Interrogatory GPS-027. 5. Loss of Electrical Power The Natural Gas Companies maintain communications with their gas distribution systems through a communication system called Supervisory Control and Data Acquisition (SCADA). SCADA is a computer-based system or systems that collects and displays information about a pipeline facility and may have the ability to send commands back to the pipeline facility. The Natural Gas Companies’ SCADA systems require electrical power and telecommunications capability in order to maintain monitoring and control capability of the gas distribution systems. The Natural Gas Companies lost electrical service to some of their gate stations and therefore lost communications to those sites. Many of the gate stations have automatic generators. Those that do not have automatic generators were supplied with portable generators.
  5. Page 113 of 125

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 13, 2026 EOE-383 Attachment 1 Page 113 of 125 Docket No. 11-09-09 Page 109 Many remotely monitored data points were without power, so the SCADA systems were not fully functional; however, in most areas the remaining functioning data points provided enough information for the Natural Gas Companies to adequately monitor their respective system’s integrity. In areas with insufficient data point information, the Natural Gas Companies dispatched personnel to monitor the systems until communications were restored. Natural Gas Companies Responses to Interrogatories GPS-005 and GPS-017. The use of fixed backup generators and portable generators met the needs of the Natural Gas Companies in order to maintain gas service and adequate monitoring of the gas distribution systems. Tr. 3/26/12, pp. 586 and 587. 6. Company Proposed Preparation and Restoration Improvement Initiatives The Natural Gas Companies’ facilities performed extremely well during the 2011 Storms. There was a minimal number of gas outages experienced. Despite this, the Natural Gas Companies conducted preparedness meetings and post-2011 Storm meetings to assess lessons learned. Lessons learned for SCG and CNG were to have multiple sources of communication and to have committed fuel suppliers for backup generators. SCG and CNG Response to Interrogatory GPS-010. In addition, SCG and CNG will be performing emergency drills in 2012 with limited communication ability and limited vehicle fueling options incorporated into the drill. SCG and CNG Response to Interrogatory GPS-022. YGS created a list of action items stemming from the 2011 Storms debriefing and lessons learned. YGS Response to Interrogatory GPS-022. The Authority expects the Natural Gas Companies to thoroughly review each of their lessons learned and to enact changes as necessary. Through associated orders, the Authority will therefore require the submission of a report on the status of each of the lessons learned and action items discussed in the Natural Gas Companies Responses to Interrogatories GPS-010 and GPS-022. The report should be a brief discussion as to what was done to close the action item or what is being done to address the concern. M. WATER COMPANIES The Authority regulates nine Class A water companies (Companies)52 and they all participated in this case with the submission of interrogatory responses and providing testimony in the hearing held on March 26, 2012. As a whole, the Companies performed very well in terms of their ability to limit service interruptions in number and duration. United and Heritage were the only two companies to experience outages. The outages represent six tenths of one percent of the total customer base of the nine companies. While there were some problems that could have been handled differently, their overall ability to provide service following the 2011 Storms can be attributed primarily to the effectiveness of the Standby Power Regulations for Water Companies (Regulations) Sections 16-11-99 through 16-11-99d of the Conn. Agencies Regs. The overwhelming cause of service interruptions was a 52 Aquarion Water Company of Connecticut (Aquarion), Avon Water Company (Avon), Connecticut Water Company (CWC), Hazardville Water Company (Hazardville), Heritage Village Water Company (Heritage), Jewett City Water Company (Jewett City), Torrington Water Company (Torrington), United Water Connecticut (United), Valley Water Systems Inc. (Valley)
  6. Page 114 of 125

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 13, 2026 EOE-383 Attachment 1 Page 114 of 125 Docket No. 11-09-09 Page 110 direct or indirect result of the loss of commercial power from the EDCs. The Connecticut Water Company (CWC) summarized what worked for most of the companies with the statement, “the advance preparation, emergency response planning, availability of standby power, interconnections, operational flexibility, considerable internal coordination, and sharing of staff and resources within the company made this possible.” CWC Response to Interrogatory WA-1. 1. Regulations of Connecticut State Agencies Section 16-11-99 a. Components of the Regulations The following are excerpts from the Regulations that describe the key components that had a direct impact on the water companies’ ability to provide continuous supplies of water during and immediately following the 2011 Storms. Each company shall provide permanently installed gasoline, propanefueled, natural gas or oil-fired standby power equipment at such facility locations as are necessary to provide sufficient standby power capacity. "Sufficient Standby Power Capacity" shall mean the ability of a company to supply 100% of the average daily demand of its system, or of each division if the company's system is comprised of multiple divisions. "Average Daily Demand" (ADD) shall mean the normal water usage of the system as determined for the most representative twenty-four (24) hour period of record. Portable generators with sufficient standby power capacity may be considered acceptable as an alternative to an on-site generator. Such portable generators may be used only if there are suitable controls, connections and manual or automatic switches in the pumphouse. Portable generators shall be owned or leased at all times by the company, by a subsidiary of the company, by the parent of the company, or by a corporation with the same parent as the company. Portable generators must be ready to provide power within four hours of an electrical outage, unless the company has sufficient atmospheric storage, for up to twenty-four hours without electric power, but in no event shall standby power not be provided more than twenty-four hours after the occurrence of an electrical outage. Sufficient fuel storage capacity shall be provided for the generation of
  7. Page 115 of 125

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 13, 2026 EOE-383 Attachment 1 Page 115 of 125 Docket No. 11-09-09 Page 111 standby power by permanently installed standby power equipment for at least twenty-four (24) hours, and by portable generators for at least eight (8) hours. Each company shall test standby power equipment. Each company shall perform maintenance of its standby power equipment 2. Storm Preparation Aquarion, CWC, Torrington, and Jewett City conducted pre-storm inspections of key components of their systems such as river crossings, dams and valve locations. Tr. 3/26/12, pp. 678-681. While larger facilities can have sufficient fuel storage for five to seven days of continuous operation, the 2011 Storms’ unprecedented impact on commercial power made refueling in nearly all instances a necessity. Accessibility was just as hard for the fuel companies and the water companies had to monitor their fuel resources to be sure deliveries were made. Id., p. 684. Some water company staff was responsible to deliver gasoline in cans and there were cases of company personnel needing to travel great distances to find gas. Id., pp. 713 and 714. CWC testified that its ability to have qualified staff on hand to ensure that its facilities were monitored and to notify customers, was critical in its ability to deliver water. Id., p. 715. The CWC witness also suggested that operational flexibility was key to meeting supply requirements. Such flexibility was in the areas of customary and planned operational changes and staffing. 3. Communications a. Inability to Communicate with the EDCs Every company experienced difficulty communicating with its EDC. Id., pp. 714719. There was only one instance, testified to by Aquarion, that had satisfactory results. Id., p. 660. In that instance, UI responded to a location in Stratford in a timely fashion to de-energize a line that allowed access for a generator to be refueled. There was no other favorable report made. Any level of a working relationship between the companies and the EDCs prior to the 2011 Storms was not apparent at the time of the 2011 Storms. Most of the Companies testified to having had some level of a historic working relationship with a representative of the EDC in any given region of its service territory. Id., pp. 714-719. The general consensus was that all the established working relationships developed over, in some instances, years, were for naught. Id., pp. 716720. CWC reported a lessons learned exercise with CL&P, post Tropical Storm Irene, that was expected to provide for a free flow of information between companies. Following the October Storm, that free flow of information did not work, as the information was jumbled and not always accurate. Id., p. 716. The companies testified that they prefer timely and accurate information which they could then rely on and plan around rather than the misinformation and inconsistent reporting that occurred following the 2011 Storms. Id., p. 736.
  8. Page 116 of 125

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 13, 2026 EOE-383 Attachment 1 Page 116 of 125 Docket No. 11-09-09 Page 112 The following excerpts from the transcript illustrate the problems the companies experienced in trying to communicate with CL&P: (Heritage) “So we would just like to talk to someone so that they know that, number one, they know that we have a problem; number two, we would want them to know that we're one customer, but by not taking care of us, you've got 600 customers that are going to be without water very shortly if you don't something, that type of thing. And unfortunately, we don't get to talk to anyone about it. And the information when we did talk to someone, the information we got was totally bogus. Yeah, we'll be there by the end of the day, and the end of the day came and the next day came and the next day came. It's like, you know, let us know exactly what's going on so we can do what we have to do accordingly. Don't give us bogus information that doesn't help our situation. So it was very frustrating.” Tr. 3/26/12, pp. 717 and 718. (Hazardville/Jewett City) “We usually have a liaison or a contact, but that seems to always change whenever you need it, that number doesn't work or the contact is not there or it's a different person.” Tr. 3/26/12, p. 718. (United) “We contacted CL&P by phone numerous times. We went to their locations on numerous times to try to get answers, and we were unsuccessful. I felt that we were getting pushed aside. We just wanted to know what they were doing, because we could work together. We weren't even successful in that.” Tr. 3/26/12, p. 736. Based on the evidence in the record, and the difficulty the water companies experienced in trying to obtain accurate and needed communication from CL&P during the outages, the Authority determines that CL&P’s communication with these service providers was less than suitable and adequate. b. Wireless Communications It was nearly unanimous that cellular phones were the primary means of communication within the companies. Id., pp. 97 and 98. Valley primarily used 2-way radio and others had pagers for back-up purposes. Id., p. 95. There were no complaints with Verizon and few with Sprint. However, some of the companies complained about AT&T Mobility. Id., pp. 696 and 697. The inability to communicate by cell phone while in remote locations made it necessary for company personnel to meet at strategic locations to discuss recovery operations. United Response to Interrogatory EN-11. 4. Company Deficiencies and areas of Concern for the Authority a. Insufficient Generation and Appurtenances Avon and United were in a situation where their usual number of portable generators was insufficient, even when rotation of the units between facilities was
  9. Page 117 of 125

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 13, 2026 EOE-383 Attachment 1 Page 117 of 125 Docket No. 11-09-09 Page 113 effective in prior outage situations. Id., p. 652. Access to the generators was hindered due to down lines and/or trees making relocation of them nearly impossible. The magnitude of the 2011 Storms also increased the demand for generation units where they would have normally been available through affiliated companies. Some companies learned a lesson from Tropical Storm Irene and by the time of the October Storm, they were prepared. United was generally harder hit by the October Storm, and coupled with not having made changes as a result of Tropical Storm Irene, had a very difficult time with their operations. Additionally, provisions of appurtenances, such as not having a receptacle and a run-through switch at a particular location made it difficult to use a generator. Id., pp. 656, 658. The Authority finds this to be a result of lack of planning. The Regulations call for proper controls and connections to be in place prior to a power outage event. United believes that it could have at its disposal sufficient portable generation to supply the needs of most but not all, of its satellite operations. Id., p. 52. This would have worked historically, as the sharing of generation was for shorter durations overall and access was not nearly as difficult. The Regulations require companies to supply the Average Daily Demand to all facilities all of the time. Following the 2011 Storms, United purchased two new generators, conducted a lessons-learned exercise and planned a mock drill. Id., p. 724. b. Use of Outside Electrical Contractor Hazardville/Jewett City hired an outside electrical company to identify downed energized lines in its service area. Those found to be de-energized (at that moment), were moved to allow access to its facilities. Id., p. 14. The companies should be cautioned that although a line is de-energized at one moment, does not necessarily mean it will forever be de-energized, even as it is lying on the ground. There are many reasons why and how a line can be energized, even when it was found to be deenergized moments earlier. c. Personnel Safety - Dams CWC testified that staff was monitoring the dams throughout the 2011 Storm and it was a problem having staff on the dams during the storm.” Id., p. 80. The Authority finds this practice to be dangerous. The Authority is aware that Dam Emergency Operations Plans identify the steps that must be taken to monitor these structures. The Companies should make safety of personnel a priority and should consider alternatives to on-site staffing that streaming video and wireless technologies can bring. 5. Planning for the future a. Permanent Versus Portable Generation With some of the difficulties encountered by the companies with portable generation equipment availability and transport, permanent generation should be considered for more facilities. Each company should make an assessment of the possibility that the company, and its customers, would benefit from permanent versus portable generation at any given site. There were instances where a portable generator
  10. Page 118 of 125

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Date Issued October 13, 2026 EOE-383 Attachment 1 Page 118 of 125 Docket No. 11-09-09 Page 114 was needed, while a permanent unit was down for maintenance or repair. Id., p. 666. This is a rare occurrence; however, Companies should be thinking in terms of redundancy for the future. b. SCADA and Remote Operations The continuous communication with remote facilities through SCADA was critical to effective operations. Id., pp. 665-667. The system provides, for example, signals from pump stations and wells for startup, shut down, low and high level alarms. The loss of land-line connections to those facilities emphasizes the importance of continuous communication and many companies are now considering radio controlled communications for the future. The loss of remote communications required the scheduled visits by onsite personnel in some instances around the clock. This also required companies to revert back to automatic controls. Id., p. 70. Typically SCADA uses telephone lines for communication. With the significant numbers of down lines, communications to facilities via SCADA was lost that subsequently required manned operations, which further tasked the busy manpower. Id., pp. 672 and 673. Those companies with radio controlled SCADA retained their effectiveness and all companies using SCADA should consider radio control communication for the future. Id., p. 24. c. Fuel Availability and Proposed Law There is great interest in a fuel availability law. It was strongly recommended by the Companies that legislation be established to prioritize local supplies of gasoline to public utility companies, among other similarly impacted entities. Id., pp. 713 and 714. The companies are encouraged to propose legislation addressing fuel availability during the next legislative session. The Companies should also evaluate additional options such as utilizing temporary above ground fuel tanks for gasoline and fueling their vehicles at municipally owned fueling stations within their service territories that have back up power supply. IV. CONCLUSION AND ORDERS A. CONCLUSION The Authority concludes that CL&P’s performance in the aftermath of the 2011 Storms was deficient and inadequate in the areas of outage and service restoration preparation of personnel, support of its municipal liaison program, development and communication of restoration times to customers, and overall communication to customers, other service providers and municipalities, as to warrant regulatory sanction. The Authority also concludes that because of CL&P’s failure to obtain adequate assistance in advance of the October Storm, its response to that storm was deficient. The Authority establishes a rebuttable presumption that CL&P should be imposed an appropriate reduction to its allowed return on equity in its next ratemaking proceeding as a penalty for poor management performance and to provide incentives for improvement. In addition, in conformance with the Settlement Agreement between NU and NSTAR, the Authority retains further jurisdictional approval for recovery of an

Text of EOE-383 Attachment 2.pdf

Extracted from the file · 182 pages · 461,233 characters

Text of EOE-383 Attachment 3.pdf

Extracted from the file · 55 pages · 132,814 characters

Text of EOE-383 Attachment 4.pdf

Extracted from the file · 2 pages · 4,635 characters

Text of EOE-383 Attachment 5.pdf

Extracted from the file · 7 pages · 11,175 characters

As listed on the current system

Question(s) Answered 379, 380, 381, 382, 383 (Connecticut Light and Power Company dba Eversource Energy) Date Filed: 10/27/2026

This filing on the current system (opens in a new tab)